Composite Building No2

by NEUMEC AND SANGAM JV · Nariman Point, Mumbai 400021Also near Marine Lines, Colaba

What’s in the report? →

Possession date of Composite Building No2 (MahaRERA P51900018301): 30 October 2027, moved from 30 June 2022 (60 months later). It has 56 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900018301, and currently active. Its completion date has moved from June 2022 to October 2027: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51900018301, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Composite Building No2?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Composite Building No2 has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT51900012375)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of the project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of the project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19.”
  3. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51900017385)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 77.27% allottees for purpose of extension of RERA registration period of the said project.”
  4. 30 June 2027

    Extended at the builder's request (MahaRERA application EXT51900028409)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 30/06/2025. to complete the project and fulfil all regulatory requirements.”
  5. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Composite Building No2’s extension records on MahaRERA (P51900018301), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Composite Building No2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900018301
Status
Registered and active
Builder
NEUMEC AND SANGAM JV
Location
Nariman Point, Mumbai · 400021
Project type
Others
Registered on
22 Oct 2018
Completion date at registration
June 2022
Latest completion date
October 2027
Delay so far
60 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
56
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Composite Building No2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
COMPOSITE BUILDING NO 2100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Composite Building No2 every 1–2 months.

Composite Building No2: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Neumec Estate Developer (a group of 7 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 1 finished, all within the promised date; 8 still being built, 7 past the promised date (typically 43 months late); 2 lapsed. 12 complaints on MahaRERA across 4 projects.

Read Google reviews of Composite Building No2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Composite Building No2: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Composite Building No2

What is the possession date of Composite Building No2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Composite Building No2 in Nariman Point, Mumbai is 30 October 2027 — 60 months later than 30 June 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 60 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Composite Building No2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Composite Building No2's builder has filed on MahaRERA, the official one, is 30 October 2027, already 60 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Composite Building No2 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Composite Building No2's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of the project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19."; to 30 June 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 77.27% allottees for purpose of extension of RERA registration period of the said project."; to 30 June 2027, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 30/06/2025. to complete the project and fulfil all regulatory requirements.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Composite Building No2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Composite Building No2 in Nariman Point, Mumbai is P51900018301.

Is Composite Building No2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Composite Building No2 is registered as P51900018301 and its status is "Registered and active".

What is the current construction status of Composite Building No2? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Composite Building No2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on COMPOSITE BUILDING NO 2 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Composite Building No2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Composite Building No2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Composite Building No2 is registered on MahaRERA as P51900018301, its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Composite Building No2?

Composite Building No2 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Composite Building No2?

For a flat in Composite Building No2 (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Composite Building No2 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Composite Building No2 is still under construction, with 30 October 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Composite Building No2 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Composite Building No2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Composite Building No2's possession date changes?

The latest dates are on Composite Building No2's MahaRERA page (P51900018301). GharKundli's Kundli Watch sends a free WhatsApp update on Composite Building No2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Composite Building No2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Composite Building No2 has one building filed: COMPOSITE BUILDING NO 2 with 21 floors.

How big is the land of Composite Building No2?

According to GharKundli's check of MahaRERA records (updated October 2026), Composite Building No2 stands on 2,658 sq m of land (about 0.7 acres), with 1,478 sq m of sanctioned built-up area.

What is the track record of Composite Building No2's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Neumec Estate Developer (a group of 7 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 1 finished, all within the promised date; 8 still being built, 7 past the promised date (typically 43 months late); 2 lapsed. 12 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Composite Building No2?

Google Maps has reviews of Composite Building No2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Composite Building No2?

Composite Building No2 by NEUMEC AND SANGAM JV is in Nariman Point, Mumbai, pincode 400021 (near Marine Lines, Colaba), Maharashtra, and is registered on MahaRERA as P51900018301, per GharKundli's check of MahaRERA records. Its land is filed as 345/PT366/PT370/PT245/PT335/PT374/PT. GharKundli lists all 3 MahaRERA projects in Nariman Point (400021).

How many flats are in Composite Building No2?

According to GharKundli's check of MahaRERA records (updated October 2026), Composite Building No2 has 56 homes in 1 tower registered on MahaRERA.

When was Composite Building No2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Composite Building No2 was registered on MahaRERA on 22 October 2018. GharKundli did not find a title report on the land on file there.

Does Composite Building No2 have any legal issues or court cases?

No court cases are listed for Composite Building No2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Composite Building No2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NEUMEC AND SANGAM JV, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Mumbai City →

Other projects in Nariman Point (400021)

All 3 projects in Nariman Point (400021) →

Other projects by NEUMEC AND SANGAM JV

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.