Redevelopment of Vijayshree Chsl
by Heritage Lifestyles & Developers Pvt Ltd · Ghatkopar, Mumbai 400077
What’s in the report? →Possession date of Redevelopment of Vijayshree Chsl (MahaRERA P51800025556): 30 April 2028, moved from 30 June 2024 (42 months later). It has 46 homes (1 BHK and 2 BHK, 367–580 sq ft carpet), 23% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800025556, and currently active. Its completion date has moved from June 2024 to April 2028: 42 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800025556, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Redevelopment of Vijayshree Chsl?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Redevelopment of Vijayshree Chsl has moved
30 June 2024
Completion date given when the project was registered
30 June 2025
Extended at the builder's request (MahaRERA application EXT51800019102)
Reason the builder gave MahaRERA:
“DUE TO A DISPUTE RAISED BY THE NAEHIBOURING SOCIETY WITH BMC IN REGARDING OUR PROJECT DUE TO WHICH THE PROJECT GOT STALLED FOR 2 YEARS EVENTUALLY, WE AND OUR SOCIETY JOINTLY APPROACHED THE COLLECTOR SUBURBAN. HE CALLED FOR JOINT HEARING WIT…” Read the full reason
“DUE TO A DISPUTE RAISED BY THE NAEHIBOURING SOCIETY WITH BMC IN REGARDING OUR PROJECT DUE TO WHICH THE PROJECT GOT STALLED FOR 2 YEARS EVENTUALLY, WE AND OUR SOCIETY JOINTLY APPROACHED THE COLLECTOR SUBURBAN. HE CALLED FOR JOINT HEARING WITH ALL PARTIES AND PASSED ORDER IN OUR FAVOUR”31 December 2027
Extended at the builder's request (MahaRERA application EA17022619881)
Reason the builder gave MahaRERA: “Due to unforeseen legal and technical challenges beyond the control of the Developer which led to procedural delays in obtaining necessary approvals, sanctions, and permissions from MCGM and other competent authorities”
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Redevelopment of Vijayshree Chsl’s extension records on MahaRERA (P51800025556), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Redevelopment of Vijayshree Chsl
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800025556
- Status
- Registered and active
- Builder
- Heritage Lifestyles & Developers Pvt Ltd
- Location
- Ghatkopar, Mumbai · 400077
- Project type
- Residential / Group Housing
- Registered on
- 28 Jun 2020
- Completion date at registration
- June 2024
- Latest completion date
- April 2028
- Delay so far
- 42 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 46
- Sold or booked
- 23%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Redevelopment of Vijayshree Chsl, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Anjali Heritage | 100% | 70% | 70% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Anjali Heritage: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Redevelopment of Vijayshree Chsl every 1–2 months.
Redevelopment of Vijayshree Chsl: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 496 – 580 | 28 |
| 1 BHK | 367 – 426 | 18 |
- Buildings: Anjali Heritage (15 floors, 46 units)
- Land: 1,066 sq m (about 0.3 acres) · recreational space 160 sq m
- Boundaries filed include: Garden
- Land, as filed: plot no. 40 ctsno 194 pt village ghatkopar
- Map: Get directions
The builder’s record and reviews
Heritage Lifestyles & Developers (a group of 8 linked companies) has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 9 finished, 2 within the promised date and 7 needed more time (typically 20 months); 7 still being built, 2 past the promised date (typically 10 months late); 3 lapsed. 3 complaints on MahaRERA across 3 projects.
Read Google reviews of Redevelopment of Vijayshree Chsl →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Redevelopment of Vijayshree Chsl: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Redevelopment of Vijayshree Chsl
What is the possession date of Redevelopment of Vijayshree Chsl?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Redevelopment of Vijayshree Chsl in Ghatkopar, Mumbai is 30 April 2028 — 42 months later than 30 June 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 42 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Redevelopment of Vijayshree Chsl?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Redevelopment of Vijayshree Chsl's builder has filed on MahaRERA, the official one, is 30 April 2028, already 42 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Redevelopment of Vijayshree Chsl extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Vijayshree Chsl's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2025, giving the reason "DUE TO A DISPUTE RAISED BY THE NAEHIBOURING SOCIETY WITH BMC IN REGARDING OUR PROJECT DUE TO WHICH THE PROJECT GOT STALLED FOR 2 YEARS EVENTUALLY, WE AND OUR SOCIETY JOINTLY APPROACHED THE COLLECTOR SUBURBAN. HE CALLED FOR JOINT HEARING WITH ALL PARTIES AND PASSED ORDER IN OUR FAVOUR"; to 31 December 2027, giving the reason "Due to unforeseen legal and technical challenges beyond the control of the Developer which led to procedural delays in obtaining necessary approvals, sanctions, and permissions from MCGM and other competent authorities". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Redevelopment of Vijayshree Chsl?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Redevelopment of Vijayshree Chsl in Ghatkopar, Mumbai is P51800025556.
