Possession date of Atmosphere O2: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800019950, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 13 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Atmosphere O2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Atmosphere O2 has moved

  1. 30 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Atmosphere O2’s extension records on MahaRERA (P51800019950), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Atmosphere O2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 13 complaints and 5 court cases, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800019950
Status
Registered and active
Builder
Atmosphere Realty Pvt Ltd
Location
Chembur West, Mumbai · 400080
Project type
Residential / Group Housing
Registered on
15 Mar 2019
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
830
Sold or booked
95%
Towers
3
Complaints on MahaRERA
13
Court cases listed
5
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Atmosphere O2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
TOWER D100%100%100%100%
TOWER E100%100%100%100%
TOWER F100%100%82%0%

Commencement certificate (CC), as filed on MahaRERA

  • TOWER D: covers 47 floors
  • TOWER E: covers 47 floors
  • TOWER F: covers 47 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Atmosphere O2 every month.

Atmosphere O2: buildings, flats and land, as filed on MahaRERA

  • Buildings: TOWER D (53 floors, 220 units) · TOWER E (53 floors, 261 units) · TOWER F (53 floors, 349 units)
  • Land: 1,990 sq m (about 0.5 acres) · sanctioned built-up 1,06,164 sq m
  • Boundaries filed include: Central Railway line, Mulund Goregaon Link road

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Atmosphere O2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Atmosphere O2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Atmosphere O2

What is the possession date of Atmosphere O2?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Atmosphere O2 in Chembur West, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Atmosphere O2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Atmosphere O2's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Atmosphere O2?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Atmosphere O2 in Chembur West, Mumbai is P51800019950.

Is Atmosphere O2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Atmosphere O2 is registered as P51800019950 and its status is "Registered and active".

What is the construction status of Atmosphere O2?

According to GharKundli's check of MahaRERA records (updated November 2026), Atmosphere O2's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Atmosphere O2 have complaints on MahaRERA?

13 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Atmosphere O2 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Atmosphere O2 is registered on MahaRERA as P51800019950, its completion date has not been moved by the builder and 13 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Atmosphere O2 have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Atmosphere O2 Tower-G (P51800033845, possession 30 Apr 2029); Atmosphere Phase 1 (P51800001243, possession 31 Oct 2019). Check that your agreement names the registration of your own wing.

How can I get updates if Atmosphere O2's possession date changes?

The latest dates are on Atmosphere O2's MahaRERA page (P51800019950). GharKundli's Kundli Watch sends a free WhatsApp update on Atmosphere O2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Atmosphere O2 have?

According to GharKundli's check of MahaRERA records (updated November 2026), Atmosphere O2 has 3 buildings filed: TOWER D with 53 floors and 220 units; TOWER E with 53 floors and 261 units; TOWER F with 53 floors and 349 units.

How big is the land of Atmosphere O2?

According to GharKundli's check of MahaRERA records (updated November 2026), Atmosphere O2 stands on 1,990 sq m of land (about 0.5 acres), with 1,06,164 sq m of sanctioned built-up area.

Where can I read reviews of Atmosphere O2?

Google Maps has reviews of Atmosphere O2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 13 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Atmosphere O2?

Atmosphere O2 by Atmosphere Realty Pvt Ltd is in Chembur West, Mumbai (pincode 400080), near Mulund West, Mulund East, Maharashtra, and is registered on MahaRERA as P51800019950, per GharKundli's check of MahaRERA records. Its boundaries filed there include Central Railway line, Mulund Goregaon Link road.

How many homes are in Atmosphere O2?

According to GharKundli's check of MahaRERA records (updated November 2026), Atmosphere O2 has 830 homes in 3 towers registered on MahaRERA, and 95% of them are sold or booked.

When was Atmosphere O2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Atmosphere O2 was registered on MahaRERA on 15 March 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Atmosphere O2?

5 court cases are listed for Atmosphere O2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Atmosphere O2?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Atmosphere Realty Pvt Ltd, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Chembur West

All 303 projects in Mulund West (400080) →

Other projects by Atmosphere Realty Pvt Ltd

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.