SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2

by DILIP HIRALAL DOSHI · Goregoan West, MumbaiAlso near Kalanagar, Goregaon East, Pahadi Goregaon West

Possession: SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800021400. Status: Completed. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 has moved

  1. 30 March 2022

    Completion date given when the project was registered

  2. 30 September 2022

    Extended at the builder's request (MahaRERA application EXT51800011608)

    Reason the builder gave MahaRERA:
    “Due to corona pandemic after effects we need extension for our project Siddharth Nagar Sukhvilla CHSL (PHASE 2), Building no 6,Siddharth Nagar, Goregaon (W),Mumbai - 400104. We have already received FINAL NOC from fire department. My one MH…” Read the full reason“Due to corona pandemic after effects we need extension for our project Siddharth Nagar Sukhvilla CHSL (PHASE 2), Building no 6,Siddharth Nagar, Goregaon (W),Mumbai - 400104. We have already received FINAL NOC from fire department. My one MHADA Visit Is Also Done. Of the 4 passenger lifts 2 lifts have been installed and the other 2 lifts installation is in progress. We Ask For A 6 Months Extension. Kindly Grant the permission.”

Source: SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2’s extension records on MahaRERA (P51800021400), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the September 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800021400
Status
Completed
Builder
DILIP HIRALAL DOSHI
Location
Goregoan West, Mumbai · 400104
Project type
Residential / Group Housing
Registered on
26 Jun 2019
Completion date at registration
March 2022
Latest completion date
September 2022
Delay so far
6 months
Homes
41
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SUKHVILLA CHS LTD PHASE 2 FROM 12 TO 20 FLOORS100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 every month.

SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Dilip Hiralal Doshi has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 4 finished, all within the promised date. 3 complaints on MahaRERA across 2 projects.

Read Google reviews of SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2

What is the possession date of SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 in Goregoan West, Mumbai is 30 September 2022 — 6 months later than 30 March 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2's builder has filed on MahaRERA, the official one, is 30 September 2022, already 6 months later than the 30 March 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2's builder applied to MahaRERA to extend the completion date once: to 30 September 2022, giving the reason "Due to corona pandemic after effects we need extension for our project Siddharth Nagar Sukhvilla CHSL (PHASE 2), Building no 6,Siddharth Nagar, Goregaon (W),Mumbai - 400104. We have already received FINAL NOC from fire department. My one MHADA Visit Is Also Done. Of the 4 passenger lifts 2 lifts have been installed and the other 2 lifts installation is in progress. We Ask For A 6 Months Extension. Kindly Grant the permission.".

What is the RERA number of SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 in Goregoan West, Mumbai is P51800021400.

Is SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 is registered as P51800021400 and its status is "Completed".

What is the construction status of SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2's status on MahaRERA is "Completed". As filed by the builder, slab work on SUKHVILLA CHS LTD PHASE 2 FROM 12 TO 20 FLOORS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 is registered on MahaRERA as P51800021400, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Siddharth Nagar Sukhvilla CHS Ltd (P51800009426, possession 30 Jun 2018). Check that your agreement names the registration of your own wing.

How can I get updates if SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2's possession date changes?

The latest dates are on SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2's MahaRERA page (P51800021400). GharKundli's Kundli Watch sends a free WhatsApp update on SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 have?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 has one building filed: SUKHVILLA CHS LTD PHASE 2 FROM 12 TO 20 FLOORS with 12 floors.

How big is the land of SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 stands on 1,486 sq m of land (about 0.4 acres), with 3,445 sq m of sanctioned built-up area.

What is the track record of SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Dilip Hiralal Doshi has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 4 finished, all within the promised date. 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2?

Google Maps has reviews of SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2?

SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 by DILIP HIRALAL DOSHI is in Goregoan West, Mumbai (pincode 400104), near Kalanagar, Goregaon East, Pahadi Goregaon West, Maharashtra, and is registered on MahaRERA as P51800021400, per GharKundli's check of MahaRERA records.

How many homes are in SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 has 41 homes in 1 tower registered on MahaRERA.

When was SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 was registered on MahaRERA on 26 June 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2?

No court cases are listed for SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SIDDHARTH NAGAR SUKHVILLA CHS LTD PHASE- 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is DILIP HIRALAL DOSHI, which has 2 other projects registered on MahaRERA.

Other projects in pincode 400104

All 183 projects in Goregaon West (400104) →

Other projects by DILIP HIRALAL DOSHI

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.