ARKADE EARTH-ASPEN
by Arkade Developers Private Limited · Kanjurmarg East, MumbaiAlso near Bhandup West, Kanjur East, Bhandup East
Possession date of ARKADE EARTH-ASPEN: 30 December 2024. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800006579. Status: Lapsed (registration period ended). 7 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2024) has passed.
What do you want to know about ARKADE EARTH-ASPEN?
GharKundli’s full report on ARKADE EARTH-ASPEN
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 7 complaints and 2 court cases, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800006579
- Status
- Lapsed (registration period ended)
- Builder
- Arkade Developers Private Limited
- Location
- Kanjurmarg East, Mumbai · 400042
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- December 2024
- Latest completion date
- December 2024
- Homes
- 86
- Towers
- 1
- Complaints on MahaRERA
- 7
- Court cases listed
- 2
- Appeals at the tribunal
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 12
Construction progress of ARKADE EARTH-ASPEN, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ASPEN | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ARKADE EARTH-ASPEN every month.
ARKADE EARTH-ASPEN: buildings, flats and land, as filed on MahaRERA
- Buildings: ASPEN (24 floors)
- Land: 254 sq m (about 0.1 acres) · sanctioned built-up 3,267 sq m
- Boundaries filed include: INDIRA NAGAR
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Arkade Developers (a group of 3 linked companies) has 29 projects on MahaRERA since 2017, this one included. Of the 29 GharKundli has checked: 16 finished, all within the promised date; 10 still being built, none past the promised date yet; 3 lapsed. 26 complaints on MahaRERA across 7 projects.
Read Google reviews of ARKADE EARTH-ASPEN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ARKADE EARTH-ASPEN: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ARKADE EARTH-ASPEN
What is the possession date of ARKADE EARTH-ASPEN?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ARKADE EARTH-ASPEN in Kanjurmarg East, Mumbai is 30 December 2024. That date has already passed.
Is the builder's possession date different from the MahaRERA date for ARKADE EARTH-ASPEN?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ARKADE EARTH-ASPEN's builder has filed on MahaRERA, the official one, is 30 December 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of ARKADE EARTH-ASPEN?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ARKADE EARTH-ASPEN in Kanjurmarg East, Mumbai is P51800006579.
Is ARKADE EARTH-ASPEN registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ARKADE EARTH-ASPEN is registered as P51800006579 and its status is "Lapsed (registration period ended)".
What is the construction status of ARKADE EARTH-ASPEN?
According to GharKundli's check of MahaRERA records (updated November 2026), ARKADE EARTH-ASPEN's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on ASPEN is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does ARKADE EARTH-ASPEN have complaints on MahaRERA?
7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ARKADE EARTH-ASPEN safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), ARKADE EARTH-ASPEN is registered on MahaRERA as P51800006579, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ARKADE EARTH-ASPEN's possession date changes?
The latest dates are on ARKADE EARTH-ASPEN's MahaRERA page (P51800006579). GharKundli's Kundli Watch sends a free WhatsApp update on ARKADE EARTH-ASPEN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ARKADE EARTH-ASPEN have?
According to GharKundli's check of MahaRERA records (updated November 2026), ARKADE EARTH-ASPEN has one building filed: ASPEN with 24 floors.
How big is the land of ARKADE EARTH-ASPEN?
According to GharKundli's check of MahaRERA records (updated November 2026), ARKADE EARTH-ASPEN stands on 254 sq m of land (about 0.1 acres), with 3,267 sq m of sanctioned built-up area.
What is the track record of ARKADE EARTH-ASPEN's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Arkade Developers (a group of 3 linked companies) has 29 projects on MahaRERA since 2017, this one included. Of the 29 GharKundli has checked: 16 finished, all within the promised date; 10 still being built, none past the promised date yet; 3 lapsed. 26 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ARKADE EARTH-ASPEN?
Google Maps has reviews of ARKADE EARTH-ASPEN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ARKADE EARTH-ASPEN?
ARKADE EARTH-ASPEN by Arkade Developers Private Limited is in Kanjurmarg East, Mumbai (pincode 400042), near Bhandup West, Kanjur East, Bhandup East, Maharashtra, and is registered on MahaRERA as P51800006579, per GharKundli's check of MahaRERA records. Its boundaries filed there include INDIRA NAGAR.
How many homes are in ARKADE EARTH-ASPEN?
According to GharKundli's check of MahaRERA records (updated November 2026), ARKADE EARTH-ASPEN has 86 homes in 1 tower registered on MahaRERA.
When was ARKADE EARTH-ASPEN registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ARKADE EARTH-ASPEN was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on ARKADE EARTH-ASPEN?
2 court cases are listed for ARKADE EARTH-ASPEN on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of ARKADE EARTH-ASPEN?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Arkade Developers Private Limited, which has 12 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ARKADE EARTH-ASPEN
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kanjurmarg East
- Runwal Bliss - Wing F
- Runwal Meadows-Aster
- Runwal Meadows-Daisy
- Runwal Avenue Wing K
- Runwal Avenue Wing-J
- Runwal Bliss - Wing H
- Runwal Bliss - Wing G
- Runwal Commerz - Tower 1
Other projects by Arkade Developers Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.