Shastri Nagar Prerna C.H.S.Ltd.
by Confiable Constructions · Goregaon, Mumbai 400104Also near Kalanagar, Andheri East, Siddharth Nagar
What’s in the report? →Possession date of Shastri Nagar Prerna C.H.S.Ltd. (MahaRERA P51800027919): 30 October 2027, moved from 30 June 2025 (24 months later). It has 125 homes (1 BHK and 2 BHK, 414–771 sq ft carpet), 60% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800027919, and currently active. Its completion date has moved from June 2025 to October 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800027919, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shastri Nagar Prerna C.H.S.Ltd.?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shastri Nagar Prerna C.H.S.Ltd. has moved
30 June 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA16062501611)
Reason the builder gave MahaRERA:
“The project was initially commenced by M/s. Ayyappa Builders and Developers Pvt. Ltd., who had undertaken the demolition work. However, due to failure in providing rent to the tenants for over two years and selling project inventories at un…” Read the full reason
“The project was initially commenced by M/s. Ayyappa Builders and Developers Pvt. Ltd., who had undertaken the demolition work. However, due to failure in providing rent to the tenants for over two years and selling project inventories at undervalued prices, the society approached us to take over and complete the project. After reaching a settlement with the previous developer, Confiable Constructions formally took over the project and assumed all liabilities and responsibilities. Unfortunately, due to the COVID-19 pandemic and the resulting halt in construction activities, as well as challe…”30 June 2027
Extended at the builder's request (MahaRERA application EA19062621433)
Reason the builder gave MahaRERA:
“The project could not be completed within the stipulated period due to the pendency of balance parking-related work and the delay in obtaining the No Objection Certificate (NOC) from the Chief Fire Officer (CFO), which is a mandatory statut…” Read the full reason
“The project could not be completed within the stipulated period due to the pendency of balance parking-related work and the delay in obtaining the No Objection Certificate (NOC) from the Chief Fire Officer (CFO), which is a mandatory statutory approval required for completion and occupancy compliance. These factors have resulted in an unavoidable delay in achieving the final completion of the project. We are actively pursuing the necessary approvals and expediting the completion of the remaining work. We remain committed to completing the project at the earliest and are making all possible…”30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shastri Nagar Prerna C.H.S.Ltd.’s extension records on MahaRERA (P51800027919), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shastri Nagar Prerna C.H.S.Ltd.
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800027919
- Status
- Registered and active
- Builder
- Confiable Constructions
- Location
- Goregaon, Mumbai · 400104
- Project type
- Others
- Registered on
- 15 Jan 2021
- Completion date at registration
- June 2025
- Latest completion date
- October 2027
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 125
- Sold or booked
- 60%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shastri Nagar Prerna C.H.S.Ltd., as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Shastri Nagar Prerna C H S Ltd | 100% | 100% | 100% | 41% |
Commencement certificate (CC), as filed on MahaRERA
- Shastri Nagar Prerna C H S Ltd: covers 23 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shastri Nagar Prerna C.H.S.Ltd. every 1–2 months.
Shastri Nagar Prerna C.H.S.Ltd.: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Other | 529 – 771 | 60 |
| 2 BHK | 568 – 571 | 42 |
| 1 BHK | 414 – 444 | 23 |
| Shops | 72 – 288 | 13 |
- Buildings: Shastri Nagar Prerna C H S Ltd (24 floors, 138 units)
- Car parking: 95 covered
- Land: 1,439 sq m (about 0.4 acres) · sanctioned built-up 3,907 sq m
- Land, as filed: CTS No. 219 pt
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Reliable Constructions (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 23 months); 4 still being built, 2 past the promised date (typically 12 months late); 1 lapsed. 20 complaints on MahaRERA across 2 projects.
Read Google reviews of Shastri Nagar Prerna C.H.S.Ltd. →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shastri Nagar Prerna C.H.S.Ltd.: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shastri Nagar Prerna C.H.S.Ltd.
What is the possession date of Shastri Nagar Prerna C.H.S.Ltd.?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shastri Nagar Prerna C.H.S.Ltd. in Goregaon, Mumbai is 30 October 2027 — 24 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shastri Nagar Prerna C.H.S.Ltd.?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shastri Nagar Prerna C.H.S.Ltd.'s builder has filed on MahaRERA, the official one, is 30 October 2027, already 24 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shastri Nagar Prerna C.H.S.Ltd. extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shastri Nagar Prerna C.H.S.Ltd.'s builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2026, giving the reason "The project was initially commenced by M/s. Ayyappa Builders and Developers Pvt. Ltd., who had undertaken the demolition work. However, due to failure in providing rent to the tenants for over two years and selling project inventories at undervalued prices, the society approached us to take over and complete the project. After reaching a settlement with the previous developer, Confiable Constructions formally took over the project and assumed all liabilities and responsibilities. Unfortunately, due to the COVID-19 pandemic and the resulting halt in construction activities, as well as challe…"; to 30 June 2027, giving the reason "The project could not be completed within the stipulated period due to the pendency of balance parking-related work and the delay in obtaining the No Objection Certificate (NOC) from the Chief Fire Officer (CFO), which is a mandatory statutory approval required for completion and occupancy compliance. These factors have resulted in an unavoidable delay in achieving the final completion of the project. We are actively pursuing the necessary approvals and expediting the completion of the remaining work. We remain committed to completing the project at the earliest and are making all possible…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Shastri Nagar Prerna C.H.S.Ltd.?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shastri Nagar Prerna C.H.S.Ltd. in Goregaon, Mumbai is P51800027919.
