by Vardhan Associates · Malad East, Mumbai 400097Also near Malad West Dely, Motilal Nagar

What’s in the report? →

Possession date of Vardhan Royale (MahaRERA P51800024821): 29 May 2027, moved from 30 May 2024 (36 months later). It has 30 homes (1 BHK and 2 BHK, 215–766 sq ft carpet), 80% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800024821, and currently active. MahaRERA has issued a regulatory order on this project.

Source: MahaRERA website — records for P51800024821, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Vardhan Royale?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Vardhan Royale has moved

  1. 30 May 2024

    Completion date given when the project was registered

  2. 29 May 2025

    Extended at the builder's request (MahaRERA application EXT51800024098)

    Reason the builder gave MahaRERA:
    “Promoter has already completed the building and applied of OC, same is likely to be received in 2-3 months. The delay in getting OC is mainly because authorities of Mumbai Municipal corporation were busy in Lok sabha elections Therefore per…” Read the full reason“Promoter has already completed the building and applied of OC, same is likely to be received in 2-3 months. The delay in getting OC is mainly because authorities of Mumbai Municipal corporation were busy in Lok sabha elections Therefore period of ONE year is sought as and by way of extension for completion of project.Promoter is applying for extension under section 6 of RERA Act.”
  3. 30 May 2026

    Extended at the builder's request (MahaRERA application EA02062501389)

    Reason the builder gave MahaRERA: “Project timeline was significantly affected by nationwide lockdowns, labor migration, and restricted material movement. Certain approvals and completion NOCs experienced unanticipated procedural delays.”
  4. 29 May 2027

    Extended at the builder's request (MahaRERA application EA28052621134)

    Reason the builder gave MahaRERA:
    “The construction of the building has been completed, and possession has already been handed over to 57 allottees. We have applied for the Occupation Certificate (OC) before the Competent Authority; however, due to administrative and procedu…” Read the full reason“The construction of the building has been completed, and possession has already been handed over to 57 allottees. We have applied for the Occupation Certificate (OC) before the Competent Authority; however, due to administrative and procedural delays at the departmental level, the issuance of the Occupation Certificate is still pending.The said delay is entirely beyond our control. We have made sincere efforts to obtain the consent of the flat purchasers; however, despite our best efforts, the same could not be obtained. Accordingly, we are constrained to apply for extension under Order 40.…”

Source: Vardhan Royale’s extension records on MahaRERA (P51800024821), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Vardhan Royale

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the May 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800024821
Status
Registered and active
Builder
Vardhan Associates
Location
Malad East, Mumbai · 400097
Project type
Residential / Group Housing
Registered on
9 Mar 2020
Completion date at registration
May 2024
Latest completion date
May 2027
Delay so far
36 months
Homes
30
Sold or booked
80%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
MahaRERA regulatory orders
1
Title report on file
Not found

Construction progress of Vardhan Royale, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Vardhan Royale100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Vardhan Royale: covers 21 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vardhan Royale every 1–2 months.

Vardhan Royale: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK604 – 63521
1 BHK215 – 7669
  • Buildings: Vardhan Royale (25 floors, 30 units)
  • Car parking: 43 covered
  • Land: 1,418 sq m (about 0.4 acres) · sanctioned built-up 3,493 sq m · recreational space 131 sq m
  • Land, as filed: Survey No.329, Hissa No. 1 and bearing CTS no 432,4321 to 51 situate, lying, being at Pandit Solicitor Road, Off. Rani Sati marg, malad East, Mumbai 400097.
  • Map: Get directions

The builder’s record and reviews

Vardhan Reality (a group of 2 linked companies) has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 17 months late). No complaints on MahaRERA.

Read Google reviews of Vardhan Royale →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vardhan Royale: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Vardhan Royale

What is the possession date of Vardhan Royale?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vardhan Royale in Malad East, Mumbai is 29 May 2027 — 36 months later than 30 May 2024, the date given at registration.

