Skip to content
GharKundli

Sai Sharddha

by RAHUL BALASAHEB TARGE · Government ITI, Nashik 422103

What’s in the report? →

Possession date of Sai Sharddha (MahaRERA P51600028508): 30 June 2024, and it has already passed. It has 15 homes, 73% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600028508. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51600028508, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2024) has passed.

What do you want to know about Sai Sharddha?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Sai Sharddha

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600028508
Status
Lapsed (registration period ended)
Builder
RAHUL BALASAHEB TARGE
Location
Government ITI, Nashik · 422103
Project type
Mixed
Registered on
8 Mar 2021
Completion date at registration
June 2024
Latest completion date
June 2024
Homes
15
Sold or booked
73%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Sai Sharddha, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAI SHARDDHA100%100%80%70%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sai Sharddha every 1–2 months.

Sai Sharddha: buildings, flats and land, as filed on MahaRERA

  • Buildings: SAI SHARDDHA (5 floors)
  • Land: 487 sq m (about 0.1 acres) · sanctioned built-up 585 sq m
  • Boundaries filed include: 9 mtr wide colony road
  • Land, as filed: PLOT NO7 8 19 SURVEY NO 981
  • Map: Get directions

The builder’s record and reviews

Rahul Balasaheb Targe has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 2 lapsed. No complaints on MahaRERA.

Read Google reviews of Sai Sharddha →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sai Sharddha: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Sai Sharddha

What is the possession date of Sai Sharddha?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sai Sharddha in Government ITI, Nashik is 30 June 2024. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Sai Sharddha?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sai Sharddha's builder has filed on MahaRERA, the official one, is 30 June 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Sai Sharddha?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sai Sharddha in Government ITI, Nashik is P51600028508.

Is Sai Sharddha registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Sharddha is registered as P51600028508 and its status is "Lapsed (registration period ended)".

What is the current construction status of Sai Sharddha? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Sharddha's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SAI SHARDDHA is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does Sai Sharddha have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Sai Sharddha safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Sharddha is registered on MahaRERA as P51600028508, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Sai Sharddha?

Sai Sharddha isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Sai Sharddha?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Sai Sharddha: gharkundli.com/tools/property-cost-calculator

Has Sai Sharddha received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Sai Sharddha isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Sai Sharddha?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Sharddha's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Sai Sharddha uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Sai Sharddha was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Sai Sharddha's possession date changes?

The latest dates are on Sai Sharddha's MahaRERA page (P51600028508). GharKundli's Kundli Watch sends a free WhatsApp update on Sai Sharddha every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sai Sharddha have?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Sharddha has one building filed: SAI SHARDDHA with 5 floors.

How big is the land of Sai Sharddha?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Sharddha stands on 487 sq m of land (about 0.1 acres), with 585 sq m of sanctioned built-up area.

What is the track record of Sai Sharddha's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Rahul Balasaheb Targe has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Sai Sharddha?

Google Maps has reviews of Sai Sharddha written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Sai Sharddha?

Sai Sharddha by RAHUL BALASAHEB TARGE is in Government ITI, Nashik, pincode 422103, Maharashtra, and is registered on MahaRERA as P51600028508, per GharKundli's check of MahaRERA records. Its boundaries filed there include 9 mtr wide colony road. Its land is filed as PLOT NO7 8 19 SURVEY NO 981. GharKundli lists all 63 MahaRERA projects in Sinnar (422103).

How many flats are in Sai Sharddha, and how many are sold?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Sharddha has 15 homes in 1 tower registered on MahaRERA, and 73% of them are sold or booked.

When was Sai Sharddha registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Sharddha was registered on MahaRERA on 8 March 2021. GharKundli did not find a title report on the land on file there.

Does Sai Sharddha have any legal issues or court cases?

No court cases are listed for Sai Sharddha on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Sai Sharddha?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RAHUL BALASAHEB TARGE, which has 1 other project registered on MahaRERA.

Other projects in Sinnar

All 63 projects in Sinnar (422103) →

Other projects by RAHUL BALASAHEB TARGE

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.