Skip to content
GharKundli

MOBIN HEIGHTS

by GAHLOT DEVELOPMENT SERVICES PVT. LTD. · Next To Arfa Hotel, MumbaiAlso near Vile Parle West, Juhu, Andheri West

Possession date of MOBIN HEIGHTS: 30 April 2027, moved from 30 December 2022 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800011697, and currently active. Its completion date has moved from December 2022 to April 2027: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about MOBIN HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MOBIN HEIGHTS has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT51800013421)

    Reason the builder gave MahaRERA: “Due to COVID-19 Pandemic, LITIGATION filed in Bom HC by partner of co-promoter firm, change in specifications and delay in approval by competent authority etc”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: MOBIN HEIGHTS’s extension records on MahaRERA (P51800011697), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MOBIN HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800011697
Status
Registered and active
Builder
GAHLOT DEVELOPMENT SERVICES PVT. LTD.
Location
Next To Arfa Hotel, Mumbai · 400058
Project type
Others
Registered on
31 Aug 2017
Completion date at registration
December 2022
Latest completion date
April 2027
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
42
Sold or booked
60%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of MOBIN HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MOBIN HEIGHTS100%100%90%95%

Commencement certificate (CC), as filed on MahaRERA

  • MOBIN HEIGHTS: covers 19 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MOBIN HEIGHTS every month.

MOBIN HEIGHTS: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK663 – 81726
1 BHK486 – 50013
Shops236 – 1,0904
Other2,3593
3 BHK950 – 9532
4 BHK1,2761

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MOBIN HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MOBIN HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MOBIN HEIGHTS

What is the possession date of MOBIN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MOBIN HEIGHTS in Next To Arfa Hotel, Mumbai is 30 April 2027 — 48 months later than 30 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for MOBIN HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MOBIN HEIGHTS's builder has filed on MahaRERA, the official one, is 30 April 2027, already 48 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MOBIN HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), MOBIN HEIGHTS's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Due to COVID-19 Pandemic, LITIGATION filed in Bom HC by partner of co-promoter firm, change in specifications and delay in approval by competent authority etc". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of MOBIN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MOBIN HEIGHTS in Next To Arfa Hotel, Mumbai is P51800011697.

Is MOBIN HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MOBIN HEIGHTS is registered as P51800011697 and its status is "Registered and active".

What is the construction status of MOBIN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), MOBIN HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MOBIN HEIGHTS is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does MOBIN HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is MOBIN HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MOBIN HEIGHTS is registered on MahaRERA as P51800011697, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MOBIN HEIGHTS's possession date changes?

The latest dates are on MOBIN HEIGHTS's MahaRERA page (P51800011697). GharKundli's Kundli Watch sends a free WhatsApp update on MOBIN HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MOBIN HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), MOBIN HEIGHTS has one building filed: MOBIN HEIGHTS with 19 floors and 49 units.

What are the flat sizes (carpet area) in MOBIN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for MOBIN HEIGHTS: 2 BHK: 663 to 817 sq ft carpet (26 homes); 1 BHK: 486 to 500 sq ft carpet (13 homes); 3 BHK: 950 to 953 sq ft carpet (2 homes); 4 BHK: 1276 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of MOBIN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), MOBIN HEIGHTS stands on 2,345 sq m of land (about 0.6 acres), with 3,899 sq m of sanctioned built-up area.

Where can I read reviews of MOBIN HEIGHTS?

Google Maps has reviews of MOBIN HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MOBIN HEIGHTS?

MOBIN HEIGHTS by GAHLOT DEVELOPMENT SERVICES PVT. LTD. is in Next To Arfa Hotel, Mumbai (pincode 400058), near Vile Parle West, Juhu, Andheri West, Maharashtra, and is registered on MahaRERA as P51800011697, per GharKundli's check of MahaRERA records.

How many homes are in MOBIN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), MOBIN HEIGHTS has 42 homes in 1 tower registered on MahaRERA, and 60% of them are sold or booked.

When was MOBIN HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MOBIN HEIGHTS was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on MOBIN HEIGHTS?

No court cases are listed for MOBIN HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of MOBIN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GAHLOT DEVELOPMENT SERVICES PVT. LTD..

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Andheri

All 148 projects in Andheri West (400058) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.