Skip to content
GharKundli

SIENNAA WING B

by S D Corporation Private Limited · Kandivali, Mumbai

Possession date of SIENNAA WING B: 31 March 2024, moved from 30 December 2023 (3 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800019658. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (March 2024) has passed.

What do you want to know about SIENNAA WING B?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SIENNAA WING B has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT51800017999)

    Reason the builder gave MahaRERA:
    “This is to state that the ongoing construction activities of project SIENNAA Wing B was impacted due to the lockdown imposed citing the pandemic COVID 19. The impact of the lockdown resulted in severe restrictions to mobility, lack of avail…” Read the full reason“This is to state that the ongoing construction activities of project SIENNAA Wing B was impacted due to the lockdown imposed citing the pandemic COVID 19. The impact of the lockdown resulted in severe restrictions to mobility, lack of availability of requisite building materials and non-availability of skilled labour. These factors impacted the pace of the ongoing construction of the project SIENNAA Wing A causing an unavoidable delay of 3 months from the earlier proposed. In view of the above would request you to grant extension of 3 months and the project will be completed by 31st March 2…”

Source: SIENNAA WING B’s extension records on MahaRERA (P51800019658), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SIENNAA WING B

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints and 1 court case, and how it ended
  • Construction pace against the March 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800019658
Status
Lapsed (registration period ended)
Builder
S D Corporation Private Limited
Location
Kandivali, Mumbai · 400101
Project type
Residential / Group Housing
Registered on
20 Feb 2019
Completion date at registration
December 2023
Latest completion date
March 2024
Delay so far
3 months
Towers
1
Complaints on MahaRERA
2
Court cases listed
1
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
13

Construction progress of SIENNAA WING B, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SIENNAA WING B100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SIENNAA WING B every month.

SIENNAA WING B: buildings, flats and land, as filed on MahaRERA

  • Buildings: SIENNAA WING B (28 floors)
  • Land: 304 sq m (about 0.1 acres) · sanctioned built-up 4,748 sq m · recreational space 332 sq m

The builder’s record and reviews

Vakratunda Buildcon (a group of 10 linked companies) has 51 projects on MahaRERA since 2017, this one included. Of the 50 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 16 months); 38 still being built, 15 past the promised date (typically 6 months late); 5 lapsed. 454 complaints on MahaRERA across 32 projects.

Read Google reviews of SIENNAA WING B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SIENNAA WING B: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SIENNAA WING B

What is the possession date of SIENNAA WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SIENNAA WING B in Kandivali, Mumbai is 31 March 2024 — 3 months later than 30 December 2023, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SIENNAA WING B?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SIENNAA WING B's builder has filed on MahaRERA, the official one, is 31 March 2024, already 3 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SIENNAA WING B extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SIENNAA WING B's builder applied to MahaRERA to extend the completion date once: to 31 March 2024, giving the reason "This is to state that the ongoing construction activities of project SIENNAA Wing B was impacted due to the lockdown imposed citing the pandemic COVID 19. The impact of the lockdown resulted in severe restrictions to mobility, lack of availability of requisite building materials and non-availability of skilled labour. These factors impacted the pace of the ongoing construction of the project SIENNAA Wing A causing an unavoidable delay of 3 months from the earlier proposed. In view of the above would request you to grant extension of 3 months and the project will be completed by 31st March 2…".

What is the RERA number of SIENNAA WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SIENNAA WING B in Kandivali, Mumbai is P51800019658.

Is SIENNAA WING B registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SIENNAA WING B is registered as P51800019658 and its status is "Lapsed (registration period ended)".

What is the construction status of SIENNAA WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), SIENNAA WING B's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SIENNAA WING B is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SIENNAA WING B have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SIENNAA WING B safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SIENNAA WING B is registered on MahaRERA as P51800019658, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 3 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does SIENNAA WING B have other wings or phases?

Yes. MahaRERA lists 5 other registrations of the same project, each with its own possession date: SIENNAA WING A (P51800019624, possession 31 Mar 2024); SIENNAA WING C (P51800019659, possession 31 Mar 2024); SIENNAA WING D (P51800019643, possession 30 Oct 2027); SIENNAA WING E (P51800019677, possession 30 Apr 2028); SIENNAA WING F (P51800019693, possession 30 Apr 2028). Check that your agreement names the registration of your own wing.

How can I get updates if SIENNAA WING B's possession date changes?

The latest dates are on SIENNAA WING B's MahaRERA page (P51800019658). GharKundli's Kundli Watch sends a free WhatsApp update on SIENNAA WING B every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SIENNAA WING B have?

According to GharKundli's check of MahaRERA records (updated October 2026), SIENNAA WING B has one building filed: SIENNAA WING B with 28 floors.

How big is the land of SIENNAA WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), SIENNAA WING B stands on 304 sq m of land (about 0.1 acres), with 4,748 sq m of sanctioned built-up area and 332 sq m of recreational open space.

What is the track record of SIENNAA WING B's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vakratunda Buildcon (a group of 10 linked companies) has 51 projects on MahaRERA since 2017, this one included. Of the 50 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 16 months); 38 still being built, 15 past the promised date (typically 6 months late); 5 lapsed. 454 complaints on MahaRERA across 32 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SIENNAA WING B?

Google Maps has reviews of SIENNAA WING B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SIENNAA WING B?

SIENNAA WING B by S D Corporation Private Limited is in Kandivali, Mumbai (pincode 400101), Maharashtra, and is registered on MahaRERA as P51800019658, per GharKundli's check of MahaRERA records.

When was SIENNAA WING B registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SIENNAA WING B was registered on MahaRERA on 20 February 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on SIENNAA WING B?

1 court case is listed for SIENNAA WING B on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SIENNAA WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is S D Corporation Private Limited, which has 13 other projects registered on MahaRERA.

Other projects in pincode 400101

All 113 projects in Kandivali East (400101) →

Other projects by S D Corporation Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.