Shubharambh Residency

by LAXMI BUILDCON · Udyog Bhavan Opp Ashoka School Sinnar, Nashik 422103

What’s in the report? →

Possession date of Shubharambh Residency (MahaRERA P51600031065): 31 August 2024, and it has already passed. It has 20 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600031065. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51600031065, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (August 2024) has passed.

What do you want to know about Shubharambh Residency?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Shubharambh Residency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the August 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600031065
Status
Lapsed (registration period ended)
Builder
LAXMI BUILDCON
Location
Udyog Bhavan Opp Ashoka School Sinnar, Nashik · 422103
Project type
Others
Registered on
5 Oct 2021
Completion date at registration
August 2024
Homes
20
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Shubharambh Residency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHUBHARAMBH RESIDENCY100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shubharambh Residency every 1–2 months.

Shubharambh Residency: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHUBHARAMBH RESIDENCY (6 floors)
  • Land: 428 sq m (about 0.1 acres) · sanctioned built-up 502 sq m
  • Boundaries filed include: 12 MTS COLONY ROAD
  • Land, as filed: S NO 923/1/2/7/8 old 1160 PLOT NO 16 at MAUJE SINNAR SHIWAR
  • Map: Get directions

The builder’s record and reviews

Laxmi Buildcon (a group of 2 linked companies) has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 3 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Shubharambh Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shubharambh Residency: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shubharambh Residency

What is the possession date of Shubharambh Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shubharambh Residency in Udyog Bhavan Opp Ashoka School Sinnar, Nashik is 31 August 2024. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Shubharambh Residency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shubharambh Residency's builder has filed on MahaRERA, the official one, is 31 August 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Shubharambh Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shubharambh Residency in Udyog Bhavan Opp Ashoka School Sinnar, Nashik is P51600031065.

Is Shubharambh Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubharambh Residency is registered as P51600031065 and its status is "Lapsed (registration period ended)".

What is the current construction status of Shubharambh Residency? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubharambh Residency's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHUBHARAMBH RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Shubharambh Residency have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Shubharambh Residency safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubharambh Residency is registered on MahaRERA as P51600031065, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shubharambh Residency?

Shubharambh Residency isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shubharambh Residency?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shubharambh Residency: gharkundli.com/tools/property-cost-calculator

Has Shubharambh Residency received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Shubharambh Residency isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 August 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Shubharambh Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubharambh Residency's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 August 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Shubharambh Residency uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Shubharambh Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shubharambh Residency's possession date changes?

The latest dates are on Shubharambh Residency's MahaRERA page (P51600031065). GharKundli's Kundli Watch sends a free WhatsApp update on Shubharambh Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shubharambh Residency have?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubharambh Residency has one building filed: SHUBHARAMBH RESIDENCY with 6 floors.

How big is the land of Shubharambh Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubharambh Residency stands on 428 sq m of land (about 0.1 acres), with 502 sq m of sanctioned built-up area.

What is the track record of Shubharambh Residency's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Laxmi Buildcon (a group of 2 linked companies) has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 3 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shubharambh Residency?

Google Maps has reviews of Shubharambh Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shubharambh Residency?

Shubharambh Residency by LAXMI BUILDCON is in Udyog Bhavan Opp Ashoka School Sinnar, Nashik, pincode 422103, Maharashtra, and is registered on MahaRERA as P51600031065, per GharKundli's check of MahaRERA records. Its boundaries filed there include 12 MTS COLONY ROAD. Its land is filed as S NO 923/1/2/7/8 old 1160 PLOT NO 16 at MAUJE SINNAR SHIWAR. GharKundli lists all 63 MahaRERA projects in Sinnar (422103).

How many flats are in Shubharambh Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubharambh Residency has 20 homes in 1 tower registered on MahaRERA.

When was Shubharambh Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubharambh Residency was registered on MahaRERA on 5 October 2021. GharKundli did not find a title report on the land on file there.

Does Shubharambh Residency have any legal issues or court cases?

No court cases are listed for Shubharambh Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Shubharambh Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is LAXMI BUILDCON, which has 5 other projects registered on MahaRERA.

Other projects in Sinnar (422103)

All 63 projects in Sinnar (422103) →

Other projects by LAXMI BUILDCON

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.