by ZODIAC DEVELOPERS PRIVATE LIMITED · Hanuman Nagar Andheri West, MumbaiAlso near Juhu, D. N. Nagar, Vile Parle East

Possession date of HANUMAN NAGAR: 30 June 2024, moved from 30 June 2021 (36 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800015181. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (June 2024) has passed.

What do you want to know about HANUMAN NAGAR?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of HANUMAN NAGAR has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51800010610)

    Reason the builder gave MahaRERA:
    “There have been several delays in the said project due to the Covid-19 pandemic and also due to ongoing litigation.We request you to for extension of time limit up to 31st December,2023 for completion of the project and obtaining Occupation…” Read the full reason“There have been several delays in the said project due to the Covid-19 pandemic and also due to ongoing litigation.We request you to for extension of time limit up to 31st December,2023 for completion of the project and obtaining Occupation Certificate for the said project.”
  3. 30 June 2024

    Revised completion date on MahaRERA

Source: HANUMAN NAGAR’s extension records on MahaRERA (P51800015181), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on HANUMAN NAGAR

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 3 court cases, and how it ended
  • Construction pace against the June 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800015181
Status
Lapsed (registration period ended)
Builder
ZODIAC DEVELOPERS PRIVATE LIMITED
Location
Hanuman Nagar Andheri West, Mumbai · 400058
Project type
Residential / Group Housing
Registered on
2 Feb 2018
Completion date at registration
June 2021
Latest completion date
June 2024
Delay so far
36 months
Homes
90
Towers
1
Complaints on MahaRERA
1
Court cases listed
3
Title report on file
Not found

Construction progress of HANUMAN NAGAR, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
HANUMAN NAGAR BUILDING NO 7100%66%66%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on HANUMAN NAGAR every month.

HANUMAN NAGAR: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Zodiac Ventures (a group of 2 linked companies) has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 16 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of HANUMAN NAGAR →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

HANUMAN NAGAR: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about HANUMAN NAGAR

What is the possession date of HANUMAN NAGAR?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for HANUMAN NAGAR in Hanuman Nagar Andheri West, Mumbai is 30 June 2024 — 36 months later than 30 June 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for HANUMAN NAGAR?

Builders and listing sites often quote an earlier "target" date for handover. The completion date HANUMAN NAGAR's builder has filed on MahaRERA, the official one, is 30 June 2024, already 36 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of HANUMAN NAGAR extended?

According to GharKundli's check of MahaRERA records (updated November 2026), HANUMAN NAGAR's builder applied to MahaRERA to extend the completion date once: to 31 December 2023, giving the reason "There have been several delays in the said project due to the Covid-19 pandemic and also due to ongoing litigation.We request you to for extension of time limit up to 31st December,2023 for completion of the project and obtaining Occupation Certificate for the said project.".

What is the RERA number of HANUMAN NAGAR?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of HANUMAN NAGAR in Hanuman Nagar Andheri West, Mumbai is P51800015181.

Is HANUMAN NAGAR registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), HANUMAN NAGAR is registered as P51800015181 and its status is "Lapsed (registration period ended)".

What is the construction status of HANUMAN NAGAR?

According to GharKundli's check of MahaRERA records (updated November 2026), HANUMAN NAGAR's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on HANUMAN NAGAR BUILDING NO 7 is 66% done and internal work 66%. GharKundli's full report compares construction progress with the deadline.

Does HANUMAN NAGAR have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is HANUMAN NAGAR safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), HANUMAN NAGAR is registered on MahaRERA as P51800015181, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if HANUMAN NAGAR's possession date changes?

The latest dates are on HANUMAN NAGAR's MahaRERA page (P51800015181). GharKundli's Kundli Watch sends a free WhatsApp update on HANUMAN NAGAR every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does HANUMAN NAGAR have?

According to GharKundli's check of MahaRERA records (updated November 2026), HANUMAN NAGAR has one building filed: HANUMAN NAGAR BUILDING NO 7 with 19 floors.

How big is the land of HANUMAN NAGAR?

According to GharKundli's check of MahaRERA records (updated November 2026), HANUMAN NAGAR stands on 2,292 sq m of land (about 0.6 acres), with 17,664 sq m of sanctioned built-up area.

What is the track record of HANUMAN NAGAR's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Zodiac Ventures (a group of 2 linked companies) has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 16 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of HANUMAN NAGAR?

Google Maps has reviews of HANUMAN NAGAR written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is HANUMAN NAGAR?

HANUMAN NAGAR by ZODIAC DEVELOPERS PRIVATE LIMITED is in Hanuman Nagar Andheri West, Mumbai (pincode 400058), near Juhu, D. N. Nagar, Vile Parle East, Maharashtra, and is registered on MahaRERA as P51800015181, per GharKundli's check of MahaRERA records.

How many homes are in HANUMAN NAGAR?

According to GharKundli's check of MahaRERA records (updated November 2026), HANUMAN NAGAR has 90 homes in 1 tower registered on MahaRERA.

When was HANUMAN NAGAR registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), HANUMAN NAGAR was registered on MahaRERA on 2 February 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on HANUMAN NAGAR?

3 court cases are listed for HANUMAN NAGAR on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of HANUMAN NAGAR?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ZODIAC DEVELOPERS PRIVATE LIMITED.