Possession date of STAR HEIGHTS: 30 April 2027, moved from 30 June 2023 (42 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800029196, and currently active. Its completion date has moved from June 2023 to April 2027: 42 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about STAR HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of STAR HEIGHTS has moved

  1. 30 June 2023

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT51800016674)

    Reason the builder gave MahaRERA:
    “1. Pandemic Covid: Covid-19 strain begun in China in the month Dec 19, In India first lock down started in the month of March 20. Pandemic had affected adversely to entire mankind and affected the entire world. The industry has been complet…” Read the full reason“1. Pandemic Covid: Covid-19 strain begun in China in the month Dec 19, In India first lock down started in the month of March 20. Pandemic had affected adversely to entire mankind and affected the entire world. The industry has been completely shut down. Subsequently even the second wave erupted in April 2021 which was more severe than the first wave and it has further worsen the situation. During the pandemic labourers had gone to its hometown didn’t came back to city for work which creates the shortages of manpower. There were lot of casualties during this period. There were massive lock…”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: STAR HEIGHTS’s extension records on MahaRERA (P51800029196), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on STAR HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800029196
Status
Registered and active
Builder
STARWOOD BUILDER AND DEVELOPER
Location
Kalina Santacruz, Mumbai · 400098
Project type
Others
Registered on
3 May 2021
Completion date at registration
June 2023
Latest completion date
April 2027
Delay so far
42 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
38
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of STAR HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
STAR HEIGHTS100%100%68%30%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on STAR HEIGHTS every month.

STAR HEIGHTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: STAR HEIGHTS (15 floors)
  • Land: 591 sq m (about 0.1 acres) · sanctioned built-up 2,217 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of STAR HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

STAR HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about STAR HEIGHTS

What is the possession date of STAR HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for STAR HEIGHTS in Kalina Santacruz, Mumbai is 30 April 2027 — 42 months later than 30 June 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for STAR HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date STAR HEIGHTS's builder has filed on MahaRERA, the official one, is 30 April 2027, already 42 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of STAR HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), STAR HEIGHTS's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "1. Pandemic Covid: Covid-19 strain begun in China in the month Dec 19, In India first lock down started in the month of March 20. Pandemic had affected adversely to entire mankind and affected the entire world. The industry has been completely shut down. Subsequently even the second wave erupted in April 2021 which was more severe than the first wave and it has further worsen the situation. During the pandemic labourers had gone to its hometown didn’t came back to city for work which creates the shortages of manpower. There were lot of casualties during this period. There were massive lock…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of STAR HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of STAR HEIGHTS in Kalina Santacruz, Mumbai is P51800029196.

Is STAR HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), STAR HEIGHTS is registered as P51800029196 and its status is "Registered and active".

What is the construction status of STAR HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), STAR HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on STAR HEIGHTS is 100% done and internal work 68%. GharKundli's full report compares construction progress with the deadline.

Does STAR HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is STAR HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), STAR HEIGHTS is registered on MahaRERA as P51800029196, its completion date has moved 42 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if STAR HEIGHTS's possession date changes?

The latest dates are on STAR HEIGHTS's MahaRERA page (P51800029196). GharKundli's Kundli Watch sends a free WhatsApp update on STAR HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does STAR HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), STAR HEIGHTS has one building filed: STAR HEIGHTS with 15 floors.

How big is the land of STAR HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), STAR HEIGHTS stands on 591 sq m of land (about 0.1 acres), with 2,217 sq m of sanctioned built-up area.

Where can I read reviews of STAR HEIGHTS?

Google Maps has reviews of STAR HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is STAR HEIGHTS?

STAR HEIGHTS by STARWOOD BUILDER AND DEVELOPER is in Kalina Santacruz, Mumbai (pincode 400098), Maharashtra, and is registered on MahaRERA as P51800029196, per GharKundli's check of MahaRERA records.

How many homes are in STAR HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), STAR HEIGHTS has 38 homes in 1 tower registered on MahaRERA.

When was STAR HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), STAR HEIGHTS was registered on MahaRERA on 3 May 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on STAR HEIGHTS?

No court cases are listed for STAR HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of STAR HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is STARWOOD BUILDER AND DEVELOPER.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Andheri

All 30 projects in Santacruz East (400098) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.