LAKE RIVIERA WING C

by PASHMINA REALTY PRIVATE LIMITED · Chandivali, MumbaiAlso near Powai, Sakinaka, Nahar Amrit Shakti

Possession date of LAKE RIVIERA WING C: 30 April 2028, moved from 30 December 2023 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800018480, and currently active. Its completion date has moved from December 2023 to April 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project. 18 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about LAKE RIVIERA WING C?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of LAKE RIVIERA WING C has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 29 December 2024

    Extended at the builder's request (MahaRERA application EXT51800016509)

    Reason the builder gave MahaRERA:
    “The SRA issued the First Stop Work Order dated 31st March, 2021 and the construction vis-à-vis the project was stopped. The SRA withdrew the First Stop Work Order on 22nd April, 2021. The SRA issued the Second Stop Work Order dated 25th May…” Read the full reason“The SRA issued the First Stop Work Order dated 31st March, 2021 and the construction vis-à-vis the project was stopped. The SRA withdrew the First Stop Work Order on 22nd April, 2021. The SRA issued the Second Stop Work Order dated 25th May, 2022 and the construction vis-à-vis the project was again stopped, causing further loss of time and monies as well. Thereafter, the SRA issued the S. 53(1) Notice under the MRTP dated 20th July, 2022 in furtherance of the Second Stop Work Order. After 5 months and constant deliberation, representations and requests the SRA vide its Withdrawal of Second…”
  3. 29 June 2025

    Extended at the builder's request (MahaRERA application EXT51800017012)

    Reason the builder gave MahaRERA:
    “We are filing this Application in order to seek an exclusion of time of 6 (six) months that was unproductive and unused due to the stop work notices issued by the Slum Rehabilitation Authority during the course of the said Project being reg…” Read the full reason“We are filing this Application in order to seek an exclusion of time of 6 (six) months that was unproductive and unused due to the stop work notices issued by the Slum Rehabilitation Authority during the course of the said Project being registered with RERA.”
  4. 30 December 2027

    Extended at the builder's request (MahaRERA application EA03112518224)

    Reason the builder gave MahaRERA:
    “Reasons for Delay (a)Subsequent Civil Aviation Clearance and Revised Height Restrictions:-Although the project had obtained the requisite building permissions and Commencement Certificate from the Planning Authority based on the approvals p…” Read the full reason“Reasons for Delay (a)Subsequent Civil Aviation Clearance and Revised Height Restrictions:-Although the project had obtained the requisite building permissions and Commencement Certificate from the Planning Authority based on the approvals prevailing at the relevant time, subsequent to such approvals, additional conditions and clearance requirements were imposed by the Civil Aviation Authorities/Airports Authority of India due to the project's location within the regulated funnel zone of the airport. The revised Civil Aviation requirements necessitated obtaining fresh clearances, submission…”
  5. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: LAKE RIVIERA WING C’s extension records on MahaRERA (P51800018480), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on LAKE RIVIERA WING C

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 18 complaints and 6 court cases, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800018480
Status
Registered and active
Builder
PASHMINA REALTY PRIVATE LIMITED
Location
Chandivali, Mumbai · 400072
Project type
Residential / Group Housing
Registered on
5 Nov 2018
Completion date at registration
December 2023
Latest completion date
April 2028
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
75
Sold or booked
75%
Towers
1
Complaints on MahaRERA
18
Court cases listed
6
Appeals at the tribunal
7
MahaRERA regulatory orders
1
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of LAKE RIVIERA WING C, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
LAKE RIVIERA WING C60%50%9%0%

Commencement certificate (CC), as filed on MahaRERA

  • LAKE RIVIERA WING C: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on LAKE RIVIERA WING C every month.

LAKE RIVIERA WING C: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK705 – 73555
3 BHK705 – 99520

The builder’s record and reviews

Pashmina Realty (a group of 2 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 still being built, 1 past the promised date (typically 18 months late); 3 lapsed. 78 complaints on MahaRERA across 4 projects.

Read Google reviews of LAKE RIVIERA WING C →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

LAKE RIVIERA WING C: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about LAKE RIVIERA WING C

What is the possession date of LAKE RIVIERA WING C?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for LAKE RIVIERA WING C in Chandivali, Mumbai is 30 April 2028 — 48 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for LAKE RIVIERA WING C?

Builders and listing sites often quote an earlier "target" date for handover. The completion date LAKE RIVIERA WING C's builder has filed on MahaRERA, the official one, is 30 April 2028, already 48 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of LAKE RIVIERA WING C extended?

