Skip to content
GharKundli

LODHA ETERNIS IDYLLIA A

by LODHA DEVELOPERS LIMITED · Village Mulgaon, MumbaiAlso near Seepz, Chakala MIDC, Jogeshwari East

Possession: LODHA ETERNIS IDYLLIA A is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800026509. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about LODHA ETERNIS IDYLLIA A?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on LODHA ETERNIS IDYLLIA A

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 26 court cases, and how it ended
  • Construction pace against the June 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800026509
Status
Completed
Builder
LODHA DEVELOPERS LIMITED
Location
Village Mulgaon, Mumbai · 400093
Project type
Residential / Group Housing
Registered on
26 Sep 2020
Completion date at registration
June 2025
Latest completion date
June 2027
Delay so far
24 months
Homes
34
Sold or booked
94%
Towers
1
Complaints on MahaRERA
1
Court cases listed
26
Title report on file
Not found
Builder's other MahaRERA projects
180

Construction progress of LODHA ETERNIS IDYLLIA A, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING 12100%100%95%95%

Commencement certificate (CC), as filed on MahaRERA

  • WING 12: covers 11 floors

Latest CC order on MahaRERA: dated 14/05/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on LODHA ETERNIS IDYLLIA A every month.

LODHA ETERNIS IDYLLIA A: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Other673 – 91534
  • Buildings: WING 12 (11 floors, 34 units)
  • Car parking: 43 covered
  • Land: 1,277 sq m (about 0.3 acres) · sanctioned built-up 2,808 sq m · recreational space 372 sq m
  • Boundaries filed include: 13 40 mt wise road

The builder’s record and reviews

Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 373 GharKundli has checked: 207 finished, 189 within the promised date and 18 needed more time (typically 11 months); 166 still being built, 12 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects.

Read Google reviews of LODHA ETERNIS IDYLLIA A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

LODHA ETERNIS IDYLLIA A: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about LODHA ETERNIS IDYLLIA A

What is the possession date of LODHA ETERNIS IDYLLIA A?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for LODHA ETERNIS IDYLLIA A in Village Mulgaon, Mumbai is 30 June 2027 — 24 months later than 30 June 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for LODHA ETERNIS IDYLLIA A?

Builders and listing sites often quote an earlier "target" date for handover. The completion date LODHA ETERNIS IDYLLIA A's builder has filed on MahaRERA, the official one, is 30 June 2027, already 24 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of LODHA ETERNIS IDYLLIA A?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of LODHA ETERNIS IDYLLIA A in Village Mulgaon, Mumbai is P51800026509.

Is LODHA ETERNIS IDYLLIA A registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), LODHA ETERNIS IDYLLIA A is registered as P51800026509 and its status is "Completed".

What is the construction status of LODHA ETERNIS IDYLLIA A?

According to GharKundli's check of MahaRERA records (updated October 2026), LODHA ETERNIS IDYLLIA A's status on MahaRERA is "Completed". As filed by the builder, slab work on WING 12 is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does LODHA ETERNIS IDYLLIA A have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is LODHA ETERNIS IDYLLIA A safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), LODHA ETERNIS IDYLLIA A is registered on MahaRERA as P51800026509, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if LODHA ETERNIS IDYLLIA A's possession date changes?

The latest dates are on LODHA ETERNIS IDYLLIA A's MahaRERA page (P51800026509). GharKundli's Kundli Watch sends a free WhatsApp update on LODHA ETERNIS IDYLLIA A every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does LODHA ETERNIS IDYLLIA A have?

According to GharKundli's check of MahaRERA records (updated October 2026), LODHA ETERNIS IDYLLIA A has one building filed: WING 12 with 11 floors and 34 units.

What are the flat sizes (carpet area) in LODHA ETERNIS IDYLLIA A?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for LODHA ETERNIS IDYLLIA A: Other: 673 to 915 sq ft carpet (34 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does LODHA ETERNIS IDYLLIA A have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 43 covered car parking spaces for LODHA ETERNIS IDYLLIA A.

How big is the land of LODHA ETERNIS IDYLLIA A?

According to GharKundli's check of MahaRERA records (updated October 2026), LODHA ETERNIS IDYLLIA A stands on 1,277 sq m of land (about 0.3 acres), with 2,808 sq m of sanctioned built-up area and 372 sq m of recreational open space.

What is the track record of LODHA ETERNIS IDYLLIA A's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 373 GharKundli has checked: 207 finished, 189 within the promised date and 18 needed more time (typically 11 months); 166 still being built, 12 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of LODHA ETERNIS IDYLLIA A?

Google Maps has reviews of LODHA ETERNIS IDYLLIA A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is LODHA ETERNIS IDYLLIA A?

LODHA ETERNIS IDYLLIA A by LODHA DEVELOPERS LIMITED is in Village Mulgaon, Mumbai (pincode 400093), near Seepz, Chakala MIDC, Jogeshwari East, Maharashtra, and is registered on MahaRERA as P51800026509, per GharKundli's check of MahaRERA records. Its boundaries filed there include 13 40 mt wise road.

How many homes are in LODHA ETERNIS IDYLLIA A?

According to GharKundli's check of MahaRERA records (updated October 2026), LODHA ETERNIS IDYLLIA A has 34 homes in 1 tower registered on MahaRERA, and 94% of them are sold or booked.

When was LODHA ETERNIS IDYLLIA A registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), LODHA ETERNIS IDYLLIA A was registered on MahaRERA on 26 September 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on LODHA ETERNIS IDYLLIA A?

26 court cases are listed for LODHA ETERNIS IDYLLIA A on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of LODHA ETERNIS IDYLLIA A?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LODHA DEVELOPERS LIMITED, which has 180 other projects registered on MahaRERA.

All projects in Andheri East (400093) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.