DHARTI PRESSIDIO

by MILAN NEMJI GALA · Malad West, MumbaiAlso near Kandivali west, Borivali, Charkop

Possession date of DHARTI PRESSIDIO: 31 December 2025, moved from 30 December 2021 (48 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800012119. Status: Lapsed (registration period ended). 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about DHARTI PRESSIDIO?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of DHARTI PRESSIDIO has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT51800011058)

    Reason the builder gave MahaRERA:
    “We hereby write to seek an extension of project registration under MahaRERA in order to complete the project and obtain OC by 31/12/2022. The grant has been requested on account of delay in obtaining the required commencement certificate fo…” Read the full reason“We hereby write to seek an extension of project registration under MahaRERA in order to complete the project and obtain OC by 31/12/2022. The grant has been requested on account of delay in obtaining the required commencement certificate for the 20th floor of the project. The delay was caused due to outbreak of COVID-19. However, now the project has obtained the required CC and project shall be completed and handed over by 31/12/2022.”
  3. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51800012852)

    Reason the builder gave MahaRERA:
    “The project was stalled for construction due to pending environmental clearance approvals. We have received the required approval on 30 July 2022. Despite our best effort to complete the construction, it is unlikely to complete the construc…” Read the full reason“The project was stalled for construction due to pending environmental clearance approvals. We have received the required approval on 30 July 2022. Despite our best effort to complete the construction, it is unlikely to complete the construction by 31-12-2022. In order to maintain transparency with our customers and the authorities we humbly seek extension for project completion up to 30 June 2023. Even in order to raise construction finance, it is imperative to have subsisting RERA registration for the project.”
  4. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51800018374)

    Reason the builder gave MahaRERA: “DUE TO COVID 19 NOT ABLE TO COMPLETE PROJECT PLEASE GRANT US EXTENSION TILL 30/06/2024”
  5. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51800019822)

    Reason the builder gave MahaRERA: “Due to shortage of matireal not able to complete project please grant us extension till 31/12/2024”
  6. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800027668)

    Reason the builder gave MahaRERA:
    “The following approvals are currently in process: 1 Occupation Certificate (OC) Compliance 2. Completion Certificate from E.E. (S.P.) (P & D) 3. P-Form for Water Connection 4 No Objection Certificates (NOCs) from Various Departments (Fire,…” Read the full reason“The following approvals are currently in process: 1 Occupation Certificate (OC) Compliance 2. Completion Certificate from E.E. (S.P.) (P & D) 3. P-Form for Water Connection 4 No Objection Certificates (NOCs) from Various Departments (Fire, Water, etc.) Since these approvals require coordination with multiple regulatory bodies, their processing involves timelines beyond our control. We are actively engaged in completing all necessary formalities at the earliest. In light of the above, we kindly request an extension until 31-12-2025 to ensure the systematic completion of all pending complianc…”

Source: DHARTI PRESSIDIO’s extension records on MahaRERA (P51800012119), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on DHARTI PRESSIDIO

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800012119
Status
Lapsed (registration period ended)
Builder
MILAN NEMJI GALA
Location
Malad West, Mumbai · 400067
Project type
Others
Registered on
1 Sep 2017
Completion date at registration
December 2021
Latest completion date
December 2025
Delay so far
48 months
Homes
221
Sold or booked
100%
Towers
1
Complaints on MahaRERA
3
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of DHARTI PRESSIDIO, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DHARTI PRESSIDIO100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • DHARTI PRESSIDIO: covers o 20th Habitable floors on 29/10/2021. (Out of approved total 20th Habitable/ Floors).

Want to know when this changes? Kundli Watch sends a free WhatsApp update on DHARTI PRESSIDIO every month.

DHARTI PRESSIDIO: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK417 – 425114
2 BHK419 – 628107
Shops102 – 1,76514

The builder’s record and reviews

Milan Nemji Gala has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 12 months). 3 complaints on MahaRERA across 1 project.

Read Google reviews of DHARTI PRESSIDIO →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

DHARTI PRESSIDIO: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about DHARTI PRESSIDIO

What is the possession date of DHARTI PRESSIDIO?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DHARTI PRESSIDIO in Malad West, Mumbai is 31 December 2025 — 48 months later than 30 December 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for DHARTI PRESSIDIO?

Builders and listing sites often quote an earlier "target" date for handover. The completion date DHARTI PRESSIDIO's builder has filed on MahaRERA, the official one, is 31 December 2025, already 48 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of DHARTI PRESSIDIO extended?

