Sethia Aashray-Phase 1
by AAKASH DEVELOPERS (Sethia) · Kandivali E, Mumbai 400101Also near Malad East
What’s in the report? →Possession date of Sethia Aashray-Phase 1 (MahaRERA P51800027166): 30 October 2027, moved from 30 June 2024 (36 months later). It has 107 homes (1 BHK, 170–321 sq ft carpet), 96% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800027166, and currently active. Its completion date has moved from June 2024 to October 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800027166, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Sethia Aashray-Phase 1?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sethia Aashray-Phase 1 has moved
30 June 2024
Completion date given when the project was registered
29 June 2025
Extended at the builder's request (MahaRERA application EXT51800024512)
Reason the builder gave MahaRERA: “Due to part encroachment on proposed D P Road providing access to the building not yet cleared by BMC ward office”
30 June 2027
Extended at the builder's request (MahaRERA application EA01072501902)
Reason the builder gave MahaRERA:
“Firstly we would like to inform you that we have successfully completed the construction of the building. Our project is Ground floor + 23rd floor, the possession of the flats have been given to all the allottees. As the building is fully c…” Read the full reason
“Firstly we would like to inform you that we have successfully completed the construction of the building. Our project is Ground floor + 23rd floor, the possession of the flats have been given to all the allottees. As the building is fully completed with amenities and occupied, the allottes are enjoying the occupation. Due to part encroachment on proposed D P Road providing access to the building not yet cleared by BMC ward office, the project was not able to get completed in time. Also the mechanical car parking tower work is going on, apart from that everything is completed and they have n…”30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sethia Aashray-Phase 1’s extension records on MahaRERA (P51800027166), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sethia Aashray-Phase 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800027166
- Status
- Registered and active
- Builder
- AAKASH DEVELOPERS
- Location
- Kandivali E, Mumbai · 400101
- Project type
- Others
- Registered on
- 20 Nov 2020
- Completion date at registration
- June 2024
- Latest completion date
- October 2027
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 107
- Sold or booked
- 96%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Sethia Aashray-Phase 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sethia Aashray - Phase 1 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Sethia Aashray - Phase 1: covers c.c is re-endorsed -u per amended plans
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sethia Aashray-Phase 1 every 1–2 months.
Sethia Aashray-Phase 1: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 321 | 98 |
| Other | 170 – 204 | 9 |
| Shops | 66 – 165 | 8 |
- Buildings: Sethia Aashray - Phase 1 (25 floors, 115 units)
- Land: 258 sq m (about 0.1 acres) · sanctioned built-up 3,721 sq m · recreational space 45 sq m
- Land, as filed: 19 A/1 Pt and 25A
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Sethia Infrastructure (a group of 6 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 35 months); 7 still being built, 5 past the promised date (typically 18 months late). 38 complaints on MahaRERA across 4 projects.
Read Google reviews of Sethia Aashray-Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sethia Aashray-Phase 1: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sethia Aashray-Phase 1
What is the possession date of Sethia Aashray-Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sethia Aashray-Phase 1 in Kandivali E, Mumbai is 30 October 2027 — 36 months later than 30 June 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 36 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Sethia Aashray-Phase 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sethia Aashray-Phase 1's builder has filed on MahaRERA, the official one, is 30 October 2027, already 36 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sethia Aashray-Phase 1 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Aashray-Phase 1's builder applied to MahaRERA to extend the completion date 2 times: to 29 June 2025, giving the reason "Due to part encroachment on proposed D P Road providing access to the building not yet cleared by BMC ward office"; to 30 June 2027, giving the reason "Firstly we would like to inform you that we have successfully completed the construction of the building. Our project is Ground floor + 23rd floor, the possession of the flats have been given to all the allottees. As the building is fully completed with amenities and occupied, the allottes are enjoying the occupation. Due to part encroachment on proposed D P Road providing access to the building not yet cleared by BMC ward office, the project was not able to get completed in time. Also the mechanical car parking tower work is going on, apart from that everything is completed and they have n…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sethia Aashray-Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sethia Aashray-Phase 1 in Kandivali E, Mumbai is P51800027166.
Is Sethia Aashray-Phase 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Aashray-Phase 1 is registered as P51800027166 and its status is "Registered and active".
What is the current construction status of Sethia Aashray-Phase 1? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Aashray-Phase 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sethia Aashray - Phase 1 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Sethia Aashray-Phase 1 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sethia Aashray-Phase 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Aashray-Phase 1 is registered on MahaRERA as P51800027166, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sethia Aashray-Phase 1?
Sethia Aashray-Phase 1 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Sethia Aashray-Phase 1 are 170 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sethia Aashray-Phase 1?
For a flat in Sethia Aashray-Phase 1 (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Sethia Aashray-Phase 1 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Aashray-Phase 1 is still under construction, with 30 October 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Sethia Aashray-Phase 1 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sethia Aashray-Phase 1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Sethia Aashray-Phase 1's possession date changes?
The latest dates are on Sethia Aashray-Phase 1's MahaRERA page (P51800027166). GharKundli's Kundli Watch sends a free WhatsApp update on Sethia Aashray-Phase 1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sethia Aashray-Phase 1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Aashray-Phase 1 has one building filed: Sethia Aashray - Phase 1 with 25 floors and 115 units.
What are the flat sizes (carpet area) in Sethia Aashray-Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Sethia Aashray-Phase 1: 1 BHK: 321 sq ft carpet (98 homes); Other: 170 to 204 sq ft carpet (9 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Sethia Aashray-Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Aashray-Phase 1 stands on 258 sq m of land (about 0.1 acres), with 3,721 sq m of sanctioned built-up area and 45 sq m of recreational open space.
What is the track record of Sethia Aashray-Phase 1's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Infrastructure (a group of 6 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 35 months); 7 still being built, 5 past the promised date (typically 18 months late). 38 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Sethia Aashray-Phase 1?
Google Maps has reviews of Sethia Aashray-Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sethia Aashray-Phase 1?
Sethia Aashray-Phase 1 by AAKASH DEVELOPERS (Sethia) is in Kandivali E, Mumbai, pincode 400101 (near Malad East), Maharashtra, and is registered on MahaRERA as P51800027166, per GharKundli's check of MahaRERA records. Its land is filed as 19 A/1 Pt and 25A. GharKundli lists all 113 MahaRERA projects in Kandivali East (400101).
How many flats are in Sethia Aashray-Phase 1, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Aashray-Phase 1 has 107 homes in 1 tower registered on MahaRERA, and 96% of them are sold or booked.
When was Sethia Aashray-Phase 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Aashray-Phase 1 was registered on MahaRERA on 20 November 2020. GharKundli did not find a title report on the land on file there.
Does Sethia Aashray-Phase 1 have any legal issues or court cases?
No court cases are listed for Sethia Aashray-Phase 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Sethia Aashray-Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AAKASH DEVELOPERS, the company Sethia files this project under, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sethia Aashray-Phase 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Kandivali East (400101)
- Avasa
- Aurigae Residency D Wing
- Ajmera Iconic
- 101 Boulevard
- Veda
- Swayambhu Co-op. HSG. Soc. LTD.
- Uk Luxecity - E - F
- Siennaa Wing F
Other projects by AAKASH DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.