The date has already moved 36 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Vardhan Royale?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vardhan Royale's builder has filed on MahaRERA, the official one, is 29 May 2027, already 36 months later than the 30 May 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Vardhan Royale extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Vardhan Royale's builder applied to MahaRERA to extend the completion date 3 times: to 29 May 2025, giving the reason "Promoter has already completed the building and applied of OC, same is likely to be received in 2-3 months. The delay in getting OC is mainly because authorities of Mumbai Municipal corporation were busy in Lok sabha elections Therefore period of ONE year is sought as and by way of extension for completion of project.Promoter is applying for extension under section 6 of RERA Act."; to 30 May 2026, giving the reason "Project timeline was significantly affected by nationwide lockdowns, labor migration, and restricted material movement. Certain approvals and completion NOCs experienced unanticipated procedural delays."; to 29 May 2027, giving the reason "The construction of the building has been completed, and possession has already been handed over to 57 allottees. We have applied for the Occupation Certificate (OC) before the Competent Authority; however, due to administrative and procedural delays at the departmental level, the issuance of the Occupation Certificate is still pending.The said delay is entirely beyond our control. We have made sincere efforts to obtain the consent of the flat purchasers; however, despite our best efforts, the same could not be obtained. Accordingly, we are constrained to apply for extension under Order 40.…".

What is the RERA number of Vardhan Royale?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vardhan Royale in Malad East, Mumbai is P51800024821.

Is Vardhan Royale registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vardhan Royale is registered as P51800024821 and its status is "Registered and active".

What is the current construction status of Vardhan Royale? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Vardhan Royale's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Vardhan Royale is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Vardhan Royale have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Vardhan Royale safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Vardhan Royale is registered on MahaRERA as P51800024821, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Vardhan Royale?

Vardhan Royale is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Vardhan Royale are 215 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Vardhan Royale?

For a flat in Vardhan Royale (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Vardhan Royale received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vardhan Royale is still under construction, with 29 May 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Vardhan Royale uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vardhan Royale was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Vardhan Royale's possession date changes?

The latest dates are on Vardhan Royale's MahaRERA page (P51800024821). GharKundli's Kundli Watch sends a free WhatsApp update on Vardhan Royale every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vardhan Royale have?

According to GharKundli's check of MahaRERA records (updated October 2026), Vardhan Royale has one building filed: Vardhan Royale with 25 floors and 30 units.

What are the flat sizes (carpet area) in Vardhan Royale?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Vardhan Royale: 2 BHK: 604 to 635 sq ft carpet (21 homes); 1 BHK: 215 to 766 sq ft carpet (9 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Vardhan Royale have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 43 covered car parking spaces for Vardhan Royale.

How big is the land of Vardhan Royale?

According to GharKundli's check of MahaRERA records (updated October 2026), Vardhan Royale stands on 1,418 sq m of land (about 0.4 acres), with 3,493 sq m of sanctioned built-up area and 131 sq m of recreational open space.

What is the track record of Vardhan Royale's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vardhan Reality (a group of 2 linked companies) has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 17 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Vardhan Royale?

Google Maps has reviews of Vardhan Royale written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Vardhan Royale?

Vardhan Royale by Vardhan Associates is in Malad East, Mumbai, pincode 400097 (near Malad West Dely, Motilal Nagar), Maharashtra, and is registered on MahaRERA as P51800024821, per GharKundli's check of MahaRERA records. Its land is filed as Survey No.329, Hissa No. 1 and bearing CTS no 432,4321 to 51 situate, lying, being at Pandit Solicitor Road, Off. Rani Sati marg, malad East, Mumbai 400097.. GharKundli lists all 195 MahaRERA projects in Malad East (400097).

How many flats are in Vardhan Royale, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Vardhan Royale has 30 homes in 1 tower registered on MahaRERA, and 80% of them are sold or booked.

When was Vardhan Royale registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vardhan Royale was registered on MahaRERA on 9 March 2020. GharKundli did not find a title report on the land on file there.

Does Vardhan Royale have any legal issues or court cases?

No court cases are listed for Vardhan Royale on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Vardhan Royale?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Vardhan Associates.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Malad East (400097)

All 195 projects in Malad East (400097) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.