by SUMER CORPORATION · Chandivali, MumbaiAlso near Powai, Sakinaka, Barve Nagar

Possession date of SUMER LIFE: 30 April 2028, moved from 30 December 2024 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800024414, and currently active. Its completion date has moved from December 2024 to April 2028: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project. 24 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SUMER LIFE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SUMER LIFE has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EXT51800024499)

    Reason the builder gave MahaRERA:
    “I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P51800024414.As per HEARING DATED 10th July 2025, Hon'ble Shri Manoj Saunik Sir granted Extension upto 31/12/2027. The order is upl…” Read the full reason“I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P51800024414.As per HEARING DATED 10th July 2025, Hon'ble Shri Manoj Saunik Sir granted Extension upto 31/12/2027. The order is uploaded in Other Tab for your reference”
  3. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SUMER LIFE’s extension records on MahaRERA (P51800024414), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SUMER LIFE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 24 complaints and 1 court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800024414
Status
Registered and active
Builder
SUMER CORPORATION
Location
Chandivali, Mumbai · 400072
Project type
Others
Registered on
12 Feb 2020
Completion date at registration
December 2024
Latest completion date
April 2028
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
309
Towers
3
Complaints on MahaRERA
24
Court cases listed
1
MahaRERA regulatory orders
1
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of SUMER LIFE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING -A100%16%40%25%
WING -B100%16%40%25%
WING - C100%16%40%25%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SUMER LIFE every month.

SUMER LIFE: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING -A (24 floors) · WING -B (24 floors) · WING - C (24 floors)
  • Land: 12,015 sq m (about 3.0 acres) · sanctioned built-up 17,214 sq m · recreational space 1,802 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Sumer Corporation (a group of 4 linked companies) has 5 projects on MahaRERA since 2019, this one included. Of the 5 GharKundli has checked: 4 still being built, 4 past the promised date (typically 12 months late); 1 lapsed. 31 complaints on MahaRERA across 2 projects.

Read Google reviews of SUMER LIFE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SUMER LIFE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SUMER LIFE

What is the possession date of SUMER LIFE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SUMER LIFE in Chandivali, Mumbai is 30 April 2028 — 36 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SUMER LIFE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SUMER LIFE's builder has filed on MahaRERA, the official one, is 30 April 2028, already 36 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SUMER LIFE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SUMER LIFE's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "I, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P51800024414.As per HEARING DATED 10th July 2025, Hon'ble Shri Manoj Saunik Sir granted Extension upto 31/12/2027. The order is uploaded in Other Tab for your reference". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SUMER LIFE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SUMER LIFE in Chandivali, Mumbai is P51800024414.

Is SUMER LIFE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SUMER LIFE is registered as P51800024414 and its status is "Registered and active".

What is the construction status of SUMER LIFE?

According to GharKundli's check of MahaRERA records (updated October 2026), SUMER LIFE's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 16% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does SUMER LIFE have complaints on MahaRERA?

24 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SUMER LIFE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SUMER LIFE is registered on MahaRERA as P51800024414, its completion date has moved 36 months since registration and 24 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SUMER LIFE's possession date changes?

The latest dates are on SUMER LIFE's MahaRERA page (P51800024414). GharKundli's Kundli Watch sends a free WhatsApp update on SUMER LIFE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SUMER LIFE have?

According to GharKundli's check of MahaRERA records (updated October 2026), SUMER LIFE has 3 buildings filed: WING -A with 24 floors; WING -B with 24 floors; WING - C with 24 floors.

How big is the land of SUMER LIFE?

According to GharKundli's check of MahaRERA records (updated October 2026), SUMER LIFE stands on 12,015 sq m of land (about 3.0 acres), with 17,214 sq m of sanctioned built-up area and 1,802 sq m of recreational open space.

What is the track record of SUMER LIFE's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sumer Corporation (a group of 4 linked companies) has 5 projects on MahaRERA since 2019, this one included. Of the 5 GharKundli has checked: 4 still being built, 4 past the promised date (typically 12 months late); 1 lapsed. 31 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SUMER LIFE?

Google Maps has reviews of SUMER LIFE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 24 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SUMER LIFE?

SUMER LIFE by SUMER CORPORATION is in Chandivali, Mumbai (pincode 400072), near Powai, Sakinaka, Barve Nagar, Maharashtra, and is registered on MahaRERA as P51800024414, per GharKundli's check of MahaRERA records.

How many homes are in SUMER LIFE?

According to GharKundli's check of MahaRERA records (updated October 2026), SUMER LIFE has 309 homes in 3 towers registered on MahaRERA.

When was SUMER LIFE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SUMER LIFE was registered on MahaRERA on 12 February 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on SUMER LIFE?

1 court case is listed for SUMER LIFE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SUMER LIFE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUMER CORPORATION, which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Chandivali

All 75 projects in Powai (400072) →