PADMAVATI TOWERS
by GOLD GHAR CONSTRUCTIONS PVT LTD · Santacruz East, MumbaiAlso near Chembur, Kalina, Bandra East
Possession date of PADMAVATI TOWERS: 30 December 2026, moved from 30 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800019132, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about PADMAVATI TOWERS?
How the possession date of PADMAVATI TOWERS has moved
30 December 2024
Completion date given when the project was registered
30 December 2025
Extended at the builder's request (MahaRERA application EXT51800025208)
Reason the builder gave MahaRERA:
“One of the director Mr Jayesh Parikh is suffering from Mouth Cancer. He had to undergo surgery and Kemo. The project remains uncompleted due to his absence in Company operations. The directors are confident of completing the project by end…” Read the full reason
“One of the director Mr Jayesh Parikh is suffering from Mouth Cancer. He had to undergo surgery and Kemo. The project remains uncompleted due to his absence in Company operations. The directors are confident of completing the project by end of next year and are therefore seeking one year extension for completing the project.”30 December 2026
Extended at the builder's request (MahaRERA application EA02012619255)
Reason the builder gave MahaRERA: “The project could not be completed within the stipulated time due to working is pending and unforeseen circumstances beyond the control of the promoter. Hence, extension of project registration is requested.”
Source: PADMAVATI TOWERS’s extension records on MahaRERA (P51800019132), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PADMAVATI TOWERS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800019132
- Status
- Registered and active
- Builder
- GOLD GHAR CONSTRUCTIONS PVT LTD
- Location
- Santacruz East, Mumbai · 400098
- Project type
- Residential / Group Housing
- Registered on
- 9 Jan 2019
- Completion date at registration
- December 2024
- Latest completion date
- December 2026
- Delay so far
- 24 months
- Homes
- 57
- Sold or booked
- 39%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of PADMAVATI TOWERS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PADMAVATI TOWERS B WING | 100% | 100% | 50% | 0% |
| PADMAVATI TOWERS C WING | 100% | 100% | 60% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- PADMAVATI TOWERS B WING: covers 13 floors
- PADMAVATI TOWERS C WING: covers 12 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PADMAVATI TOWERS every month.
PADMAVATI TOWERS: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 538 – 770 | 51 |
| 1 BHK | 282 | 6 |
- Buildings: PADMAVATI TOWERS B WING (14 floors, 9 units) · PADMAVATI TOWERS C WING (14 floors, 48 units)
- Car parking: 32 covered, 14 open
- Land: 1,910 sq m (about 0.5 acres) · sanctioned built-up 4,410 sq m · recreational space 148 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of PADMAVATI TOWERS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PADMAVATI TOWERS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PADMAVATI TOWERS
What is the possession date of PADMAVATI TOWERS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PADMAVATI TOWERS in Santacruz East, Mumbai is 30 December 2026 — 24 months later than 30 December 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for PADMAVATI TOWERS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PADMAVATI TOWERS's builder has filed on MahaRERA, the official one, is 30 December 2026, already 24 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PADMAVATI TOWERS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), PADMAVATI TOWERS's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2025, giving the reason "One of the director Mr Jayesh Parikh is suffering from Mouth Cancer. He had to undergo surgery and Kemo. The project remains uncompleted due to his absence in Company operations. The directors are confident of completing the project by end of next year and are therefore seeking one year extension for completing the project."; to 30 December 2026, giving the reason "The project could not be completed within the stipulated time due to working is pending and unforeseen circumstances beyond the control of the promoter. Hence, extension of project registration is requested.".
What is the RERA number of PADMAVATI TOWERS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PADMAVATI TOWERS in Santacruz East, Mumbai is P51800019132.
Is PADMAVATI TOWERS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PADMAVATI TOWERS is registered as P51800019132 and its status is "Registered and active".
What is the construction status of PADMAVATI TOWERS?
According to GharKundli's check of MahaRERA records (updated October 2026), PADMAVATI TOWERS's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does PADMAVATI TOWERS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is PADMAVATI TOWERS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), PADMAVATI TOWERS is registered on MahaRERA as P51800019132, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PADMAVATI TOWERS's possession date changes?
The latest dates are on PADMAVATI TOWERS's MahaRERA page (P51800019132). GharKundli's Kundli Watch sends a free WhatsApp update on PADMAVATI TOWERS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PADMAVATI TOWERS have?
According to GharKundli's check of MahaRERA records (updated October 2026), PADMAVATI TOWERS has 2 buildings filed: PADMAVATI TOWERS B WING with 14 floors and 9 units; PADMAVATI TOWERS C WING with 14 floors and 48 units.
What are the flat sizes (carpet area) in PADMAVATI TOWERS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for PADMAVATI TOWERS: 2 BHK: 538 to 770 sq ft carpet (51 homes); 1 BHK: 282 sq ft carpet (6 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does PADMAVATI TOWERS have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 32 covered and 14 open car parking spaces for PADMAVATI TOWERS.
How big is the land of PADMAVATI TOWERS?
According to GharKundli's check of MahaRERA records (updated October 2026), PADMAVATI TOWERS stands on 1,910 sq m of land (about 0.5 acres), with 4,410 sq m of sanctioned built-up area and 148 sq m of recreational open space.
Where can I read reviews of PADMAVATI TOWERS?
Google Maps has reviews of PADMAVATI TOWERS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PADMAVATI TOWERS?
PADMAVATI TOWERS by GOLD GHAR CONSTRUCTIONS PVT LTD is in Santacruz East, Mumbai (pincode 400098), near Chembur, Kalina, Bandra East, Maharashtra, and is registered on MahaRERA as P51800019132, per GharKundli's check of MahaRERA records.
How many homes are in PADMAVATI TOWERS?
According to GharKundli's check of MahaRERA records (updated October 2026), PADMAVATI TOWERS has 57 homes in 2 towers registered on MahaRERA, and 39% of them are sold or booked.
When was PADMAVATI TOWERS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PADMAVATI TOWERS was registered on MahaRERA on 9 January 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on PADMAVATI TOWERS?
No court cases are listed for PADMAVATI TOWERS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of PADMAVATI TOWERS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GOLD GHAR CONSTRUCTIONS PVT LTD.
Check it yourself on MahaRERA
- How to check the possession date of PADMAVATI TOWERS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Santacruz East
- CRYSTAL AVENUE
- SANA ENCLAVE
- PRUTHI ANNEXE
- Miraya Residency
- SUNFLOWER REALINFRA LLP ASTER
- CENTRAL PARK
- Courtyard
- PRABHAT KUNJ
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.