According to GharKundli's check of MahaRERA records (updated October 2026), DHARTI PRESSIDIO's builder applied to MahaRERA to extend the completion date 5 times: to 31 December 2022, giving the reason "We hereby write to seek an extension of project registration under MahaRERA in order to complete the project and obtain OC by 31/12/2022. The grant has been requested on account of delay in obtaining the required commencement certificate for the 20th floor of the project. The delay was caused due to outbreak of COVID-19. However, now the project has obtained the required CC and project shall be completed and handed over by 31/12/2022."; to 31 December 2023, giving the reason "The project was stalled for construction due to pending environmental clearance approvals. We have received the required approval on 30 July 2022. Despite our best effort to complete the construction, it is unlikely to complete the construction by 31-12-2022. In order to maintain transparency with our customers and the authorities we humbly seek extension for project completion up to 30 June 2023. Even in order to raise construction finance, it is imperative to have subsisting RERA registration for the project."; to 30 June 2024, giving the reason "DUE TO COVID 19 NOT ABLE TO COMPLETE PROJECT PLEASE GRANT US EXTENSION TILL 30/06/2024"; to 31 December 2024, giving the reason "Due to shortage of matireal not able to complete project please grant us extension till 31/12/2024"; to 31 December 2025, giving the reason "The following approvals are currently in process: 1 Occupation Certificate (OC) Compliance 2. Completion Certificate from E.E. (S.P.) (P & D) 3. P-Form for Water Connection 4 No Objection Certificates (NOCs) from Various Departments (Fire, Water, etc.) Since these approvals require coordination with multiple regulatory bodies, their processing involves timelines beyond our control. We are actively engaged in completing all necessary formalities at the earliest. In light of the above, we kindly request an extension until 31-12-2025 to ensure the systematic completion of all pending complianc…".

What is the RERA number of DHARTI PRESSIDIO?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DHARTI PRESSIDIO in Malad West, Mumbai is P51800012119.

Is DHARTI PRESSIDIO registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DHARTI PRESSIDIO is registered as P51800012119 and its status is "Lapsed (registration period ended)".

What is the construction status of DHARTI PRESSIDIO?

According to GharKundli's check of MahaRERA records (updated October 2026), DHARTI PRESSIDIO's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on DHARTI PRESSIDIO is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does DHARTI PRESSIDIO have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is DHARTI PRESSIDIO safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), DHARTI PRESSIDIO is registered on MahaRERA as P51800012119, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 48 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if DHARTI PRESSIDIO's possession date changes?

The latest dates are on DHARTI PRESSIDIO's MahaRERA page (P51800012119). GharKundli's Kundli Watch sends a free WhatsApp update on DHARTI PRESSIDIO every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does DHARTI PRESSIDIO have?

According to GharKundli's check of MahaRERA records (updated October 2026), DHARTI PRESSIDIO has one building filed: DHARTI PRESSIDIO with 25 floors and 235 units.

What are the flat sizes (carpet area) in DHARTI PRESSIDIO?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for DHARTI PRESSIDIO: 1 BHK: 417 to 425 sq ft carpet (114 homes); 2 BHK: 419 to 628 sq ft carpet (107 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of DHARTI PRESSIDIO?

According to GharKundli's check of MahaRERA records (updated October 2026), DHARTI PRESSIDIO stands on 2,828 sq m of land (about 0.7 acres), with 12,721 sq m of sanctioned built-up area and 483 sq m of recreational open space.

What is the track record of DHARTI PRESSIDIO's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Milan Nemji Gala has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 12 months). 3 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of DHARTI PRESSIDIO?

Google Maps has reviews of DHARTI PRESSIDIO written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is DHARTI PRESSIDIO?

DHARTI PRESSIDIO by MILAN NEMJI GALA is in Malad West, Mumbai (pincode 400067), near Kandivali west, Borivali, Charkop, Maharashtra, and is registered on MahaRERA as P51800012119, per GharKundli's check of MahaRERA records.

How many homes are in DHARTI PRESSIDIO?

According to GharKundli's check of MahaRERA records (updated October 2026), DHARTI PRESSIDIO has 221 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was DHARTI PRESSIDIO registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DHARTI PRESSIDIO was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on DHARTI PRESSIDIO?

No court cases are listed for DHARTI PRESSIDIO on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of DHARTI PRESSIDIO?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MILAN NEMJI GALA, which has 1 other project registered on MahaRERA.

Other projects in Malad West

All 318 projects in Kandivali West (400067) →

Other projects by MILAN NEMJI GALA

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.