Redevelopment of Saraswati CHSL
by RAWOOLNATH INFRASTRUCTURE PRIVATE LIMITED · Gorai Road, Mumbai 400091Also near Borivali West, Vile Parle East, Kandivali
What’s in the report? →Possession date of Redevelopment of Saraswati CHSL (MahaRERA P51800007585): 31 December 2025, moved from 30 December 2023 (24 months later), and it has already passed. It has 67 homes (2 BHK, 3 BHK and 4 BHK, 693–3005 sq ft carpet), 95% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800007585. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800007585, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Redevelopment of Saraswati CHSL?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Redevelopment of Saraswati CHSL has moved
30 December 2023
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51800018392)
Reason the builder gave MahaRERA:
“We are pleased to inform you that as per the Intimation of Disapproval (IOD) and Commencement Certificate(CC) already received, the construction work for the project is 95% complete. However, as per the provisions under the new Development…” Read the full reason
“We are pleased to inform you that as per the Intimation of Disapproval (IOD) and Commencement Certificate(CC) already received, the construction work for the project is 95% complete. However, as per the provisions under the new Development Control and Promotion Regulations (DCPR) 2034, it is now possible to avail additional FSI for the project. In view of this development, we intend to utilise the additional FSI as per the new guidelines. To facilitate the process and complete the requisite formalities, we humbly request an extention of 12 months. This extension will allow us to: 1. Apply f…”
Source: Redevelopment of Saraswati CHSL’s extension records on MahaRERA (P51800007585), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Redevelopment of Saraswati CHSL
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800007585
- Status
- Lapsed (registration period ended)
- Builder
- RAWOOLNATH INFRASTRUCTURE PRIVATE LIMITED
- Location
- Gorai Road, Mumbai · 400091
- Project type
- Others
- Registered on
- 17 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- December 2025
- Delay so far
- 24 months
- Homes
- 67
- Sold or booked
- 95%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Redevelopment of Saraswati CHSL, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Parrk Riviera | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Parrk Riviera: covers PLINTH LEVEL
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Redevelopment of Saraswati CHSL every 1–2 months.
Redevelopment of Saraswati CHSL: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 1,017 – 1,120 | 34 |
| 2 BHK | 693 – 752 | 32 |
| Shops | 306 – 538 | 8 |
| Office Space | 610 – 674 | 2 |
| 4 BHK | 3,005 | 1 |
- Buildings: Parrk Riviera (23 floors, 77 units)
- Land: 1,228 sq m (about 0.3 acres) · sanctioned built-up 2,578 sq m · recreational space 369 sq m
- Land, as filed: Bldg 36 F.P. No. 457
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Redevelopment of Saraswati CHSL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Redevelopment of Saraswati CHSL: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Redevelopment of Saraswati CHSL
What is the possession date of Redevelopment of Saraswati CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Redevelopment of Saraswati CHSL in Gorai Road, Mumbai is 31 December 2025 — 24 months later than 30 December 2023, the date given at registration. That date has already passed.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Redevelopment of Saraswati CHSL?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Redevelopment of Saraswati CHSL's builder has filed on MahaRERA, the official one, is 31 December 2025, already 24 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Redevelopment of Saraswati CHSL extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Saraswati CHSL's builder applied to MahaRERA to extend the completion date once: to 31 December 2025, giving the reason "We are pleased to inform you that as per the Intimation of Disapproval (IOD) and Commencement Certificate(CC) already received, the construction work for the project is 95% complete. However, as per the provisions under the new Development Control and Promotion Regulations (DCPR) 2034, it is now possible to avail additional FSI for the project. In view of this development, we intend to utilise the additional FSI as per the new guidelines. To facilitate the process and complete the requisite formalities, we humbly request an extention of 12 months. This extension will allow us to: 1. Apply f…".
What is the RERA number of Redevelopment of Saraswati CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Redevelopment of Saraswati CHSL in Gorai Road, Mumbai is P51800007585.
Is Redevelopment of Saraswati CHSL registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Saraswati CHSL is registered as P51800007585 and its status is "Lapsed (registration period ended)".
What is the current construction status of Redevelopment of Saraswati CHSL? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Saraswati CHSL's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Parrk Riviera is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Redevelopment of Saraswati CHSL have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Redevelopment of Saraswati CHSL safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Saraswati CHSL is registered on MahaRERA as P51800007585, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Redevelopment of Saraswati CHSL?
Redevelopment of Saraswati CHSL isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Redevelopment of Saraswati CHSL start at 693 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Redevelopment of Saraswati CHSL?
For a flat in Redevelopment of Saraswati CHSL (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Redevelopment of Saraswati CHSL received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Saraswati CHSL isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Redevelopment of Saraswati CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Saraswati CHSL's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Is Redevelopment of Saraswati CHSL a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Saraswati CHSL is a redevelopment: 22 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Redevelopment of Saraswati CHSL uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Redevelopment of Saraswati CHSL was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Redevelopment of Saraswati CHSL's possession date changes?
The latest dates are on Redevelopment of Saraswati CHSL's MahaRERA page (P51800007585). GharKundli's Kundli Watch sends a free WhatsApp update on Redevelopment of Saraswati CHSL every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Redevelopment of Saraswati CHSL have?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Saraswati CHSL has one building filed: Parrk Riviera with 23 floors and 77 units.
What are the flat sizes (carpet area) in Redevelopment of Saraswati CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Redevelopment of Saraswati CHSL: 3 BHK: 1017 to 1120 sq ft carpet (34 homes); 2 BHK: 693 to 752 sq ft carpet (32 homes); 4 BHK: 3005 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Redevelopment of Saraswati CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Saraswati CHSL stands on 1,228 sq m of land (about 0.3 acres), with 2,578 sq m of sanctioned built-up area and 369 sq m of recreational open space.
What are the reviews of Redevelopment of Saraswati CHSL?
Google Maps has reviews of Redevelopment of Saraswati CHSL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Redevelopment of Saraswati CHSL?
Redevelopment of Saraswati CHSL by RAWOOLNATH INFRASTRUCTURE PRIVATE LIMITED is in Gorai Road, Mumbai, pincode 400091 (near Borivali West, Vile Parle East, Kandivali), Maharashtra, and is registered on MahaRERA as P51800007585, per GharKundli's check of MahaRERA records. Its land is filed as Bldg 36 F.P. No. 457. GharKundli lists all 69 MahaRERA projects in Borivali West (400091).
How many flats are in Redevelopment of Saraswati CHSL, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Saraswati CHSL has 67 homes in 1 tower registered on MahaRERA, and 95% of them are sold or booked.
When was Redevelopment of Saraswati CHSL registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Saraswati CHSL was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Does Redevelopment of Saraswati CHSL have any legal issues or court cases?
No court cases are listed for Redevelopment of Saraswati CHSL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Redevelopment of Saraswati CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAWOOLNATH INFRASTRUCTURE PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of Redevelopment of Saraswati CHSL
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Borivali
- Saffronwoods CHSL
- Parshuram Heights
- Avirahi Elegance
- L&T Realty Ahana Tower A
- L&T Realty Ahana Tower B
- Rashmi Icon
- Shraddha Skyline
- LA SERENA Tower 5, Tower 6 and Tower 7
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.