SIGNIFICANT
by IND DEVELOPERS · Wadala, NashikAlso near Indira Nagar, Trimurti Chowk
Possession date of SIGNIFICANT: 19 November 2026, moved from 30 June 2025 (17 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600027892, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SIGNIFICANT?
How the possession date of SIGNIFICANT has moved
30 June 2025
Completion date given when the project was registered
19 November 2026
Extended at the builder's request (MahaRERA application EA20082622264)
Reason the builder gave MahaRERA:
“The project has been completed, and the extension is being sought to facilitate necessary corrections and updates in the application. Upon completion of the required corrections, the application will be updated accordingly, following which…” Read the full reason
“The project has been completed, and the extension is being sought to facilitate necessary corrections and updates in the application. Upon completion of the required corrections, the application will be updated accordingly, following which the completion update will be submitted”
Source: SIGNIFICANT’s extension records on MahaRERA (P51600027892), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SIGNIFICANT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600027892
- Status
- Registered and active
- Builder
- IND DEVELOPERS
- Location
- Wadala, Nashik · 422006
- Project type
- Residential / Group Housing
- Registered on
- 14 Jan 2021
- Completion date at registration
- June 2025
- Latest completion date
- November 2026
- Delay so far
- 17 months
- Homes
- 266
- Sold or booked
- 56%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of SIGNIFICANT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SIGNIFICANT | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- SIGNIFICANT: covers 9 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SIGNIFICANT every month.
SIGNIFICANT: buildings, flats and land, as filed on MahaRERA
- Buildings: SIGNIFICANT (9 floors, 266 units)
- Car parking: 100 covered
- Land: 7,600 sq m (about 1.9 acres) · sanctioned built-up 10,810 sq m · recreational space 760 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
IND Developers has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 10 months late). No complaints on MahaRERA.
Read Google reviews of SIGNIFICANT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SIGNIFICANT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SIGNIFICANT
What is the possession date of SIGNIFICANT?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SIGNIFICANT in Wadala, Nashik is 19 November 2026 — 17 months later than 30 June 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SIGNIFICANT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SIGNIFICANT's builder has filed on MahaRERA, the official one, is 19 November 2026, already 17 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SIGNIFICANT extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SIGNIFICANT's builder applied to MahaRERA to extend the completion date once: to 19 November 2026, giving the reason "The project has been completed, and the extension is being sought to facilitate necessary corrections and updates in the application. Upon completion of the required corrections, the application will be updated accordingly, following which the completion update will be submitted".
What is the RERA number of SIGNIFICANT?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SIGNIFICANT in Wadala, Nashik is P51600027892.
Is SIGNIFICANT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SIGNIFICANT is registered as P51600027892 and its status is "Registered and active".
What is the construction status of SIGNIFICANT?
According to GharKundli's check of MahaRERA records (updated October 2026), SIGNIFICANT's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SIGNIFICANT is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SIGNIFICANT have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SIGNIFICANT safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SIGNIFICANT is registered on MahaRERA as P51600027892, its completion date has moved 17 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SIGNIFICANT's possession date changes?
The latest dates are on SIGNIFICANT's MahaRERA page (P51600027892). GharKundli's Kundli Watch sends a free WhatsApp update on SIGNIFICANT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SIGNIFICANT have?
According to GharKundli's check of MahaRERA records (updated October 2026), SIGNIFICANT has one building filed: SIGNIFICANT with 9 floors and 266 units.
How much parking does SIGNIFICANT have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 100 covered car parking spaces for SIGNIFICANT.
How big is the land of SIGNIFICANT?
According to GharKundli's check of MahaRERA records (updated October 2026), SIGNIFICANT stands on 7,600 sq m of land (about 1.9 acres), with 10,810 sq m of sanctioned built-up area and 760 sq m of recreational open space.
What is the track record of SIGNIFICANT's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), IND Developers has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 10 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SIGNIFICANT?
Google Maps has reviews of SIGNIFICANT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SIGNIFICANT?
SIGNIFICANT by IND DEVELOPERS is in Wadala, Nashik (pincode 422006), near Indira Nagar, Trimurti Chowk, Maharashtra, and is registered on MahaRERA as P51600027892, per GharKundli's check of MahaRERA records.
How many homes are in SIGNIFICANT?
According to GharKundli's check of MahaRERA records (updated October 2026), SIGNIFICANT has 266 homes in 1 tower registered on MahaRERA, and 56% of them are sold or booked.
When was SIGNIFICANT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SIGNIFICANT was registered on MahaRERA on 14 January 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on SIGNIFICANT?
No court cases are listed for SIGNIFICANT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SIGNIFICANT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is IND DEVELOPERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SIGNIFICANT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Nashik →
Other projects in Wadala
- GURUSIDDHI KRUPA
- AJMERA MANHATTAN BUILDING 3A AND 3B
- TABEER VISTA
- ADAN TOWER
- KOMAL ORCHID
- MANGALMURTI APARTMENT
- AMMARAH HEIGHTS
- SHRINIWAS APARTMENT
Other projects by IND DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.