by Ashwini Buildcon · Dindori S.O (Nashik), Nashik

Possession date of Sai Aanand: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600052834, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Sai Aanand?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sai Aanand has moved

  1. 31 December 2028

    Completion date given when the project was registered

  2. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Sai Aanand’s extension records on MahaRERA (P51600052834), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sai Aanand

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600052834
Status
Registered and active
Builder
Ashwini Buildcon
Location
Dindori S.O (Nashik), Nashik · 422202
Project type
Others
Registered on
5 Oct 2023
Completion date at registration
December 2028
Latest completion date
April 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
32
Sold or booked
48%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Sai Aanand, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sai Aanand100%100%97%95%

Commencement certificate (CC), as filed on MahaRERA

  • Sai Aanand: covers 6 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sai Aanand every month.

Sai Aanand: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Sai Aanand →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sai Aanand: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sai Aanand

What is the possession date of Sai Aanand?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sai Aanand in Dindori S.O (Nashik), Nashik is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Sai Aanand?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sai Aanand's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Sai Aanand?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sai Aanand in Dindori S.O (Nashik), Nashik is P51600052834.

Is Sai Aanand registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aanand is registered as P51600052834 and its status is "Registered and active".

What is the construction status of Sai Aanand?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aanand's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sai Aanand is 100% done and internal work 97%. GharKundli's full report compares construction progress with the deadline.

Does Sai Aanand have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Sai Aanand safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aanand is registered on MahaRERA as P51600052834, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Sai Aanand's possession date changes?

The latest dates are on Sai Aanand's MahaRERA page (P51600052834). GharKundli's Kundli Watch sends a free WhatsApp update on Sai Aanand every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sai Aanand have?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aanand has one building filed: Sai Aanand with 6 floors and 45 units.

How big is the land of Sai Aanand?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aanand stands on 946 sq m of land (about 0.2 acres), with 2,111 sq m of sanctioned built-up area.

Where can I read reviews of Sai Aanand?

Google Maps has reviews of Sai Aanand written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sai Aanand?

Sai Aanand by Ashwini Buildcon is in Dindori S.O (Nashik), Nashik (pincode 422202), Maharashtra, and is registered on MahaRERA as P51600052834, per GharKundli's check of MahaRERA records.

How many homes are in Sai Aanand?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aanand has 32 homes in 1 tower registered on MahaRERA, and 48% of them are sold or booked.

When was Sai Aanand registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aanand was registered on MahaRERA on 5 October 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Sai Aanand?

No court cases are listed for Sai Aanand on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Sai Aanand?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Ashwini Buildcon.

All projects with possession due in 2029 in Nashik →

Other projects in pincode 422202

All 10 projects in Next to Unnati School (422202) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.