Is Redevelopment of Vijayshree Chsl registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Vijayshree Chsl is registered as P51800025556 and its status is "Registered and active".
What is the current construction status of Redevelopment of Vijayshree Chsl? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Vijayshree Chsl's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Anjali Heritage is 70% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.
Does Redevelopment of Vijayshree Chsl have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Redevelopment of Vijayshree Chsl safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Vijayshree Chsl is registered on MahaRERA as P51800025556, its completion date has moved 42 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Redevelopment of Vijayshree Chsl?
Redevelopment of Vijayshree Chsl is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Redevelopment of Vijayshree Chsl are 367 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Redevelopment of Vijayshree Chsl?
For a flat in Redevelopment of Vijayshree Chsl (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Redevelopment of Vijayshree Chsl received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Vijayshree Chsl is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Redevelopment of Vijayshree Chsl a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Vijayshree Chsl is a redevelopment: 24 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Redevelopment of Vijayshree Chsl uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Redevelopment of Vijayshree Chsl was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Redevelopment of Vijayshree Chsl's possession date changes?
The latest dates are on Redevelopment of Vijayshree Chsl's MahaRERA page (P51800025556). GharKundli's Kundli Watch sends a free WhatsApp update on Redevelopment of Vijayshree Chsl every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Redevelopment of Vijayshree Chsl have?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Vijayshree Chsl has one building filed: Anjali Heritage with 15 floors and 46 units.
What are the flat sizes (carpet area) in Redevelopment of Vijayshree Chsl?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Redevelopment of Vijayshree Chsl: 2 BHK: 496 to 580 sq ft carpet (28 homes); 1 BHK: 367 to 426 sq ft carpet (18 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Redevelopment of Vijayshree Chsl?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Vijayshree Chsl stands on 1,066 sq m of land (about 0.3 acres) and 160 sq m of recreational open space.
What is the track record of Redevelopment of Vijayshree Chsl's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Heritage Lifestyles & Developers (a group of 8 linked companies) has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 9 finished, 2 within the promised date and 7 needed more time (typically 20 months); 7 still being built, 2 past the promised date (typically 10 months late); 3 lapsed. 3 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Redevelopment of Vijayshree Chsl?
Google Maps has reviews of Redevelopment of Vijayshree Chsl written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Redevelopment of Vijayshree Chsl?
Redevelopment of Vijayshree Chsl by Heritage Lifestyles & Developers Pvt Ltd is in Ghatkopar, Mumbai, pincode 400077, Maharashtra, and is registered on MahaRERA as P51800025556, per GharKundli's check of MahaRERA records. Its boundaries filed there include Garden. Its land is filed as plot no. 40 ctsno 194 pt village ghatkopar. GharKundli lists all 228 MahaRERA projects in Ghatkopar East (400077).
How many flats are in Redevelopment of Vijayshree Chsl, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Vijayshree Chsl has 46 homes in 1 tower registered on MahaRERA, and 23% of them are sold or booked.
When was Redevelopment of Vijayshree Chsl registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Redevelopment of Vijayshree Chsl was registered on MahaRERA on 28 June 2020. GharKundli did not find a title report on the land on file there.
Does Redevelopment of Vijayshree Chsl have any legal issues or court cases?
No court cases are listed for Redevelopment of Vijayshree Chsl on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Redevelopment of Vijayshree Chsl?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Heritage Lifestyles & Developers Pvt Ltd.
Check it yourself on MahaRERA
- How to check the possession date of Redevelopment of Vijayshree Chsl
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Ghatkopar East (400077)
- Redevlopement of SBI Madhur Milan CHSL
- Pragati Elanza
- Lifescapes Prithvii
- Cypress Heights
- Ruparel Pristine
- Garden View
- Neelkanth Enclave D Wing Siddhartha
- Royale Residences B and C Wing
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.