Ruparel Elara
by Shree Siddhivinayak Infrastructure & Realty (Ruparel) · Matunga W, MumbaiAlso near Kandivali West, Malad West, Bandra
Possession: Ruparel Elara is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800014328. Status: Completed. MahaRERA has issued a regulatory order on this project. 5 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Ruparel Elara?
GharKundli’s full report on Ruparel Elara
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 complaints, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800014328
- Status
- Completed
- Builder
- Shree Siddhivinayak Infrastructure & Realty
- Location
- Matunga W, Mumbai · 400067
- Project type
- Residential / Group Housing
- Registered on
- 23 Nov 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2023
- Delay so far
- 48 months
- Homes
- 84
- Towers
- 1
- Complaints on MahaRERA
- 5
- Court cases listed
- 0
- Appeals at the tribunal
- 3
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Ruparel Elara, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Ruparel Elara | 100% | 90% | 55% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ruparel Elara every month.
Ruparel Elara: buildings, flats and land, as filed on MahaRERA
- Buildings: Ruparel Elara (24 floors)
- Land: 1,303 sq m (about 0.3 acres) · sanctioned built-up 3,818 sq m · recreational space 110 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Ruparel Infra & Realty (a group of 12 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 47 months); 13 still being built, 7 past the promised date (typically 28 months late); 10 lapsed. 856 complaints on MahaRERA across 19 projects.
Read Google reviews of Ruparel Elara →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Ruparel Elara: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Ruparel Elara
What is the possession date of Ruparel Elara?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Ruparel Elara in Matunga W, Mumbai is 30 December 2023 — 48 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Ruparel Elara?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Ruparel Elara's builder has filed on MahaRERA, the official one, is 30 December 2023, already 48 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Ruparel Elara?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Ruparel Elara in Matunga W, Mumbai is P51800014328.
Is Ruparel Elara registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Elara is registered as P51800014328 and its status is "Completed".
What is the construction status of Ruparel Elara?
According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Elara's status on MahaRERA is "Completed". As filed by the builder, slab work on Ruparel Elara is 90% done and internal work 55%. GharKundli's full report compares construction progress with the deadline.
Does Ruparel Elara have complaints on MahaRERA?
5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Ruparel Elara safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Elara is registered on MahaRERA as P51800014328, its MahaRERA status is "Completed", its completion date has moved 48 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Ruparel Elara's possession date changes?
The latest dates are on Ruparel Elara's MahaRERA page (P51800014328). GharKundli's Kundli Watch sends a free WhatsApp update on Ruparel Elara every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Ruparel Elara have?
According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Elara has one building filed: Ruparel Elara with 24 floors.
How big is the land of Ruparel Elara?
According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Elara stands on 1,303 sq m of land (about 0.3 acres), with 3,818 sq m of sanctioned built-up area and 110 sq m of recreational open space.
What is the track record of Ruparel Elara's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Infra & Realty (a group of 12 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 47 months); 13 still being built, 7 past the promised date (typically 28 months late); 10 lapsed. 856 complaints on MahaRERA across 19 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Ruparel Elara?
Google Maps has reviews of Ruparel Elara written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Ruparel Elara?
Ruparel Elara by Shree Siddhivinayak Infrastructure & Realty (Ruparel) is in Matunga W, Mumbai (pincode 400067), near Kandivali West, Malad West, Bandra, Maharashtra, and is registered on MahaRERA as P51800014328, per GharKundli's check of MahaRERA records.
How many homes are in Ruparel Elara?
According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Elara has 84 homes in 1 tower registered on MahaRERA.
When was Ruparel Elara registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Ruparel Elara was registered on MahaRERA on 23 November 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Ruparel Elara?
No court cases are listed for Ruparel Elara on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Ruparel Elara?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shree Siddhivinayak Infrastructure & Realty, the company Ruparel files this project under, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Ruparel Elara
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects in Kandivali West (400067) →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.