Possession date of THE AVENUE MILESTONE - TOWER 1 - Wing A: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600053718, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about THE AVENUE MILESTONE - TOWER 1 - Wing A?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of THE AVENUE MILESTONE - TOWER 1 - Wing A has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: THE AVENUE MILESTONE - TOWER 1 - Wing A’s extension records on MahaRERA (P51600053718), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on THE AVENUE MILESTONE - TOWER 1 - Wing A

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51600053718
Status
Registered and active
Builder
NASHIK CONSTRUWELL PRIVATE LIMITED
Location
Govind Nagar, Nashik · 422009
Project type
Others
Registered on
22 Nov 2023
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
30
Sold or booked
39%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of THE AVENUE MILESTONE - TOWER 1 - Wing A, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
THE AVENUE MILESTONE - TOWER 1 - Wing A100%100%95%0%

Commencement certificate (CC), as filed on MahaRERA

  • THE AVENUE MILESTONE - TOWER 1 - Wing A: covers 17 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on THE AVENUE MILESTONE - TOWER 1 - Wing A every month.

THE AVENUE MILESTONE - TOWER 1 - Wing A: buildings, flats and land, as filed on MahaRERA

  • Buildings: THE AVENUE MILESTONE - TOWER 1 - Wing A (17 floors, 33 units)
  • Land: 1,854 sq m (about 0.5 acres) · sanctioned built-up 7,347 sq m
  • Boundaries filed include: 7 5 Mtr colony road

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of THE AVENUE MILESTONE - TOWER 1 - Wing A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

THE AVENUE MILESTONE - TOWER 1 - Wing A: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about THE AVENUE MILESTONE - TOWER 1 - Wing A

What is the possession date of THE AVENUE MILESTONE - TOWER 1 - Wing A?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for THE AVENUE MILESTONE - TOWER 1 - Wing A in Govind Nagar, Nashik is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for THE AVENUE MILESTONE - TOWER 1 - Wing A?

Builders and listing sites often quote an earlier "target" date for handover. The completion date THE AVENUE MILESTONE - TOWER 1 - Wing A's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of THE AVENUE MILESTONE - TOWER 1 - Wing A?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of THE AVENUE MILESTONE - TOWER 1 - Wing A in Govind Nagar, Nashik is P51600053718.

Is THE AVENUE MILESTONE - TOWER 1 - Wing A registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), THE AVENUE MILESTONE - TOWER 1 - Wing A is registered as P51600053718 and its status is "Registered and active".

What is the construction status of THE AVENUE MILESTONE - TOWER 1 - Wing A?

According to GharKundli's check of MahaRERA records (updated November 2026), THE AVENUE MILESTONE - TOWER 1 - Wing A's status on MahaRERA is "Registered and active". As filed by the builder, slab work on THE AVENUE MILESTONE - TOWER 1 - Wing A is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does THE AVENUE MILESTONE - TOWER 1 - Wing A have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is THE AVENUE MILESTONE - TOWER 1 - Wing A safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), THE AVENUE MILESTONE - TOWER 1 - Wing A is registered on MahaRERA as P51600053718, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does THE AVENUE MILESTONE - TOWER 1 - Wing A have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: THE AVENUE MILESTONE - TOWER 2 - Wing B (P51600053640, possession 30 Apr 2029). Check that your agreement names the registration of your own wing.

How can I get updates if THE AVENUE MILESTONE - TOWER 1 - Wing A's possession date changes?

The latest dates are on THE AVENUE MILESTONE - TOWER 1 - Wing A's MahaRERA page (P51600053718). GharKundli's Kundli Watch sends a free WhatsApp update on THE AVENUE MILESTONE - TOWER 1 - Wing A every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does THE AVENUE MILESTONE - TOWER 1 - Wing A have?

According to GharKundli's check of MahaRERA records (updated November 2026), THE AVENUE MILESTONE - TOWER 1 - Wing A has one building filed: THE AVENUE MILESTONE - TOWER 1 - Wing A with 17 floors and 33 units.

How big is the land of THE AVENUE MILESTONE - TOWER 1 - Wing A?

According to GharKundli's check of MahaRERA records (updated November 2026), THE AVENUE MILESTONE - TOWER 1 - Wing A stands on 1,854 sq m of land (about 0.5 acres), with 7,347 sq m of sanctioned built-up area.

Where can I read reviews of THE AVENUE MILESTONE - TOWER 1 - Wing A?

Google Maps has reviews of THE AVENUE MILESTONE - TOWER 1 - Wing A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is THE AVENUE MILESTONE - TOWER 1 - Wing A?

THE AVENUE MILESTONE - TOWER 1 - Wing A by NASHIK CONSTRUWELL PRIVATE LIMITED is in Govind Nagar, Nashik (pincode 422009), Maharashtra, and is registered on MahaRERA as P51600053718, per GharKundli's check of MahaRERA records. Its boundaries filed there include 7 5 Mtr colony road.

How many homes are in THE AVENUE MILESTONE - TOWER 1 - Wing A?

According to GharKundli's check of MahaRERA records (updated November 2026), THE AVENUE MILESTONE - TOWER 1 - Wing A has 30 homes in 1 tower registered on MahaRERA, and 39% of them are sold or booked.

When was THE AVENUE MILESTONE - TOWER 1 - Wing A registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), THE AVENUE MILESTONE - TOWER 1 - Wing A was registered on MahaRERA on 22 November 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on THE AVENUE MILESTONE - TOWER 1 - Wing A?

No court cases are listed for THE AVENUE MILESTONE - TOWER 1 - Wing A on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of THE AVENUE MILESTONE - TOWER 1 - Wing A?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NASHIK CONSTRUWELL PRIVATE LIMITED, which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Nashik →

Other projects in Govind Nagar

All 209 projects in CIDCO Colony (422009) →

Other projects by NASHIK CONSTRUWELL PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.