Is Shastri Nagar Prerna C.H.S.Ltd. registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shastri Nagar Prerna C.H.S.Ltd. is registered as P51800027919 and its status is "Registered and active".
What is the current construction status of Shastri Nagar Prerna C.H.S.Ltd.? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shastri Nagar Prerna C.H.S.Ltd.'s status on MahaRERA is "Registered and active". As filed by the builder, slab work on Shastri Nagar Prerna C H S Ltd is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Shastri Nagar Prerna C.H.S.Ltd. have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shastri Nagar Prerna C.H.S.Ltd. safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shastri Nagar Prerna C.H.S.Ltd. is registered on MahaRERA as P51800027919, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shastri Nagar Prerna C.H.S.Ltd.?
Shastri Nagar Prerna C.H.S.Ltd. is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Shastri Nagar Prerna C.H.S.Ltd. are 414 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shastri Nagar Prerna C.H.S.Ltd.?
For a flat in Shastri Nagar Prerna C.H.S.Ltd. (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Shastri Nagar Prerna C.H.S.Ltd. received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shastri Nagar Prerna C.H.S.Ltd. is still under construction, with 30 October 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Shastri Nagar Prerna C.H.S.Ltd. a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Shastri Nagar Prerna C.H.S.Ltd. is a redevelopment: 32 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Shastri Nagar Prerna C.H.S.Ltd. uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shastri Nagar Prerna C.H.S.Ltd. was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shastri Nagar Prerna C.H.S.Ltd.'s possession date changes?
The latest dates are on Shastri Nagar Prerna C.H.S.Ltd.'s MahaRERA page (P51800027919). GharKundli's Kundli Watch sends a free WhatsApp update on Shastri Nagar Prerna C.H.S.Ltd. every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shastri Nagar Prerna C.H.S.Ltd. have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shastri Nagar Prerna C.H.S.Ltd. has one building filed: Shastri Nagar Prerna C H S Ltd with 24 floors and 138 units.
What are the flat sizes (carpet area) in Shastri Nagar Prerna C.H.S.Ltd.?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shastri Nagar Prerna C.H.S.Ltd.: Other: 529 to 771 sq ft carpet (60 homes); 2 BHK: 568 to 571 sq ft carpet (42 homes); 1 BHK: 414 to 444 sq ft carpet (23 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Shastri Nagar Prerna C.H.S.Ltd. have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 95 covered car parking spaces for Shastri Nagar Prerna C.H.S.Ltd..
How big is the land of Shastri Nagar Prerna C.H.S.Ltd.?
According to GharKundli's check of MahaRERA records (updated October 2026), Shastri Nagar Prerna C.H.S.Ltd. stands on 1,439 sq m of land (about 0.4 acres), with 3,907 sq m of sanctioned built-up area.
What is the track record of Shastri Nagar Prerna C.H.S.Ltd.'s builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Reliable Constructions (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 23 months); 4 still being built, 2 past the promised date (typically 12 months late); 1 lapsed. 20 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Shastri Nagar Prerna C.H.S.Ltd.?
Google Maps has reviews of Shastri Nagar Prerna C.H.S.Ltd. written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shastri Nagar Prerna C.H.S.Ltd.?
Shastri Nagar Prerna C.H.S.Ltd. by Confiable Constructions is in Goregaon, Mumbai, pincode 400104 (near Kalanagar, Andheri East, Siddharth Nagar), Maharashtra, and is registered on MahaRERA as P51800027919, per GharKundli's check of MahaRERA records. Its land is filed as CTS No. 219 pt. GharKundli lists all 183 MahaRERA projects in Goregaon West (400104).
How many flats are in Shastri Nagar Prerna C.H.S.Ltd., and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Shastri Nagar Prerna C.H.S.Ltd. has 125 homes in 1 tower registered on MahaRERA, and 60% of them are sold or booked.
When was Shastri Nagar Prerna C.H.S.Ltd. registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shastri Nagar Prerna C.H.S.Ltd. was registered on MahaRERA on 15 January 2021. GharKundli did not find a title report on the land on file there.
Does Shastri Nagar Prerna C.H.S.Ltd. have any legal issues or court cases?
No court cases are listed for Shastri Nagar Prerna C.H.S.Ltd. on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shastri Nagar Prerna C.H.S.Ltd.?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Confiable Constructions.
Check it yourself on MahaRERA
- How to check the possession date of Shastri Nagar Prerna C.H.S.Ltd.
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Goregaon West (400104)
- io Residences by PCPL
- io Tower by PCPL
- Ekta Tripolis Phase II
- Apricus
- Paras Residency
- Bali Ananda
- Sunteck Pinnacle 1
- DRM Sheetal Landmark
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.