According to GharKundli's check of MahaRERA records (updated October 2026), LAKE RIVIERA WING C's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2024, giving the reason "The SRA issued the First Stop Work Order dated 31st March, 2021 and the construction vis-à-vis the project was stopped. The SRA withdrew the First Stop Work Order on 22nd April, 2021. The SRA issued the Second Stop Work Order dated 25th May, 2022 and the construction vis-à-vis the project was again stopped, causing further loss of time and monies as well. Thereafter, the SRA issued the S. 53(1) Notice under the MRTP dated 20th July, 2022 in furtherance of the Second Stop Work Order. After 5 months and constant deliberation, representations and requests the SRA vide its Withdrawal of Second…"; to 29 June 2025, giving the reason "We are filing this Application in order to seek an exclusion of time of 6 (six) months that was unproductive and unused due to the stop work notices issued by the Slum Rehabilitation Authority during the course of the said Project being registered with RERA."; to 30 December 2027, giving the reason "Reasons for Delay (a)Subsequent Civil Aviation Clearance and Revised Height Restrictions:-Although the project had obtained the requisite building permissions and Commencement Certificate from the Planning Authority based on the approvals prevailing at the relevant time, subsequent to such approvals, additional conditions and clearance requirements were imposed by the Civil Aviation Authorities/Airports Authority of India due to the project's location within the regulated funnel zone of the airport. The revised Civil Aviation requirements necessitated obtaining fresh clearances, submission…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of LAKE RIVIERA WING C?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of LAKE RIVIERA WING C in Chandivali, Mumbai is P51800018480.

Is LAKE RIVIERA WING C registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), LAKE RIVIERA WING C is registered as P51800018480 and its status is "Registered and active".

What is the construction status of LAKE RIVIERA WING C?

According to GharKundli's check of MahaRERA records (updated October 2026), LAKE RIVIERA WING C's status on MahaRERA is "Registered and active". As filed by the builder, slab work on LAKE RIVIERA WING C is 50% done and internal work 9%. GharKundli's full report compares construction progress with the deadline.

Does LAKE RIVIERA WING C have complaints on MahaRERA?

18 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is LAKE RIVIERA WING C safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), LAKE RIVIERA WING C is registered on MahaRERA as P51800018480, its completion date has moved 48 months since registration and 18 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does LAKE RIVIERA WING C have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: LAKE RIVIERA WING A AND B (P51800009353, possession 31 Dec 2025); LAKE RIVIERA WING D (P51800048354, possession 30 Apr 2028). Check that your agreement names the registration of your own wing.

How can I get updates if LAKE RIVIERA WING C's possession date changes?

The latest dates are on LAKE RIVIERA WING C's MahaRERA page (P51800018480). GharKundli's Kundli Watch sends a free WhatsApp update on LAKE RIVIERA WING C every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does LAKE RIVIERA WING C have?

According to GharKundli's check of MahaRERA records (updated October 2026), LAKE RIVIERA WING C has one building filed: LAKE RIVIERA WING C with 24 floors and 75 units.

What are the flat sizes (carpet area) in LAKE RIVIERA WING C?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for LAKE RIVIERA WING C: 2 BHK: 705 to 735 sq ft carpet (55 homes); 3 BHK: 705 to 995 sq ft carpet (20 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does LAKE RIVIERA WING C have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for LAKE RIVIERA WING C.

How big is the land of LAKE RIVIERA WING C?

According to GharKundli's check of MahaRERA records (updated October 2026), LAKE RIVIERA WING C stands on 333 sq m of land (about 0.1 acres), with 4,029 sq m of sanctioned built-up area.

What is the track record of LAKE RIVIERA WING C's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Pashmina Realty (a group of 2 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 still being built, 1 past the promised date (typically 18 months late); 3 lapsed. 78 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of LAKE RIVIERA WING C?

Google Maps has reviews of LAKE RIVIERA WING C written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 18 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is LAKE RIVIERA WING C?

LAKE RIVIERA WING C by PASHMINA REALTY PRIVATE LIMITED is in Chandivali, Mumbai (pincode 400072), near Powai, Sakinaka, Nahar Amrit Shakti, Maharashtra, and is registered on MahaRERA as P51800018480, per GharKundli's check of MahaRERA records.

How many homes are in LAKE RIVIERA WING C?

According to GharKundli's check of MahaRERA records (updated October 2026), LAKE RIVIERA WING C has 75 homes in 1 tower registered on MahaRERA, and 75% of them are sold or booked.

When was LAKE RIVIERA WING C registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), LAKE RIVIERA WING C was registered on MahaRERA on 5 November 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on LAKE RIVIERA WING C?

6 court cases are listed for LAKE RIVIERA WING C on MahaRERA, and 7 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of LAKE RIVIERA WING C?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PASHMINA REALTY PRIVATE LIMITED, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Chandivali

All 75 projects in Powai (400072) →

Other projects by PASHMINA REALTY PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.