CHINTAMANI GLORY

by CHINTAMANI REALTY · Matunga, MumbaiAlso near Ghatkopar- West, Vile Parle West, Ghatkopar Kirol

Possession date of CHINTAMANI GLORY: 30 June 2022, moved from 31 March 2019 (39 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800009774. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (June 2022) has passed.

What do you want to know about CHINTAMANI GLORY?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on CHINTAMANI GLORY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the June 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800009774
Status
Lapsed (registration period ended)
Builder
CHINTAMANI REALTY
Location
Matunga, Mumbai · 400084
Project type
Residential / Group Housing
Registered on
22 Aug 2017
Completion date at registration
March 2019
Latest completion date
June 2022
Delay so far
39 months
Homes
45
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of CHINTAMANI GLORY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
CHINTAMANI GLORY100%8%50%50%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on CHINTAMANI GLORY every month.

CHINTAMANI GLORY: buildings, flats and land, as filed on MahaRERA

  • Buildings: CHINTAMANI GLORY (1 floors)
  • Land: 913 sq m (about 0.2 acres) · sanctioned built-up 2,740 sq m · recreational space 913 sq m
  • Boundaries filed include: 6 WIDE MUNICIPAL ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of CHINTAMANI GLORY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

CHINTAMANI GLORY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about CHINTAMANI GLORY

What is the possession date of CHINTAMANI GLORY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for CHINTAMANI GLORY in Matunga, Mumbai is 30 June 2022 — 39 months later than 31 March 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for CHINTAMANI GLORY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date CHINTAMANI GLORY's builder has filed on MahaRERA, the official one, is 30 June 2022, already 39 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of CHINTAMANI GLORY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of CHINTAMANI GLORY in Matunga, Mumbai is P51800009774.

Is CHINTAMANI GLORY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), CHINTAMANI GLORY is registered as P51800009774 and its status is "Lapsed (registration period ended)".

What is the construction status of CHINTAMANI GLORY?

According to GharKundli's check of MahaRERA records (updated November 2026), CHINTAMANI GLORY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on CHINTAMANI GLORY is 8% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does CHINTAMANI GLORY have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is CHINTAMANI GLORY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), CHINTAMANI GLORY is registered on MahaRERA as P51800009774, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 39 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if CHINTAMANI GLORY's possession date changes?

The latest dates are on CHINTAMANI GLORY's MahaRERA page (P51800009774). GharKundli's Kundli Watch sends a free WhatsApp update on CHINTAMANI GLORY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does CHINTAMANI GLORY have?

According to GharKundli's check of MahaRERA records (updated November 2026), CHINTAMANI GLORY has one building filed: CHINTAMANI GLORY with 1 floors.

How big is the land of CHINTAMANI GLORY?

According to GharKundli's check of MahaRERA records (updated November 2026), CHINTAMANI GLORY stands on 913 sq m of land (about 0.2 acres), with 2,740 sq m of sanctioned built-up area and 913 sq m of recreational open space.

Where can I read reviews of CHINTAMANI GLORY?

Google Maps has reviews of CHINTAMANI GLORY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is CHINTAMANI GLORY?

CHINTAMANI GLORY by CHINTAMANI REALTY is in Matunga, Mumbai (pincode 400084), near Ghatkopar- West, Vile Parle West, Ghatkopar Kirol, Maharashtra, and is registered on MahaRERA as P51800009774, per GharKundli's check of MahaRERA records. Its boundaries filed there include 6 WIDE MUNICIPAL ROAD.

How many homes are in CHINTAMANI GLORY?

According to GharKundli's check of MahaRERA records (updated November 2026), CHINTAMANI GLORY has 45 homes in 1 tower registered on MahaRERA.

When was CHINTAMANI GLORY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), CHINTAMANI GLORY was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on CHINTAMANI GLORY?

No court cases are listed for CHINTAMANI GLORY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of CHINTAMANI GLORY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is CHINTAMANI REALTY.

All projects in Barve Nagar (400084) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.