Skip to content
GharKundli

GEM PARADISE

by VAYUPUTTRA BUILDERS & INFRASTRUCTURES PVT. LTD. · Vira Desai Road Andheri west, MumbaiAlso near Ambivali West, Amboli, Azad Nagar

Possession: GEM PARADISE is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800014003. Status: Completed. 7 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about GEM PARADISE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GEM PARADISE has moved

  1. 30 July 2021

    Completion date given when the project was registered

  2. 30 July 2022

    Extended at the builder's request (MahaRERA application EXT51800006098)

    Reason the builder gave MahaRERA:
    “Due to various reasons being lack of labour, shortage of buyers, implementation of RERA and then GST and shortage of material, it appears that the project shall atleast be delayed by a year. The recent pandemic COVID-19 that has been declar…” Read the full reason“Due to various reasons being lack of labour, shortage of buyers, implementation of RERA and then GST and shortage of material, it appears that the project shall atleast be delayed by a year. The recent pandemic COVID-19 that has been declared as Force Majeure has also brought the real estate industry to standstill and due to reverse migration of labourers, the construction work has been stopped completely. Moreover, various private and government offices have not been working at full force and complete supply chain has broken down. MHADA approvals and sanctions are getting inordinately dela…”
  3. 30 January 2023

    Revised completion date on MahaRERA

Source: GEM PARADISE’s extension records on MahaRERA (P51800014003), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GEM PARADISE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 7 complaints and 4 court cases, and how it ended
  • Construction pace against the January 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800014003
Status
Completed
Builder
VAYUPUTTRA BUILDERS & INFRASTRUCTURES PVT. LTD.
Location
Vira Desai Road Andheri west, Mumbai · 400053
Project type
Residential / Group Housing
Registered on
7 Nov 2017
Completion date at registration
July 2021
Latest completion date
January 2023
Delay so far
18 months
Homes
41
Towers
1
Complaints on MahaRERA
7
Court cases listed
4
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of GEM PARADISE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GEM PARADISE100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GEM PARADISE every month.

GEM PARADISE: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Vayuputtra Builders & Infrastructures (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 4 months). 7 complaints on MahaRERA across 1 project.

Read Google reviews of GEM PARADISE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GEM PARADISE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GEM PARADISE

What is the possession date of GEM PARADISE?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for GEM PARADISE in Vira Desai Road Andheri west, Mumbai is 30 January 2023 — 18 months later than 30 July 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for GEM PARADISE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GEM PARADISE's builder has filed on MahaRERA, the official one, is 30 January 2023, already 18 months later than the 30 July 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GEM PARADISE extended?

According to GharKundli's check of MahaRERA records (updated November 2026), GEM PARADISE's builder applied to MahaRERA to extend the completion date once: to 30 July 2022, giving the reason "Due to various reasons being lack of labour, shortage of buyers, implementation of RERA and then GST and shortage of material, it appears that the project shall atleast be delayed by a year. The recent pandemic COVID-19 that has been declared as Force Majeure has also brought the real estate industry to standstill and due to reverse migration of labourers, the construction work has been stopped completely. Moreover, various private and government offices have not been working at full force and complete supply chain has broken down. MHADA approvals and sanctions are getting inordinately dela…".

What is the RERA number of GEM PARADISE?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of GEM PARADISE in Vira Desai Road Andheri west, Mumbai is P51800014003.

Is GEM PARADISE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GEM PARADISE is registered as P51800014003 and its status is "Completed".

What is the construction status of GEM PARADISE?

According to GharKundli's check of MahaRERA records (updated November 2026), GEM PARADISE's status on MahaRERA is "Completed". As filed by the builder, slab work on GEM PARADISE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does GEM PARADISE have complaints on MahaRERA?

7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is GEM PARADISE safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), GEM PARADISE is registered on MahaRERA as P51800014003, its MahaRERA status is "Completed", its completion date has moved 18 months since registration and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GEM PARADISE's possession date changes?

The latest dates are on GEM PARADISE's MahaRERA page (P51800014003). GharKundli's Kundli Watch sends a free WhatsApp update on GEM PARADISE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GEM PARADISE have?

According to GharKundli's check of MahaRERA records (updated November 2026), GEM PARADISE has one building filed: GEM PARADISE with 19 floors.

How big is the land of GEM PARADISE?

According to GharKundli's check of MahaRERA records (updated November 2026), GEM PARADISE stands on 932 sq m of land (about 0.2 acres), with 4,220 sq m of sanctioned built-up area.

What is the track record of GEM PARADISE's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Vayuputtra Builders & Infrastructures (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 4 months). 7 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of GEM PARADISE?

Google Maps has reviews of GEM PARADISE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GEM PARADISE?

GEM PARADISE by VAYUPUTTRA BUILDERS & INFRASTRUCTURES PVT. LTD. is in Vira Desai Road Andheri west, Mumbai (pincode 400053), near Ambivali West, Amboli, Azad Nagar, Maharashtra, and is registered on MahaRERA as P51800014003, per GharKundli's check of MahaRERA records. Its boundaries filed there include AZAD NAGAR PRESTIGE CHS.

How many homes are in GEM PARADISE?

According to GharKundli's check of MahaRERA records (updated November 2026), GEM PARADISE has 41 homes in 1 tower registered on MahaRERA.

When was GEM PARADISE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GEM PARADISE was registered on MahaRERA on 7 November 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on GEM PARADISE?

4 court cases are listed for GEM PARADISE on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of GEM PARADISE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VAYUPUTTRA BUILDERS & INFRASTRUCTURES PVT. LTD..

Other projects in Andheri

All 161 projects in Andheri West (400053) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.