Skip to content
GharKundli

Sethia Imperial Avenue

by Sai Enterprises (Sethia) · Bandongri, Malkani Estate, MumbaiAlso near Malad east, Kandivali East, Kurar Village

Possession date of Sethia Imperial Avenue: 30 April 2027, moved from 30 December 2023 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800015798, and currently active. Its completion date has moved from December 2023 to April 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 24 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Sethia Imperial Avenue?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sethia Imperial Avenue has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 29 December 2024

    Extended at the builder's request (MahaRERA application EXT51800018702)

    Reason the builder gave MahaRERA: “DUE TO COVID 19 NOT ABLE TO COMPLETE PROJECT GRANT US EXTENSION TILL 29/12/2024”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT51800025582)

    Reason the builder gave MahaRERA:
    “Firstly we would like to inform you that we have successfully completed the construction of the building. Our project is Stilt + 40th floors out of which we have already obtained part OL for stilt 1 to 23 upper floor from the competent auth…” Read the full reason“Firstly we would like to inform you that we have successfully completed the construction of the building. Our project is Stilt + 40th floors out of which we have already obtained part OL for stilt 1 to 23 upper floor from the competent authority on 29 October 2021 before the validity period got over. Even the possession of the flats have been given to all the allottees. The part OC copy has also been uploaded on MahaRERA portal. Firstly we would like to inform you that we have successfully completed the construction of the building. Our project is Stilt + 40th floors out of which we have al…”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Sethia Imperial Avenue’s extension records on MahaRERA (P51800015798), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sethia Imperial Avenue

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 24 complaints and 4 court cases, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800015798
Status
Registered and active
Builder
Sai Enterprises
Location
Bandongri, Malkani Estate, Mumbai · 400097
Project type
Residential / Group Housing
Registered on
26 Mar 2018
Completion date at registration
December 2023
Latest completion date
April 2027
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
453
Sold or booked
100%
Towers
1
Complaints on MahaRERA
24
Court cases listed
4
Appeals at the tribunal
8
Title report on file
Not found
Builder's other MahaRERA projects
12

Construction progress of Sethia Imperial Avenue, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sethia Imperial Avenue100%100%100%90%

Commencement certificate (CC), as filed on MahaRERA

  • Sethia Imperial Avenue: covers 40 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sethia Imperial Avenue every month.

Sethia Imperial Avenue: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK308 – 569372
2 BHK328 – 56981
  • Buildings: Sethia Imperial Avenue (43 floors, 453 units)
  • Land: 1,737 sq m (about 0.4 acres) · recreational space 139 sq m
  • Boundaries filed include: Western Express Highway
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Sethia Infrastructure (a group of 7 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 35 months); 7 still being built, 5 past the promised date (typically 18 months late); 1 lapsed. 40 complaints on MahaRERA across 5 projects.

Read Google reviews of Sethia Imperial Avenue →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sethia Imperial Avenue: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sethia Imperial Avenue

What is the possession date of Sethia Imperial Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sethia Imperial Avenue in Bandongri, Malkani Estate, Mumbai is 30 April 2027 — 36 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Sethia Imperial Avenue?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sethia Imperial Avenue's builder has filed on MahaRERA, the official one, is 30 April 2027, already 36 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sethia Imperial Avenue extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Imperial Avenue's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2024, giving the reason "DUE TO COVID 19 NOT ABLE TO COMPLETE PROJECT GRANT US EXTENSION TILL 29/12/2024"; to 31 December 2026, giving the reason "Firstly we would like to inform you that we have successfully completed the construction of the building. Our project is Stilt + 40th floors out of which we have already obtained part OL for stilt 1 to 23 upper floor from the competent authority on 29 October 2021 before the validity period got over. Even the possession of the flats have been given to all the allottees. The part OC copy has also been uploaded on MahaRERA portal. Firstly we would like to inform you that we have successfully completed the construction of the building. Our project is Stilt + 40th floors out of which we have al…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Sethia Imperial Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sethia Imperial Avenue in Bandongri, Malkani Estate, Mumbai is P51800015798.

Is Sethia Imperial Avenue registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Imperial Avenue is registered as P51800015798 and its status is "Registered and active".

What is the construction status of Sethia Imperial Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Imperial Avenue's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sethia Imperial Avenue is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Sethia Imperial Avenue have complaints on MahaRERA?

24 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Sethia Imperial Avenue safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Imperial Avenue is registered on MahaRERA as P51800015798, its completion date has moved 36 months since registration and 24 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Sethia Imperial Avenue's possession date changes?

The latest dates are on Sethia Imperial Avenue's MahaRERA page (P51800015798). GharKundli's Kundli Watch sends a free WhatsApp update on Sethia Imperial Avenue every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sethia Imperial Avenue have?

According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Imperial Avenue has one building filed: Sethia Imperial Avenue with 43 floors and 453 units.

What are the flat sizes (carpet area) in Sethia Imperial Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Sethia Imperial Avenue: 1 BHK: 308 to 569 sq ft carpet (372 homes); 2 BHK: 328 to 569 sq ft carpet (81 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Sethia Imperial Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Imperial Avenue stands on 1,737 sq m of land (about 0.4 acres) and 139 sq m of recreational open space.

What is the track record of Sethia Imperial Avenue's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Infrastructure (a group of 7 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 35 months); 7 still being built, 5 past the promised date (typically 18 months late); 1 lapsed. 40 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Sethia Imperial Avenue?

Google Maps has reviews of Sethia Imperial Avenue written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 24 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sethia Imperial Avenue?

Sethia Imperial Avenue by Sai Enterprises (Sethia) is in Bandongri, Malkani Estate, Mumbai (pincode 400097), near Malad east, Kandivali East, Kurar Village, Maharashtra, and is registered on MahaRERA as P51800015798, per GharKundli's check of MahaRERA records. Its boundaries filed there include Western Express Highway.

How many homes are in Sethia Imperial Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Imperial Avenue has 453 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was Sethia Imperial Avenue registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Imperial Avenue was registered on MahaRERA on 26 March 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on Sethia Imperial Avenue?

4 court cases are listed for Sethia Imperial Avenue on MahaRERA, and 8 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Sethia Imperial Avenue?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sai Enterprises, the company Sethia files this project under, which has 12 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Borivali

All 195 projects in Malad East (400097) →

Other projects by Sai Enterprises

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.