Hill Casa
by HUSAIN TAHER PATNI · Bandra, Mumbai 400050Also near Khar West, Santacruz West, Nashik Road
What’s in the report? →Possession date of Hill Casa (MahaRERA P51800018188): 31 December 2026, moved from 30 June 2022 (54 months later). It has 26 homes (1 Room Kitchen, 1 BHK and 2 BHK, 240–794 sq ft carpet), 33% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800018188, and currently active.
Source: MahaRERA website — records for P51800018188, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Hill Casa?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Hill Casa has moved
30 June 2022
Completion date given when the project was registered
30 June 2023
Extended at the builder's request (MahaRERA application EXT51800012362)
Reason the builder gave MahaRERA: “Due to covid-19pandemic/lockdown and also there was a shortage of labour therefore so the construction work has been delayed estimated time frame, so we require more time to complete the project .”
31 December 2023
Extended at the builder's request (MahaRERA application EXT51800016719)
Reason the builder gave MahaRERA: “There is unexpected delay on account of receiving permissions from the competent authorities. And after Covid the material supply chain is disrupted and we are trying over level best to complete the work faster.”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51800024857)
Reason the builder gave MahaRERA:
“Due to COVID-19, the regular flow of work was hampered and there was shortage of labour. Also, there are limitations in construction on daily basis due to residential area which hampers continue of work on regular basis. Also, please refer…” Read the full reason
“Due to COVID-19, the regular flow of work was hampered and there was shortage of labour. Also, there are limitations in construction on daily basis due to residential area which hampers continue of work on regular basis. Also, please refer to our attached detailed request letter.”31 December 2026
Extended at the builder's request (MahaRERA application EA07032620131)
Reason the builder gave MahaRERA:
“a) As the entire country including Mumbai Suburban were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to cur…” Read the full reason
“a) As the entire country including Mumbai Suburban were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to curb the spread of the COVID-19. In view of the curbs and measures imposed by the Governments, I stopped work till such time as the said lockdowns, curbs and measures were relaxed by the respective Governments. b) Inspite of best efforts, the said project was adversely affected due to unprecedented COVID-19 Pandemic which lasted for more than 2 years and are…”
Source: Hill Casa’s extension records on MahaRERA (P51800018188), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Hill Casa
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800018188
- Status
- Registered and active
- Builder
- HUSAIN TAHER PATNI
- Location
- Bandra, Mumbai · 400050
- Project type
- Residential / Group Housing
- Registered on
- 15 Oct 2018
- Completion date at registration
- June 2022
- Latest completion date
- December 2026
- Delay so far
- 54 months
- Homes
- 26
- Sold or booked
- 33%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Hill Casa, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A wing | 100% | 100% | 90% | 0% |
| B Wing | 100% | 100% | 90% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- A wing: covers 5 floors
- B Wing: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Hill Casa every 1–2 months.
Hill Casa: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 540 – 648 | 13 |
| 1 Room Kitchen | 240 – 304 | 8 |
| 1 BHK | 345 – 442 | 4 |
| 3 BHK | 794 | 1 |
- Buildings: A wing (6 floors, 8 units) · B Wing (5 floors, 18 units)
- Land: 624 sq m (about 0.2 acres) · sanctioned built-up 936 sq m
- Land, as filed: A/689, A/690, A/691, A/692,
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Hill Casa →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Hill Casa: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Hill Casa
What is the possession date of Hill Casa?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Hill Casa in Bandra, Mumbai is 31 December 2026 — 54 months later than 30 June 2022, the date given at registration.
The date has already moved 54 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Hill Casa?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Hill Casa's builder has filed on MahaRERA, the official one, is 31 December 2026, already 54 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Hill Casa extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill Casa's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2023, giving the reason "Due to covid-19pandemic/lockdown and also there was a shortage of labour therefore so the construction work has been delayed estimated time frame, so we require more time to complete the project ."; to 31 December 2023, giving the reason "There is unexpected delay on account of receiving permissions from the competent authorities. And after Covid the material supply chain is disrupted and we are trying over level best to complete the work faster."; to 31 December 2025, giving the reason "Due to COVID-19, the regular flow of work was hampered and there was shortage of labour. Also, there are limitations in construction on daily basis due to residential area which hampers continue of work on regular basis. Also, please refer to our attached detailed request letter."; to 31 December 2026, giving the reason "a) As the entire country including Mumbai Suburban were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to curb the spread of the COVID-19. In view of the curbs and measures imposed by the Governments, I stopped work till such time as the said lockdowns, curbs and measures were relaxed by the respective Governments. b) Inspite of best efforts, the said project was adversely affected due to unprecedented COVID-19 Pandemic which lasted for more than 2 years and are…".
What is the RERA number of Hill Casa?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Hill Casa in Bandra, Mumbai is P51800018188.
Is Hill Casa registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill Casa is registered as P51800018188 and its status is "Registered and active".
What is the current construction status of Hill Casa? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill Casa's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Hill Casa have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Hill Casa safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill Casa is registered on MahaRERA as P51800018188, its completion date has moved 54 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Hill Casa?
Hill Casa is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Hill Casa are 240 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Hill Casa?
For a flat in Hill Casa (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Hill Casa received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Hill Casa is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Hill Casa a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill Casa is a redevelopment: 14 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Hill Casa uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Hill Casa was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Hill Casa's possession date changes?
The latest dates are on Hill Casa's MahaRERA page (P51800018188). GharKundli's Kundli Watch sends a free WhatsApp update on Hill Casa every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Hill Casa have?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill Casa has 2 buildings filed: A wing with 6 floors and 8 units; B Wing with 5 floors and 18 units.
What are the flat sizes (carpet area) in Hill Casa?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Hill Casa: 2 BHK: 540 to 648 sq ft carpet (13 homes); 1 Room Kitchen: 240 to 304 sq ft carpet (8 homes); 1 BHK: 345 to 442 sq ft carpet (4 homes); 3 BHK: 794 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Hill Casa?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill Casa stands on 624 sq m of land (about 0.2 acres), with 936 sq m of sanctioned built-up area.
What are the reviews of Hill Casa?
Google Maps has reviews of Hill Casa written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Hill Casa?
Hill Casa by HUSAIN TAHER PATNI is in Bandra, Mumbai, pincode 400050 (near Khar West, Santacruz West, Nashik Road), Maharashtra, and is registered on MahaRERA as P51800018188, per GharKundli's check of MahaRERA records. Its land is filed as A/689, A/690, A/691, A/692,. GharKundli lists all 168 MahaRERA projects in Bandra West (400050).
How many flats are in Hill Casa, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill Casa has 26 homes in 2 towers registered on MahaRERA, and 33% of them are sold or booked.
When was Hill Casa registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Hill Casa was registered on MahaRERA on 15 October 2018. GharKundli did not find a title report on the land on file there.
Does Hill Casa have any legal issues or court cases?
No court cases are listed for Hill Casa on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Hill Casa?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is HUSAIN TAHER PATNI.
Check it yourself on MahaRERA
- How to check the possession date of Hill Casa
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Bandra West (400050)
- Manthan Embassy
- The Marque
- Therese
- Tonino Lamborghini Residences Mumbai
- Godrej Bandra Bay Phase 2
- Godrej Bandra Bay Phase 3
- KK 415 West
- Verdant
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.