RAJ DARSHAN
by VENEZIA REALTORS · Andheri East, MumbaiAlso near J.B. Nagar, Chakala MIDC, Seepz
Possession date of RAJ DARSHAN: 30 June 2024, moved from 30 June 2021 (36 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800018351. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (June 2024) has passed.
What do you want to know about RAJ DARSHAN?
GharKundli’s full report on RAJ DARSHAN
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 12 court cases, and how it ended
- Construction pace against the June 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800018351
- Status
- Lapsed (registration period ended)
- Builder
- VENEZIA REALTORS
- Location
- Andheri East, Mumbai · 400059
- Project type
- Residential / Group Housing
- Registered on
- 24 Oct 2018
- Completion date at registration
- June 2021
- Latest completion date
- June 2024
- Delay so far
- 36 months
- Homes
- 27
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 12
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of RAJ DARSHAN, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RAJ DARSHAN | 100% | 100% | 100% | 95% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RAJ DARSHAN every month.
RAJ DARSHAN: buildings, flats and land, as filed on MahaRERA
- Buildings: RAJ DARSHAN (11 floors)
- Land: 649 sq m (about 0.2 acres) · sanctioned built-up 1,251 sq m
- Boundaries filed include: CHURCH ROAD
The builder’s record and reviews
Venezia Realtors (a group of 2 linked companies) has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 42 months late); 1 lapsed. 3 complaints on MahaRERA across 2 projects.
Read Google reviews of RAJ DARSHAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RAJ DARSHAN: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RAJ DARSHAN
What is the possession date of RAJ DARSHAN?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for RAJ DARSHAN in Andheri East, Mumbai is 30 June 2024 — 36 months later than 30 June 2021, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for RAJ DARSHAN?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RAJ DARSHAN's builder has filed on MahaRERA, the official one, is 30 June 2024, already 36 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of RAJ DARSHAN?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of RAJ DARSHAN in Andheri East, Mumbai is P51800018351.
Is RAJ DARSHAN registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RAJ DARSHAN is registered as P51800018351 and its status is "Lapsed (registration period ended)".
What is the construction status of RAJ DARSHAN?
According to GharKundli's check of MahaRERA records (updated November 2026), RAJ DARSHAN's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on RAJ DARSHAN is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does RAJ DARSHAN have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is RAJ DARSHAN safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), RAJ DARSHAN is registered on MahaRERA as P51800018351, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RAJ DARSHAN's possession date changes?
The latest dates are on RAJ DARSHAN's MahaRERA page (P51800018351). GharKundli's Kundli Watch sends a free WhatsApp update on RAJ DARSHAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RAJ DARSHAN have?
According to GharKundli's check of MahaRERA records (updated November 2026), RAJ DARSHAN has one building filed: RAJ DARSHAN with 11 floors.
How big is the land of RAJ DARSHAN?
According to GharKundli's check of MahaRERA records (updated November 2026), RAJ DARSHAN stands on 649 sq m of land (about 0.2 acres), with 1,251 sq m of sanctioned built-up area.
What is the track record of RAJ DARSHAN's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Venezia Realtors (a group of 2 linked companies) has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 42 months late); 1 lapsed. 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of RAJ DARSHAN?
Google Maps has reviews of RAJ DARSHAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RAJ DARSHAN?
RAJ DARSHAN by VENEZIA REALTORS is in Andheri East, Mumbai (pincode 400059), near J.B. Nagar, Chakala MIDC, Seepz, Maharashtra, and is registered on MahaRERA as P51800018351, per GharKundli's check of MahaRERA records. Its boundaries filed there include CHURCH ROAD.
How many homes are in RAJ DARSHAN?
According to GharKundli's check of MahaRERA records (updated November 2026), RAJ DARSHAN has 27 homes in 1 tower registered on MahaRERA.
When was RAJ DARSHAN registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RAJ DARSHAN was registered on MahaRERA on 24 October 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on RAJ DARSHAN?
12 court cases are listed for RAJ DARSHAN on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of RAJ DARSHAN?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VENEZIA REALTORS.
Check it yourself on MahaRERA
- How to check the possession date of RAJ DARSHAN
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects in Andheri East (400059) →