Shahid Nagar
by NEUMEC AND SANGAM JV · Nariman Point, Mumbai 400021Also near Marine Lines, Colaba
What’s in the report? →Possession date of Shahid Nagar (MahaRERA P51900002527): 31 December 2027, moved from 30 June 2024 (42 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900002527, and currently active. MahaRERA has issued a regulatory order on this project.
Source: MahaRERA website — records for P51900002527, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shahid Nagar?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shahid Nagar has moved
30 June 2024
Completion date given when the project was registered
29 June 2025
Extended at the builder's request (MahaRERA application EXT51900024546)
Reason the builder gave MahaRERA:
“The delay in the completion of the project has occurred due to several unforeseen challenges, primarily: 1. Impact of the COVID-19 Pandemic: The pandemic caused significant disruptions, including delays in the remobilization of workers afte…” Read the full reason
“The delay in the completion of the project has occurred due to several unforeseen challenges, primarily: 1. Impact of the COVID-19 Pandemic: The pandemic caused significant disruptions, including delays in the remobilization of workers after the lockdowns and travel restrictions were lifted, resulting in labor shortages and hindering the progress of the project. In addition to the above, the delay has also been caused by procurement issues, unforeseen site conditions, coordination challenges. We are pleased to inform you that the project is now 100% completed. We are in the process of apply…”31 December 2027
Extended at the builder's request (MahaRERA application EA11092502560)
Reason the builder gave MahaRERA:
“I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P51900002527. As per HEARING DATED 3rd November 2025, Hon'ble Shri Manoj Saunik Sir granted Extension upto 31.12.2027. The order is…” Read the full reason
“I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P51900002527. As per HEARING DATED 3rd November 2025, Hon'ble Shri Manoj Saunik Sir granted Extension upto 31.12.2027. The order is uploaded in Other Tab for your reference”
Source: Shahid Nagar’s extension records on MahaRERA (P51900002527), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shahid Nagar
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900002527
- Status
- Registered and active
- Builder
- NEUMEC AND SANGAM JV
- Location
- Nariman Point, Mumbai · 400021
- Project type
- Others
- Registered on
- 1 Aug 2017
- Completion date at registration
- June 2024
- Latest completion date
- December 2027
- Delay so far
- 42 months
- Homes
- 0
- Sold or booked
- 46%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Shahid Nagar, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHAHID NAGAR | 100% | 95% | 95% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- SHAHID NAGAR: covers 3 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shahid Nagar every 1–2 months.
Shahid Nagar: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 37 – 180 | 39 |
- Buildings: SHAHID NAGAR (8 floors, 39 units)
- Land: 2,658 sq m (about 0.7 acres) · sanctioned built-up 3,284 sq m
- Land, as filed: 245/PT 335/PT 374/PT
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Neumec Estate Developer (a group of 7 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 1 finished, all within the promised date; 8 still being built, 7 past the promised date (typically 43 months late); 2 lapsed. 12 complaints on MahaRERA across 4 projects.
Read Google reviews of Shahid Nagar →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shahid Nagar: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shahid Nagar
What is the possession date of Shahid Nagar?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shahid Nagar in Nariman Point, Mumbai is 31 December 2027 — 42 months later than 30 June 2024, the date given at registration.
The date has already moved 42 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shahid Nagar?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shahid Nagar's builder has filed on MahaRERA, the official one, is 31 December 2027, already 42 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shahid Nagar extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shahid Nagar's builder applied to MahaRERA to extend the completion date 2 times: to 29 June 2025, giving the reason "The delay in the completion of the project has occurred due to several unforeseen challenges, primarily: 1. Impact of the COVID-19 Pandemic: The pandemic caused significant disruptions, including delays in the remobilization of workers after the lockdowns and travel restrictions were lifted, resulting in labor shortages and hindering the progress of the project. In addition to the above, the delay has also been caused by procurement issues, unforeseen site conditions, coordination challenges. We are pleased to inform you that the project is now 100% completed. We are in the process of apply…"; to 31 December 2027, giving the reason "I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P51900002527. As per HEARING DATED 3rd November 2025, Hon'ble Shri Manoj Saunik Sir granted Extension upto 31.12.2027. The order is uploaded in Other Tab for your reference".
What is the RERA number of Shahid Nagar?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shahid Nagar in Nariman Point, Mumbai is P51900002527.
Is Shahid Nagar registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shahid Nagar is registered as P51900002527 and its status is "Registered and active".
What is the current construction status of Shahid Nagar? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shahid Nagar's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHAHID NAGAR is 95% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does Shahid Nagar have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shahid Nagar safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shahid Nagar is registered on MahaRERA as P51900002527, its completion date has moved 42 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shahid Nagar?
Shahid Nagar is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shahid Nagar?
For a flat in Shahid Nagar (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Shahid Nagar received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shahid Nagar is still under construction, with 31 December 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Shahid Nagar uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shahid Nagar was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shahid Nagar's possession date changes?
The latest dates are on Shahid Nagar's MahaRERA page (P51900002527). GharKundli's Kundli Watch sends a free WhatsApp update on Shahid Nagar every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shahid Nagar have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shahid Nagar has one building filed: SHAHID NAGAR with 8 floors and 39 units.
How big is the land of Shahid Nagar?
According to GharKundli's check of MahaRERA records (updated October 2026), Shahid Nagar stands on 2,658 sq m of land (about 0.7 acres), with 3,284 sq m of sanctioned built-up area.
What is the track record of Shahid Nagar's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Neumec Estate Developer (a group of 7 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 1 finished, all within the promised date; 8 still being built, 7 past the promised date (typically 43 months late); 2 lapsed. 12 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Shahid Nagar?
Google Maps has reviews of Shahid Nagar written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shahid Nagar?
Shahid Nagar by NEUMEC AND SANGAM JV is in Nariman Point, Mumbai, pincode 400021 (near Marine Lines, Colaba), Maharashtra, and is registered on MahaRERA as P51900002527, per GharKundli's check of MahaRERA records. Its land is filed as 245/PT 335/PT 374/PT. GharKundli lists all 3 MahaRERA projects in Nariman Point (400021).
How many flats are in Shahid Nagar, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Shahid Nagar has 0 homes in 1 tower registered on MahaRERA, and 46% of them are sold or booked.
When was Shahid Nagar registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shahid Nagar was registered on MahaRERA on 1 August 2017. GharKundli did not find a title report on the land on file there.
Does Shahid Nagar have any legal issues or court cases?
No court cases are listed for Shahid Nagar on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shahid Nagar?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NEUMEC AND SANGAM JV, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Shahid Nagar
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in Nariman Point (400021)
- Composite Building No2
- Om Sahil Solitaire
- Lovedale Residences
- Lighthall D Wing
- S R scheme Sai Prathana CHS Prop
- Allure
- Shanti Garden Sector-5 BLDG -9
Other projects by NEUMEC AND SANGAM JV
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.