Shree Nakoda Heights
by M/s Royal Developers · Mazgaon, MumbaiAlso near Byculla, Tank Road, Chinchbunder
Possession date of Shree Nakoda Heights: 31 December 2024, moved from 31 December 2019 (60 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900008923. Status: Lapsed (registration period ended). 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2024) has passed.
What do you want to know about Shree Nakoda Heights?
How the possession date of Shree Nakoda Heights has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51900005059)
Reason the builder gave MahaRERA: “Application as attached.”
31 December 2024
Extended at the builder's request (MahaRERA application EXT51900011355)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 75% allottees for purpose of extension of RERA registration period of the said project.”
Source: Shree Nakoda Heights’s extension records on MahaRERA (P51900008923), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shree Nakoda Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints and 1 court case, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900008923
- Status
- Lapsed (registration period ended)
- Builder
- M/s Royal Developers
- Location
- Mazgaon, Mumbai · 400033
- Project type
- Residential / Group Housing
- Registered on
- 19 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2024
- Delay so far
- 60 months
- Homes
- 208
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 1
- Appeals at the tribunal
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Shree Nakoda Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Shree Nakoda Heights | 0% | 70% | 10% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shree Nakoda Heights every month.
Shree Nakoda Heights: buildings, flats and land, as filed on MahaRERA
- Buildings: Shree Nakoda Heights (27 floors)
- Land: 1,916 sq m (about 0.5 acres) · sanctioned built-up 8,062 sq m
- Boundaries filed include: Umesh Shalunkhe Marg, Rambhau Bhogle Marg
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shree Nakoda Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shree Nakoda Heights: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Shree Nakoda Heights
What is the possession date of Shree Nakoda Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shree Nakoda Heights in Mazgaon, Mumbai is 31 December 2024 — 60 months later than 31 December 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Shree Nakoda Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shree Nakoda Heights's builder has filed on MahaRERA, the official one, is 31 December 2024, already 60 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shree Nakoda Heights extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Nakoda Heights's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2020, giving the reason "Application as attached."; to 31 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 75% allottees for purpose of extension of RERA registration period of the said project.".
What is the RERA number of Shree Nakoda Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shree Nakoda Heights in Mazgaon, Mumbai is P51900008923.
Is Shree Nakoda Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Nakoda Heights is registered as P51900008923 and its status is "Lapsed (registration period ended)".
What is the construction status of Shree Nakoda Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Nakoda Heights's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Shree Nakoda Heights is 70% done and internal work 10%. GharKundli's full report compares construction progress with the deadline.
Does Shree Nakoda Heights have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Shree Nakoda Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Nakoda Heights is registered on MahaRERA as P51900008923, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 60 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Shree Nakoda Heights's possession date changes?
The latest dates are on Shree Nakoda Heights's MahaRERA page (P51900008923). GharKundli's Kundli Watch sends a free WhatsApp update on Shree Nakoda Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shree Nakoda Heights have?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Nakoda Heights has one building filed: Shree Nakoda Heights with 27 floors.
How big is the land of Shree Nakoda Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Nakoda Heights stands on 1,916 sq m of land (about 0.5 acres), with 8,062 sq m of sanctioned built-up area.
Where can I read reviews of Shree Nakoda Heights?
Google Maps has reviews of Shree Nakoda Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Shree Nakoda Heights?
Shree Nakoda Heights by M/s Royal Developers is in Mazgaon, Mumbai (pincode 400033), near Byculla, Tank Road, Chinchbunder, Maharashtra, and is registered on MahaRERA as P51900008923, per GharKundli's check of MahaRERA records. Its boundaries filed there include Umesh Shalunkhe Marg, Rambhau Bhogle Marg.
How many homes are in Shree Nakoda Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Nakoda Heights has 208 homes in 1 tower registered on MahaRERA.
When was Shree Nakoda Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Nakoda Heights was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Shree Nakoda Heights?
1 court case is listed for Shree Nakoda Heights on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Shree Nakoda Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/s Royal Developers, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Shree Nakoda Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Mazgaon
- Presidence Eternia
- 52 Avenue
- Atlantis Residency
- The Aga Hall Estate
- An-Nur Residency
- M4 Cledor
- 379 Vista
- Presidence Marina
Other projects by M/s Royal Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.