Skip to content
GharKundli

Gajanan Plaza

by Balaji Construction Co. · Mahavir nagar, MumbaiAlso near Kandivali west, Charkop, malad west

Possession date of Gajanan Plaza: 30 April 2028, moved from 31 December 2018 (108 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800009622, and currently active. Its completion date has moved from December 2018 to April 2028: 108 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project. 14 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Gajanan Plaza?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on Gajanan Plaza

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 14 complaints, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800009622
Status
Registered and active
Builder
Balaji Construction Co.
Location
Mahavir nagar, Mumbai · 400067
Project type
Others
Registered on
22 Aug 2017
Completion date at registration
December 2018
Latest completion date
April 2028
Delay so far
108 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
38
Towers
1
Complaints on MahaRERA
14
Court cases listed
0
Appeals at the tribunal
12
MahaRERA regulatory orders
1
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Gajanan Plaza, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GAJANAN PLAZA100%100%100%95%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gajanan Plaza every month.

Gajanan Plaza: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Balaji Construction (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 90 months late); 1 lapsed. 31 complaints on MahaRERA across 2 projects.

Read Google reviews of Gajanan Plaza →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Gajanan Plaza: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Gajanan Plaza

What is the possession date of Gajanan Plaza?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Gajanan Plaza in Mahavir nagar, Mumbai is 30 April 2028 — 108 months later than 31 December 2018, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Gajanan Plaza?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Gajanan Plaza's builder has filed on MahaRERA, the official one, is 30 April 2028, already 108 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Gajanan Plaza?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Gajanan Plaza in Mahavir nagar, Mumbai is P51800009622.

Is Gajanan Plaza registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Plaza is registered as P51800009622 and its status is "Registered and active". On MahaRERA's own list: Sales frozen by MahaRERA: completion date lapsed. MahaRERA has put this project in abeyance because its completion date has lapsed. Its bank account is frozen, and the builder may not sign agreements for sale or sale deeds with buyers until it complies.

What is the construction status of Gajanan Plaza?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Plaza's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GAJANAN PLAZA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Gajanan Plaza have complaints on MahaRERA?

14 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Gajanan Plaza safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Plaza is registered on MahaRERA as P51800009622, its completion date has moved 108 months since registration, 14 complaints are listed against it and it is on MahaRERA's list "Sales frozen by MahaRERA: completion date lapsed". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Gajanan Plaza's possession date changes?

The latest dates are on Gajanan Plaza's MahaRERA page (P51800009622). GharKundli's Kundli Watch sends a free WhatsApp update on Gajanan Plaza every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Gajanan Plaza have?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Plaza has one building filed: GAJANAN PLAZA with 6 floors.

How big is the land of Gajanan Plaza?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Plaza stands on 565 sq m of land (about 0.1 acres), with 1,127 sq m of sanctioned built-up area.

What is the track record of Gajanan Plaza's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Construction (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 90 months late); 1 lapsed. 31 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Gajanan Plaza?

Google Maps has reviews of Gajanan Plaza written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 14 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Gajanan Plaza?

Gajanan Plaza by Balaji Construction Co. is in Mahavir nagar, Mumbai (pincode 400067), near Kandivali west, Charkop, malad west, Maharashtra, and is registered on MahaRERA as P51800009622, per GharKundli's check of MahaRERA records.

How many homes are in Gajanan Plaza?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Plaza has 38 homes in 1 tower registered on MahaRERA.

When was Gajanan Plaza registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Gajanan Plaza was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Gajanan Plaza?

No court cases are listed for Gajanan Plaza on MahaRERA, and 12 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Gajanan Plaza?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Balaji Construction Co., which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

All projects in Kandivali West (400067) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.