by GRACE ESTATE DEVELOPMENT VENTURE - Parvez Suleman Lakdawala (Proprietor) · Bandra West, MumbaiAlso near Vile Parle West, Vile Parle East, Juhu

Possession date of Grace Grandeur: 30 August 2027, moved from 30 December 2020 (76 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800010438, and currently active. Its completion date has moved from December 2020 to August 2027: 76 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Grace Grandeur?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Grace Grandeur has moved

  1. 30 December 2020

    Completion date given when the project was registered

  2. 1 October 2023

    Extended at the builder's request (MahaRERA application EXT51800010956)

    Reason the builder gave MahaRERA: “The project got delayed due to we are not received any approval from Competent authority.”
  3. 30 April 2025

    Extended at the builder's request (MahaRERA application EXT51800019844)

    Reason the builder gave MahaRERA: “Covid”
  4. 30 April 2027

    Extended at the builder's request (MahaRERA application EA16072502078)

    Reason the builder gave MahaRERA:
    “1) As the entire country including Mumbai Suburban were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to cur…” Read the full reason“1) As the entire country including Mumbai Suburban were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to curb the spread of the COVID-19. In view of the curbs and measures imposed by the Governments, I stopped work till such time as the said lockdowns, curbs and measures were relaxed by the respective Governments. 2) Inspite of best efforts, the said project was adversely affected due to unprecedented COVID-19 Pandemic which lasted for more than 2 years and are…”
  5. 30 August 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Grace Grandeur’s extension records on MahaRERA (P51800010438), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Grace Grandeur

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 1 court case, and how it ended
  • Construction pace against the August 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800010438
Status
Registered and active
Builder
GRACE ESTATE DEVELOPMENT VENTURE - Parvez Suleman Lakdawala (Proprietor)
Location
Bandra West, Mumbai · 400053
Project type
Residential / Group Housing
Registered on
24 Aug 2017
Completion date at registration
December 2020
Latest completion date
August 2027
Delay so far
76 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
69
Sold or booked
85%
Towers
1
Complaints on MahaRERA
1
Court cases listed
1
Title report on file
Not found

Construction progress of Grace Grandeur, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Commencement certificate (CC), as filed on MahaRERA

  • Wing A and Wing B: covers 10 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Grace Grandeur every month.

Grace Grandeur: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK515 – 60048
1 BHK500 – 1,00321

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Grace Grandeur →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Grace Grandeur: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Grace Grandeur

What is the possession date of Grace Grandeur?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Grace Grandeur in Bandra West, Mumbai is 30 August 2027 — 76 months later than 30 December 2020, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Grace Grandeur?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Grace Grandeur's builder has filed on MahaRERA, the official one, is 30 August 2027, already 76 months later than the 30 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Grace Grandeur extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Grace Grandeur's builder applied to MahaRERA to extend the completion date 3 times: to 1 October 2023, giving the reason "The project got delayed due to we are not received any approval from Competent authority."; to 30 April 2025, giving the reason "Covid"; to 30 April 2027, giving the reason "1) As the entire country including Mumbai Suburban were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to curb the spread of the COVID-19. In view of the curbs and measures imposed by the Governments, I stopped work till such time as the said lockdowns, curbs and measures were relaxed by the respective Governments. 2) Inspite of best efforts, the said project was adversely affected due to unprecedented COVID-19 Pandemic which lasted for more than 2 years and are…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Grace Grandeur?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Grace Grandeur in Bandra West, Mumbai is P51800010438.

Is Grace Grandeur registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Grace Grandeur is registered as P51800010438 and its status is "Registered and active".

What is the construction status of Grace Grandeur?

According to GharKundli's check of MahaRERA records (updated October 2026), Grace Grandeur's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.

Does Grace Grandeur have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Grace Grandeur safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Grace Grandeur is registered on MahaRERA as P51800010438, its completion date has moved 76 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Grace Grandeur's possession date changes?

The latest dates are on Grace Grandeur's MahaRERA page (P51800010438). GharKundli's Kundli Watch sends a free WhatsApp update on Grace Grandeur every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Grace Grandeur have?

According to GharKundli's check of MahaRERA records (updated October 2026), Grace Grandeur has one building filed: Wing A and Wing B with 18 floors and 69 units.

What are the flat sizes (carpet area) in Grace Grandeur?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Grace Grandeur: 2 BHK: 515 to 600 sq ft carpet (48 homes); 1 BHK: 500 to 1003 sq ft carpet (21 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Grace Grandeur have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 70 covered car parking spaces for Grace Grandeur.

How big is the land of Grace Grandeur?

According to GharKundli's check of MahaRERA records (updated October 2026), Grace Grandeur stands on 2,428 sq m of land (about 0.6 acres), with 2,428 sq m of sanctioned built-up area.

Where can I read reviews of Grace Grandeur?

Google Maps has reviews of Grace Grandeur written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Grace Grandeur?

Grace Grandeur by GRACE ESTATE DEVELOPMENT VENTURE - Parvez Suleman Lakdawala (Proprietor) is in Bandra West, Mumbai (pincode 400053), near Vile Parle West, Vile Parle East, Juhu, Maharashtra, and is registered on MahaRERA as P51800010438, per GharKundli's check of MahaRERA records.

How many homes are in Grace Grandeur?

According to GharKundli's check of MahaRERA records (updated October 2026), Grace Grandeur has 69 homes in 1 tower registered on MahaRERA, and 85% of them are sold or booked.

When was Grace Grandeur registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Grace Grandeur was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Grace Grandeur?

1 court case is listed for Grace Grandeur on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Grace Grandeur?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GRACE ESTATE DEVELOPMENT VENTURE - Parvez Suleman Lakdawala (Proprietor).

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Bandra West

All 161 projects in Andheri West (400053) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.