by The Bombay Dyeing and Manufacturing Company Limited · Wadala, MumbaiAlso near Ballard Estate, Sewri, Fort
Possession: ICC is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900008726. Status: Completed. 70 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ICC?
How the possession date of ICC has moved
31 August 2019
Completion date given when the project was registered
31 March 2025
Extended at the builder's request (MahaRERA application EXT51900017686)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project received Part OC before the due date, all the units that have been sold have taken possession. The units that have not receive…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project received Part OC before the due date, all the units that have been sold have taken possession. The units that have not received OC, remain unsold and we intend to retain it for the company as of now.”31 March 2026
Extended at the builder's request (MahaRERA application EXT51900028103)
Reason the builder gave MahaRERA: “AS PER ATTACHMENT”
Source: ICC’s extension records on MahaRERA (P51900008726), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ICC
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 70 complaints and 26 court cases, and how it ended
- Construction pace against the March 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900008726
- Status
- Completed
- Builder
- The Bombay Dyeing and Manufacturing Company Limited
- Location
- Wadala, Mumbai · 400015
- Project type
- Residential / Group Housing
- Registered on
- 19 Aug 2017
- Completion date at registration
- August 2019
- Latest completion date
- March 2026
- Delay so far
- 79 months
- Homes
- 537
- Towers
- 2
- Complaints on MahaRERA
- 70
- Court cases listed
- 26
- Appeals at the tribunal
- 46
- Title report on file
- Not found
Construction progress of ICC, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ONE ICC | 100% | 100% | 100% | 100% |
| TWO ICC | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ICC every month.
ICC: buildings, flats and land, as filed on MahaRERA
- Buildings: ONE ICC (61 floors) · TWO ICC (68 floors)
- Land: 3,090 sq m (about 0.8 acres) · sanctioned built-up 96,964 sq m · recreational space 7,642 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
The Bombay Dyeing And Manufacturing has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 56 months); 3 still being built, none past the promised date yet. 73 complaints on MahaRERA across 4 projects.
Read Google reviews of ICC →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ICC: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ICC
What is the possession date of ICC?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ICC in Wadala, Mumbai is 31 March 2026 — 79 months later than 31 August 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for ICC?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ICC's builder has filed on MahaRERA, the official one, is 31 March 2026, already 79 months later than the 31 August 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ICC extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ICC's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project received Part OC before the due date, all the units that have been sold have taken possession. The units that have not received OC, remain unsold and we intend to retain it for the company as of now."; to 31 March 2026, giving the reason "AS PER ATTACHMENT".
What is the RERA number of ICC?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ICC in Wadala, Mumbai is P51900008726.
Is ICC registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ICC is registered as P51900008726 and its status is "Completed".
What is the construction status of ICC?
According to GharKundli's check of MahaRERA records (updated October 2026), ICC's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does ICC have complaints on MahaRERA?
70 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ICC safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ICC is registered on MahaRERA as P51900008726, its MahaRERA status is "Completed", its completion date has moved 79 months since registration and 70 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ICC's possession date changes?
The latest dates are on ICC's MahaRERA page (P51900008726). GharKundli's Kundli Watch sends a free WhatsApp update on ICC every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ICC have?
According to GharKundli's check of MahaRERA records (updated October 2026), ICC has 2 buildings filed: ONE ICC with 61 floors; TWO ICC with 68 floors.
How big is the land of ICC?
According to GharKundli's check of MahaRERA records (updated October 2026), ICC stands on 3,090 sq m of land (about 0.8 acres), with 96,964 sq m of sanctioned built-up area and 7,642 sq m of recreational open space.
What is the track record of ICC's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), The Bombay Dyeing And Manufacturing has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 56 months); 3 still being built, none past the promised date yet. 73 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ICC?
Google Maps has reviews of ICC written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 70 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ICC?
ICC by The Bombay Dyeing and Manufacturing Company Limited is in Wadala, Mumbai (pincode 400015), near Ballard Estate, Sewri, Fort, Maharashtra, and is registered on MahaRERA as P51900008726, per GharKundli's check of MahaRERA records.
How many homes are in ICC?
According to GharKundli's check of MahaRERA records (updated October 2026), ICC has 537 homes in 2 towers registered on MahaRERA.
When was ICC registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ICC was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on ICC?
26 court cases are listed for ICC on MahaRERA, and 46 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of ICC?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is The Bombay Dyeing and Manufacturing Company Limited.
Check it yourself on MahaRERA
- How to check the possession date of ICC
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Wadala
- Shanti Kunj- A Project by Tridhaatu
- Skye 31
- Lodha NCP Tower - 2
- THREE ICC-B WING
- THREE ICC-C WING
- THREE ICC-A WING
- Lodha NCP Tower - 1
- Godrej Horizon Phase II
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.