Skip to content
GharKundli

KANCHANGIRI

by GOODWILL BUILDERS · Village Wadhwan, MumbaiAlso near Kandivali East, Malad east, Kandivali West

Possession: KANCHANGIRI is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800009001. Status: Completed. Its completion date has moved from December 2023 to January 2027: 33 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about KANCHANGIRI?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of KANCHANGIRI has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 29 December 2024

    Extended at the builder's request (MahaRERA application EXT51800017554)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”
  3. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800024954)

    Reason the builder gave MahaRERA:
    “As per Order No. 40 Dated 27/12/2022 we are applying for Extension without majority consents of the allottees. We have also received the Order from the Chairperson of MahaRERA Mr. Manoj Saunik for the approval of extension As per Order No.…” Read the full reason“As per Order No. 40 Dated 27/12/2022 we are applying for Extension without majority consents of the allottees. We have also received the Order from the Chairperson of MahaRERA Mr. Manoj Saunik for the approval of extension As per Order No. 40 for the same which has been uploaded in the application for the extension.”
  4. 15 September 2026

    Extended at the builder's request (MahaRERA application EA09062501457)

    Reason the builder gave MahaRERA:
    “The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 29/08/2025 and we have also initiated the process for…” Read the full reason“The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 29/08/2025 and we have also initiated the process for the possession as well. In view of this as the said project obtained full OC uploading consents from allottees will not be required. To provide assurance and facilitate a smooth completion process, we are closely monitoring the remaining activities, ensuring timely execution, and addressing any issues that may arise. This proactive approach aims to ensure…”
  5. 15 January 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: KANCHANGIRI’s extension records on MahaRERA (P51800009001), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on KANCHANGIRI

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800009001
Status
Completed
Builder
GOODWILL BUILDERS
Location
Village Wadhwan, Mumbai · 400101
Project type
Others
Registered on
19 Aug 2017
Completion date at registration
December 2023
Latest completion date
January 2027
Delay so far
33 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
155
Sold or booked
62%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
MahaRERA regulatory orders
1
Title report on file
Not found

Construction progress of KANCHANGIRI, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KANCHANGIRI100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • KANCHANGIRI: covers 28 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on KANCHANGIRI every month.

KANCHANGIRI: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK392 – 1,29467
2 BHK770 – 83043
1 BHK505 – 57723
4 BHK1,565 – 1,62622
Shops136 – 1,3638
Office Space2,5731
  • Buildings: KANCHANGIRI (28 floors, 164 units)
  • Car parking: 266 covered
  • Land: 5,399 sq m (about 1.3 acres) · sanctioned built-up 16,956 sq m · recreational space 576 sq m
  • Boundaries filed include: Chakravarti Ashok Road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Hindustan Klockner Switchgear (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 17 months); 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of KANCHANGIRI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

KANCHANGIRI: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KANCHANGIRI

What is the possession date of KANCHANGIRI?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KANCHANGIRI in Village Wadhwan, Mumbai is 15 January 2027 — 33 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for KANCHANGIRI?

Builders and listing sites often quote an earlier "target" date for handover. The completion date KANCHANGIRI's builder has filed on MahaRERA, the official one, is 15 January 2027, already 33 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of KANCHANGIRI extended?

According to GharKundli's check of MahaRERA records (updated October 2026), KANCHANGIRI's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 30 June 2025, giving the reason "As per Order No. 40 Dated 27/12/2022 we are applying for Extension without majority consents of the allottees. We have also received the Order from the Chairperson of MahaRERA Mr. Manoj Saunik for the approval of extension As per Order No. 40 for the same which has been uploaded in the application for the extension."; to 15 September 2026, giving the reason "The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 29/08/2025 and we have also initiated the process for the possession as well. In view of this as the said project obtained full OC uploading consents from allottees will not be required. To provide assurance and facilitate a smooth completion process, we are closely monitoring the remaining activities, ensuring timely execution, and addressing any issues that may arise. This proactive approach aims to ensure…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of KANCHANGIRI?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KANCHANGIRI in Village Wadhwan, Mumbai is P51800009001.

Is KANCHANGIRI registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KANCHANGIRI is registered as P51800009001 and its status is "Completed".

What is the construction status of KANCHANGIRI?

According to GharKundli's check of MahaRERA records (updated October 2026), KANCHANGIRI's status on MahaRERA is "Completed". As filed by the builder, slab work on KANCHANGIRI is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does KANCHANGIRI have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is KANCHANGIRI safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), KANCHANGIRI is registered on MahaRERA as P51800009001, its MahaRERA status is "Completed", its completion date has moved 33 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if KANCHANGIRI's possession date changes?

The latest dates are on KANCHANGIRI's MahaRERA page (P51800009001). GharKundli's Kundli Watch sends a free WhatsApp update on KANCHANGIRI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does KANCHANGIRI have?

According to GharKundli's check of MahaRERA records (updated October 2026), KANCHANGIRI has one building filed: KANCHANGIRI with 28 floors and 164 units.

What are the flat sizes (carpet area) in KANCHANGIRI?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for KANCHANGIRI: 3 BHK: 392 to 1294 sq ft carpet (67 homes); 2 BHK: 770 to 830 sq ft carpet (43 homes); 1 BHK: 505 to 577 sq ft carpet (23 homes); 4 BHK: 1565 to 1626 sq ft carpet (22 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does KANCHANGIRI have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 266 covered car parking spaces for KANCHANGIRI.

How big is the land of KANCHANGIRI?

According to GharKundli's check of MahaRERA records (updated October 2026), KANCHANGIRI stands on 5,399 sq m of land (about 1.3 acres), with 16,956 sq m of sanctioned built-up area and 576 sq m of recreational open space.

What is the track record of KANCHANGIRI's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Hindustan Klockner Switchgear (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 17 months); 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of KANCHANGIRI?

Google Maps has reviews of KANCHANGIRI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is KANCHANGIRI?

KANCHANGIRI by GOODWILL BUILDERS is in Village Wadhwan, Mumbai (pincode 400101), near Kandivali East, Malad east, Kandivali West, Maharashtra, and is registered on MahaRERA as P51800009001, per GharKundli's check of MahaRERA records. Its boundaries filed there include Chakravarti Ashok Road.

How many homes are in KANCHANGIRI?

According to GharKundli's check of MahaRERA records (updated October 2026), KANCHANGIRI has 155 homes in 1 tower registered on MahaRERA, and 62% of them are sold or booked.

When was KANCHANGIRI registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KANCHANGIRI was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on KANCHANGIRI?

No court cases are listed for KANCHANGIRI on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of KANCHANGIRI?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GOODWILL BUILDERS.

Other projects in Borivali

All 113 projects in Kandivali East (400101) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.