by Omkar Vijay Vidhate · Ycm Open Univesity, NashikAlso near Sukena, B.S. Nagar, Nashik Road

Possession date of Belvedere Heights: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600051431, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Belvedere Heights?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Belvedere Heights has moved

  1. 31 December 2028

    Completion date given when the project was registered

  2. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Belvedere Heights’s extension records on MahaRERA (P51600051431), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Belvedere Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600051431
Status
Registered and active
Builder
Omkar Vijay Vidhate
Location
Ycm Open Univesity, Nashik · 422222
Project type
Others
Registered on
14 Jun 2023
Completion date at registration
December 2028
Latest completion date
April 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
16
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Belvedere Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Belvedere Heights100%50%10%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Belvedere Heights every month.

Belvedere Heights: buildings, flats and land, as filed on MahaRERA

  • Buildings: Belvedere Heights (7 floors)
  • Land: 631 sq m (about 0.2 acres) · sanctioned built-up 1,394 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Belvedere Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Belvedere Heights: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Belvedere Heights

What is the possession date of Belvedere Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Belvedere Heights in Ycm Open Univesity, Nashik is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Belvedere Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Belvedere Heights's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Belvedere Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Belvedere Heights in Ycm Open Univesity, Nashik is P51600051431.

Is Belvedere Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Belvedere Heights is registered as P51600051431 and its status is "Registered and active".

What is the construction status of Belvedere Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Belvedere Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Belvedere Heights is 50% done and internal work 10%. GharKundli's full report compares construction progress with the deadline.

Does Belvedere Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Belvedere Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Belvedere Heights is registered on MahaRERA as P51600051431, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Belvedere Heights's possession date changes?

The latest dates are on Belvedere Heights's MahaRERA page (P51600051431). GharKundli's Kundli Watch sends a free WhatsApp update on Belvedere Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Belvedere Heights have?

According to GharKundli's check of MahaRERA records (updated November 2026), Belvedere Heights has one building filed: Belvedere Heights with 7 floors.

How big is the land of Belvedere Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Belvedere Heights stands on 631 sq m of land (about 0.2 acres), with 1,394 sq m of sanctioned built-up area.

Where can I read reviews of Belvedere Heights?

Google Maps has reviews of Belvedere Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Belvedere Heights?

Belvedere Heights by Omkar Vijay Vidhate is in Ycm Open Univesity, Nashik (pincode 422222), near Sukena, B.S. Nagar, Nashik Road, Maharashtra, and is registered on MahaRERA as P51600051431, per GharKundli's check of MahaRERA records.

How many homes are in Belvedere Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Belvedere Heights has 16 homes in 1 tower registered on MahaRERA.

When was Belvedere Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Belvedere Heights was registered on MahaRERA on 14 June 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Belvedere Heights?

No court cases are listed for Belvedere Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Belvedere Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Omkar Vijay Vidhate.

All projects with possession due in 2029 in Nashik →

Other projects in pincode 422222

All 24 projects in Ycm Open Univesity (422222) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.