KAMALA CHS LTD
by PRAVESH KIRTI KANTHER · Iraniwadi, MumbaiAlso near Kandivali West, Bandra, Malad West
Possession date of KAMALA CHS LTD: 30 December 2031, moved from 31 December 2024 (84 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800003738. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about KAMALA CHS LTD?
How the possession date of KAMALA CHS LTD has moved
31 December 2024
Completion date given when the project was registered
30 December 2031
Revised completion date on MahaRERA
Source: KAMALA CHS LTD’s extension records on MahaRERA (P51800003738), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KAMALA CHS LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 1 court case, and how it ended
- Construction pace against the December 2031 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800003738
- Status
- Lapsed (registration period ended)
- Builder
- PRAVESH KIRTI KANTHER
- Location
- Iraniwadi, Mumbai · 400067
- Project type
- Others
- Registered on
- 6 Aug 2017
- Completion date at registration
- December 2024
- Latest completion date
- December 2031
- Delay so far
- 84 months
- Homes
- 110
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 1
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of KAMALA CHS LTD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KAMALA CHS LTD | 100% | 100% | 98% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KAMALA CHS LTD every month.
KAMALA CHS LTD: buildings, flats and land, as filed on MahaRERA
- Buildings: KAMALA CHS LTD (31 floors)
- Land: 855 sq m (about 0.2 acres) · sanctioned built-up 2,568 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of KAMALA CHS LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KAMALA CHS LTD: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KAMALA CHS LTD
What is the possession date of KAMALA CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KAMALA CHS LTD in Iraniwadi, Mumbai is 30 December 2031 — 84 months later than 31 December 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for KAMALA CHS LTD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KAMALA CHS LTD's builder has filed on MahaRERA, the official one, is 30 December 2031, already 84 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of KAMALA CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KAMALA CHS LTD in Iraniwadi, Mumbai is P51800003738.
Is KAMALA CHS LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KAMALA CHS LTD is registered as P51800003738 and its status is "Lapsed (registration period ended)".
What is the construction status of KAMALA CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), KAMALA CHS LTD's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on KAMALA CHS LTD is 100% done and internal work 98%. GharKundli's full report compares construction progress with the deadline.
Does KAMALA CHS LTD have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is KAMALA CHS LTD safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), KAMALA CHS LTD is registered on MahaRERA as P51800003738, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 84 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KAMALA CHS LTD's possession date changes?
The latest dates are on KAMALA CHS LTD's MahaRERA page (P51800003738). GharKundli's Kundli Watch sends a free WhatsApp update on KAMALA CHS LTD every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KAMALA CHS LTD have?
According to GharKundli's check of MahaRERA records (updated November 2026), KAMALA CHS LTD has one building filed: KAMALA CHS LTD with 31 floors.
How big is the land of KAMALA CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), KAMALA CHS LTD stands on 855 sq m of land (about 0.2 acres), with 2,568 sq m of sanctioned built-up area.
Where can I read reviews of KAMALA CHS LTD?
Google Maps has reviews of KAMALA CHS LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KAMALA CHS LTD?
KAMALA CHS LTD by PRAVESH KIRTI KANTHER is in Iraniwadi, Mumbai (pincode 400067), near Kandivali West, Bandra, Malad West, Maharashtra, and is registered on MahaRERA as P51800003738, per GharKundli's check of MahaRERA records.
How many homes are in KAMALA CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), KAMALA CHS LTD has 110 homes in 1 tower registered on MahaRERA.
When was KAMALA CHS LTD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KAMALA CHS LTD was registered on MahaRERA on 6 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on KAMALA CHS LTD?
1 court case is listed for KAMALA CHS LTD on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of KAMALA CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PRAVESH KIRTI KANTHER.
Check it yourself on MahaRERA
- How to check the possession date of KAMALA CHS LTD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2031 in Mumbai Suburban →
Other projects in Borivali
- Gabadia Heights
- Gabadia Homes
- SAFFRONWOODS CHSL
- L&T Realty Ahana Tower A
- L&T Realty Ahana Tower B
- AVIRAHI ELEGANCE
- PARSHURAM HEIGHTS
- MARU MANSION
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.