Arkk Pushp Phase II
by VIJAY LALJIBHAI CHHEDA · Bhagur, Nashik 422401
What’s in the report? →Possession date of Arkk Pushp Phase II (MahaRERA P51600028565): 30 October 2026, and it has already passed. It has 52 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600028565. Status: Lapsed (registration period ended). Its completion date is now October 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51600028565, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about Arkk Pushp Phase II?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Arkk Pushp Phase II has moved
30 June 2026
Completion date given when the project was registered
30 October 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Arkk Pushp Phase II’s extension records on MahaRERA (P51600028565), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Arkk Pushp Phase II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600028565
- Status
- Lapsed (registration period ended)
- Builder
- VIJAY LALJIBHAI CHHEDA
- Location
- Bhagur, Nashik · 422401
- Project type
- Residential / Group Housing
- Registered on
- 19 Mar 2021
- Completion date at registration
- June 2026
- Latest completion date
- October 2026
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 52
- Towers
- 5
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Arkk Pushp Phase II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING A | 0% | 0% | 0% | 0% |
| BUILDING B | 0% | 0% | 0% | 0% |
| BUILDING C | 100% | 100% | 90% | 90% |
| BUILDING D | 100% | 100% | 90% | 90% |
| BUILDING E | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Arkk Pushp Phase II every 1–2 months.
Arkk Pushp Phase II: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING A (4 floors) · BUILDING B (4 floors) · BUILDING C (4 floors) · BUILDING D (5 floors) · BUILDING E (4 floors)
- Land: 4,400 sq m (about 1.1 acres) · sanctioned built-up 1,876 sq m
- Land, as filed: PLOT NO 56/4A
- Map: Get directions
The builder’s record and reviews
Vijay Laljibhai Chheda has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Arkk Pushp Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Arkk Pushp Phase II: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Arkk Pushp Phase II
What is the possession date of Arkk Pushp Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Arkk Pushp Phase II in Bhagur, Nashik is 30 October 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Arkk Pushp Phase II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Arkk Pushp Phase II's builder has filed on MahaRERA, the official one, is 30 October 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Arkk Pushp Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Arkk Pushp Phase II in Bhagur, Nashik is P51600028565.
Is Arkk Pushp Phase II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Arkk Pushp Phase II is registered as P51600028565 and its status is "Lapsed (registration period ended)".
What is the current construction status of Arkk Pushp Phase II? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Arkk Pushp Phase II's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does Arkk Pushp Phase II have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Arkk Pushp Phase II safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Arkk Pushp Phase II is registered on MahaRERA as P51600028565, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Arkk Pushp Phase II?
Arkk Pushp Phase II isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Arkk Pushp Phase II?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Arkk Pushp Phase II: gharkundli.com/tools/property-cost-calculator
Has Arkk Pushp Phase II received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Arkk Pushp Phase II isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Arkk Pushp Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), Arkk Pushp Phase II's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 October 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Arkk Pushp Phase II uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Arkk Pushp Phase II was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Arkk Pushp Phase II's possession date changes?
The latest dates are on Arkk Pushp Phase II's MahaRERA page (P51600028565). GharKundli's Kundli Watch sends a free WhatsApp update on Arkk Pushp Phase II every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Arkk Pushp Phase II have?
According to GharKundli's check of MahaRERA records (updated November 2026), Arkk Pushp Phase II has 5 buildings filed: BUILDING A with 4 floors; BUILDING B with 4 floors; BUILDING C with 4 floors; BUILDING D with 5 floors; BUILDING E with 4 floors.
How big is the land of Arkk Pushp Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), Arkk Pushp Phase II stands on 4,400 sq m of land (about 1.1 acres), with 1,876 sq m of sanctioned built-up area.
What is the track record of Arkk Pushp Phase II's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Vijay Laljibhai Chheda has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Arkk Pushp Phase II?
Google Maps has reviews of Arkk Pushp Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Arkk Pushp Phase II?
Arkk Pushp Phase II by VIJAY LALJIBHAI CHHEDA is in Bhagur, Nashik, pincode 422401, Maharashtra, and is registered on MahaRERA as P51600028565, per GharKundli's check of MahaRERA records. Its land is filed as PLOT NO 56/4A. GharKundli lists all 81 MahaRERA projects in Devlali (422401).
How many flats are in Arkk Pushp Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), Arkk Pushp Phase II has 52 homes in 5 towers registered on MahaRERA.
When was Arkk Pushp Phase II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Arkk Pushp Phase II was registered on MahaRERA on 19 March 2021. GharKundli did not find a title report on the land on file there.
Does Arkk Pushp Phase II have any legal issues or court cases?
No court cases are listed for Arkk Pushp Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Arkk Pushp Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VIJAY LALJIBHAI CHHEDA, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Arkk Pushp Phase II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Nashik →
Other projects in Devlali (422401)
- Yamuna Park
- Kings Harmony
- Shah and Kasar's Laxmi Park Phase I
- Green Square
- Shah S Landmark
- Arkk Estate Phase II
- Arkk Estate
- Kuber Nagari Apartment
Other projects by VIJAY LALJIBHAI CHHEDA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.