Skip to content
GharKundli

Sheetala Sheetal Ganga Gobind

by SHEETALA DEVELOPERS · Opp Kalina Masjid, Mumbai 400055Registered on MahaRERA as “SHEETAL GANGA GOBIND”

What’s in the report? →

Possession date of Sheetala Sheetal Ganga Gobind (MahaRERA P51800026943): 31 December 2025, moved from 1 May 2024 (19 months later), and it has already passed. It has 63 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800026943. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800026943, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about Sheetala Sheetal Ganga Gobind?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Sheetala Sheetal Ganga Gobind has moved

  1. 1 May 2024

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800025117)

    Reason the builder gave MahaRERA: “We have in details with explanation why we need extension till 31-12-2025 and how we will complete our project till 31-12-2025”

Source: Sheetala Sheetal Ganga Gobind’s extension records on MahaRERA (P51800026943), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sheetala Sheetal Ganga Gobind

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800026943
Status
Lapsed (registration period ended)
Builder
SHEETALA DEVELOPERS
Location
Opp Kalina Masjid, Mumbai · 400055
Project type
Residential / Group Housing
Registered on
7 Nov 2020
Completion date at registration
May 2024
Latest completion date
December 2025
Delay so far
19 months
Homes
63
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Sheetala Sheetal Ganga Gobind, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHEETAL GANGA GOBIND0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sheetala Sheetal Ganga Gobind every 1–2 months.

Sheetala Sheetal Ganga Gobind: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHEETAL GANGA GOBIND (11 floors)
  • Land: 866 sq m (about 0.2 acres) · sanctioned built-up 2,792 sq m
  • Land, as filed: 6387
  • Map: Get directions

The builder’s record and reviews

Sheetala Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Sheetala Sheetal Ganga Gobind →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sheetala Sheetal Ganga Gobind: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Sheetala Sheetal Ganga Gobind

What is the possession date of Sheetala Sheetal Ganga Gobind?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sheetala Sheetal Ganga Gobind in Opp Kalina Masjid, Mumbai is 31 December 2025 — 19 months later than 1 May 2024, the date given at registration. That date has already passed.

The date has already moved 19 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Sheetala Sheetal Ganga Gobind?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sheetala Sheetal Ganga Gobind's builder has filed on MahaRERA, the official one, is 31 December 2025, already 19 months later than the 1 May 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sheetala Sheetal Ganga Gobind extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Sheetala Sheetal Ganga Gobind's builder applied to MahaRERA to extend the completion date once: to 31 December 2025, giving the reason "We have in details with explanation why we need extension till 31-12-2025 and how we will complete our project till 31-12-2025".

What is the RERA number of Sheetala Sheetal Ganga Gobind?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sheetala Sheetal Ganga Gobind in Opp Kalina Masjid, Mumbai is P51800026943.

Is Sheetala Sheetal Ganga Gobind registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sheetala Sheetal Ganga Gobind is registered as P51800026943 and its status is "Lapsed (registration period ended)".

What is the current construction status of Sheetala Sheetal Ganga Gobind? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Sheetala Sheetal Ganga Gobind's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHEETAL GANGA GOBIND is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Sheetala Sheetal Ganga Gobind have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Sheetala Sheetal Ganga Gobind safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Sheetala Sheetal Ganga Gobind is registered on MahaRERA as P51800026943, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 19 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Sheetala Sheetal Ganga Gobind?

Sheetala Sheetal Ganga Gobind isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Sheetala Sheetal Ganga Gobind?

For a flat in Sheetala Sheetal Ganga Gobind (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Sheetala Sheetal Ganga Gobind received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sheetala Sheetal Ganga Gobind isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Sheetala Sheetal Ganga Gobind?

According to GharKundli's check of MahaRERA records (updated October 2026), Sheetala Sheetal Ganga Gobind's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Sheetala Sheetal Ganga Gobind uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sheetala Sheetal Ganga Gobind was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Sheetala Sheetal Ganga Gobind's possession date changes?

The latest dates are on Sheetala Sheetal Ganga Gobind's MahaRERA page (P51800026943). GharKundli's Kundli Watch sends a free WhatsApp update on Sheetala Sheetal Ganga Gobind every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sheetala Sheetal Ganga Gobind have?

According to GharKundli's check of MahaRERA records (updated October 2026), Sheetala Sheetal Ganga Gobind has one building filed: SHEETAL GANGA GOBIND with 11 floors.

How big is the land of Sheetala Sheetal Ganga Gobind?

According to GharKundli's check of MahaRERA records (updated October 2026), Sheetala Sheetal Ganga Gobind stands on 866 sq m of land (about 0.2 acres), with 2,792 sq m of sanctioned built-up area.

What is the track record of Sheetala Sheetal Ganga Gobind's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sheetala Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Sheetala Sheetal Ganga Gobind?

Google Maps has reviews of Sheetala Sheetal Ganga Gobind written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Sheetala Sheetal Ganga Gobind?

Sheetala Sheetal Ganga Gobind by SHEETALA DEVELOPERS is in Opp Kalina Masjid, Mumbai, pincode 400055, Maharashtra, and is registered on MahaRERA as P51800026943, per GharKundli's check of MahaRERA records. Its land is filed as 6387. GharKundli lists all 112 MahaRERA projects in Santacruz East (400055).

How many flats are in Sheetala Sheetal Ganga Gobind?

According to GharKundli's check of MahaRERA records (updated October 2026), Sheetala Sheetal Ganga Gobind has 63 homes in 1 tower registered on MahaRERA.

When was Sheetala Sheetal Ganga Gobind registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sheetala Sheetal Ganga Gobind was registered on MahaRERA on 7 November 2020. GharKundli did not find a title report on the land on file there.

Does Sheetala Sheetal Ganga Gobind have any legal issues or court cases?

No court cases are listed for Sheetala Sheetal Ganga Gobind on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Sheetala Sheetal Ganga Gobind?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHEETALA DEVELOPERS.

Other projects in Andheri

All 112 projects in Santacruz East (400055) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.