VERTU
by BALAJI CORPORATION PRIVATE LIMITED · Wadala, MumbaiAlso near Dadar East, Matunga (CR), Barc
Possession date of VERTU: 30 December 2021, moved from 31 December 2019 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900005401. Status: Lapsed (registration period ended). 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2021) has passed.
What do you want to know about VERTU?
How the possession date of VERTU has moved
31 December 2019
Completion date given when the project was registered
31 December 2020
Extended at the builder's request (MahaRERA application EXT51900005270)
Reason the builder gave MahaRERA:
“1. The MHADA abnormally delayed (a) intimating us about handover of surplus Built Up Area and (b) took abnormal time in completing the formalities of handing over the surplus Built Up Area. 2. The MCGM Estate Department has not been able to…” Read the full reason
“1. The MHADA abnormally delayed (a) intimating us about handover of surplus Built Up Area and (b) took abnormal time in completing the formalities of handing over the surplus Built Up Area. 2. The MCGM Estate Department has not been able to intimate us the balance payment of one-time premium required to be paid due to their office records not available for calculating the premium amount. 3. There were several on-going litigations which created hurdles in redevelopment and some of them are still continuing for no fault on our part and have dragged on beyond reasonable time. These litigations…”30 December 2021
Revised completion date on MahaRERA
Source: VERTU’s extension records on MahaRERA (P51900005401), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VERTU
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints and 7 court cases, and how it ended
- Construction pace against the December 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900005401
- Status
- Lapsed (registration period ended)
- Builder
- BALAJI CORPORATION PRIVATE LIMITED
- Location
- Wadala, Mumbai · 400031
- Project type
- Residential / Group Housing
- Registered on
- 11 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2021
- Delay so far
- 24 months
- Homes
- 39
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 7
- Title report on file
- Not found
Construction progress of VERTU, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| VERTU | 90% | 90% | 90% | 70% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VERTU every month.
VERTU: buildings, flats and land, as filed on MahaRERA
- Buildings: VERTU (45 floors)
- Land: 2,350 sq m (about 0.6 acres) · sanctioned built-up 5,938 sq m · recreational space 211 sq m
- Boundaries filed include: KATRAK ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of VERTU →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VERTU: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VERTU
What is the possession date of VERTU?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for VERTU in Wadala, Mumbai is 30 December 2021 — 24 months later than 31 December 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for VERTU?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VERTU's builder has filed on MahaRERA, the official one, is 30 December 2021, already 24 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of VERTU extended?
According to GharKundli's check of MahaRERA records (updated November 2026), VERTU's builder applied to MahaRERA to extend the completion date once: to 31 December 2020, giving the reason "1. The MHADA abnormally delayed (a) intimating us about handover of surplus Built Up Area and (b) took abnormal time in completing the formalities of handing over the surplus Built Up Area. 2. The MCGM Estate Department has not been able to intimate us the balance payment of one-time premium required to be paid due to their office records not available for calculating the premium amount. 3. There were several on-going litigations which created hurdles in redevelopment and some of them are still continuing for no fault on our part and have dragged on beyond reasonable time. These litigations…".
What is the RERA number of VERTU?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of VERTU in Wadala, Mumbai is P51900005401.
Is VERTU registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), VERTU is registered as P51900005401 and its status is "Lapsed (registration period ended)".
What is the construction status of VERTU?
According to GharKundli's check of MahaRERA records (updated November 2026), VERTU's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on VERTU is 90% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does VERTU have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is VERTU safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), VERTU is registered on MahaRERA as P51900005401, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VERTU's possession date changes?
The latest dates are on VERTU's MahaRERA page (P51900005401). GharKundli's Kundli Watch sends a free WhatsApp update on VERTU every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VERTU have?
According to GharKundli's check of MahaRERA records (updated November 2026), VERTU has one building filed: VERTU with 45 floors.
How big is the land of VERTU?
According to GharKundli's check of MahaRERA records (updated November 2026), VERTU stands on 2,350 sq m of land (about 0.6 acres), with 5,938 sq m of sanctioned built-up area and 211 sq m of recreational open space.
Where can I read reviews of VERTU?
Google Maps has reviews of VERTU written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VERTU?
VERTU by BALAJI CORPORATION PRIVATE LIMITED is in Wadala, Mumbai (pincode 400031), near Dadar East, Matunga (CR), Barc, Maharashtra, and is registered on MahaRERA as P51900005401, per GharKundli's check of MahaRERA records. Its boundaries filed there include KATRAK ROAD.
How many homes are in VERTU?
According to GharKundli's check of MahaRERA records (updated November 2026), VERTU has 39 homes in 1 tower registered on MahaRERA.
When was VERTU registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), VERTU was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on VERTU?
7 court cases are listed for VERTU on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of VERTU?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is BALAJI CORPORATION PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of VERTU
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400031
- Skye 31
- Aura Bliss
- Shanti Kunj- A Project by Tridhaatu
- New National Market Annexe
- Dignity Bayview
- Godrej Horizon Phase II
- Rustomjee Vista Bay
- ALLIANCE HARMONY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.