Redevelopment of Vijayshree Chsl
by Heritage Lifestyles & Developers Pvt Ltd · Ghatkopar, Mumbai
Registered on MahaRERA under P51800025556, and currently active. Its completion date has moved from June 2024 to April 2028, 46 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
- MahaRERA registration
- P51800025556
- Status
- Registered and active
- Builder
- Heritage Lifestyles & Developers Pvt Ltd
- Location
- Ghatkopar, Mumbai · 400077
- Project type
- Residential / Group Housing
- Registered on
- 28 Jun 2020
- Completion date at registration
- June 2024
- Latest completion date
- April 2028
- Delay so far
- 46 months
- Homes
- 46
- Sold or booked
- 23%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
GharKundli’s full report on Redevelopment of Vijayshree Chsl
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Kundli Watch
Redevelopment of Vijayshree Chsl: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Redevelopment of Vijayshree Chsl
Is Redevelopment of Vijayshree Chsl registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Vijayshree Chsl is registered as P51800025556 and its status is "Registered and active".
Where is Redevelopment of Vijayshree Chsl?
Redevelopment of Vijayshree Chsl by Heritage Lifestyles & Developers Pvt Ltd is in Ghatkopar, Mumbai (pincode 400077), Maharashtra, and is registered on MahaRERA as P51800025556, per GharKundli's check of MahaRERA records.
When is possession of Redevelopment of Vijayshree Chsl due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Redevelopment of Vijayshree Chsl in Ghatkopar, Mumbai is 30 April 2028 — 46 months later than 30 June 2024, the date given at registration.
Does Redevelopment of Vijayshree Chsl have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Redevelopment of Vijayshree Chsl?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Heritage Lifestyles & Developers Pvt Ltd.
Other projects in pincode 400077
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.