Pranav Avenue
by Ekveera Developers · Kamatwada, Nashik
Possession date of Pranav Avenue: 1 January 2025. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51600033649. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (January 2025) has passed.
What do you want to know about Pranav Avenue?
GharKundli’s full report on Pranav Avenue
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the January 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600033649
- Status
- Lapsed (registration period ended)
- Builder
- Ekveera Developers
- Location
- Kamatwada, Nashik · 422010
- Project type
- Commercial
- Registered on
- 2 Mar 2022
- Completion date at registration
- January 2025
- Homes
- 13
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Pranav Avenue, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Pranav Avenue | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Pranav Avenue every month.
Pranav Avenue: buildings, flats and land, as filed on MahaRERA
- Buildings: Pranav Avenue (7 floors)
- Land: 2,547 sq m (about 0.6 acres) · sanctioned built-up 3,278 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Pranav Avenue →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Pranav Avenue: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Pranav Avenue
What is the possession date of Pranav Avenue?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Pranav Avenue in Kamatwada, Nashik is 1 January 2025. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Pranav Avenue?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Pranav Avenue's builder has filed on MahaRERA, the official one, is 1 January 2025, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Pranav Avenue?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Pranav Avenue in Kamatwada, Nashik is P51600033649.
Is Pranav Avenue registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Pranav Avenue is registered as P51600033649 and its status is "Lapsed (registration period ended)".
What is the construction status of Pranav Avenue?
According to GharKundli's check of MahaRERA records (updated November 2026), Pranav Avenue's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Pranav Avenue is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Pranav Avenue have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Pranav Avenue safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Pranav Avenue is registered on MahaRERA as P51600033649, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Pranav Avenue's possession date changes?
The latest dates are on Pranav Avenue's MahaRERA page (P51600033649). GharKundli's Kundli Watch sends a free WhatsApp update on Pranav Avenue every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Pranav Avenue have?
According to GharKundli's check of MahaRERA records (updated November 2026), Pranav Avenue has one building filed: Pranav Avenue with 7 floors.
How big is the land of Pranav Avenue?
According to GharKundli's check of MahaRERA records (updated November 2026), Pranav Avenue stands on 2,547 sq m of land (about 0.6 acres), with 3,278 sq m of sanctioned built-up area.
Where can I read reviews of Pranav Avenue?
Google Maps has reviews of Pranav Avenue written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Pranav Avenue?
Pranav Avenue by Ekveera Developers is in Kamatwada, Nashik (pincode 422010), Maharashtra, and is registered on MahaRERA as P51600033649, per GharKundli's check of MahaRERA records.
How many homes are in Pranav Avenue?
According to GharKundli's check of MahaRERA records (updated November 2026), Pranav Avenue has 13 homes in 1 tower registered on MahaRERA.
When was Pranav Avenue registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Pranav Avenue was registered on MahaRERA on 2 March 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Pranav Avenue?
No court cases are listed for Pranav Avenue on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Pranav Avenue?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Ekveera Developers.
Check it yourself on MahaRERA
- How to check the possession date of Pranav Avenue
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Nashik
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.