NIRLON EMPLOYEES CHS LTD BUILDING NO. 10

by Shivam Parivar Developers Private Limited · Goregaon West, MumbaiAlso near Borivali West, Borivali East, Mandapeshwar

Possession date of NIRLON EMPLOYEES CHS LTD BUILDING NO. 10: 30 April 2027, moved from 30 June 2024 (30 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800029048, and currently active. Its completion date has moved from June 2024 to April 2027: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about NIRLON EMPLOYEES CHS LTD BUILDING NO. 10?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 has moved

  1. 30 June 2024

    Completion date given when the project was registered

  2. 29 June 2025

    Extended at the builder's request (MahaRERA application EXT51800024392)

    Reason the builder gave MahaRERA: “AS per attachment”
  3. 30 December 2026

    Extended at the builder's request (MahaRERA application EA09102518072)

    Reason the builder gave MahaRERA:
    “We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstan…” Read the full reason“We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the Industry Slow Down – As everybody is aware, Real Estate Industry is facing severe slowdown all across the country and we are no exceptions. It has affected our sales and further our liquidity. Lack of liquidity is affecting project progress which ultimately affecting Sales of the project.Uncertain operational challenges like heavy rains during ra…”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: NIRLON EMPLOYEES CHS LTD BUILDING NO. 10’s extension records on MahaRERA (P51800029048), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NIRLON EMPLOYEES CHS LTD BUILDING NO. 10

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800029048
Status
Registered and active
Builder
Shivam Parivar Developers Private Limited
Location
Goregaon West, Mumbai · 400062
Project type
Residential / Group Housing
Registered on
23 Apr 2021
Completion date at registration
June 2024
Latest completion date
April 2027
Delay so far
30 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
109
Sold or booked
90%
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found

Construction progress of NIRLON EMPLOYEES CHS LTD BUILDING NO. 10, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Nirlon Employees CHS LTD Building No 10100%72%70%2%

Commencement certificate (CC), as filed on MahaRERA

  • Nirlon Employees CHS LTD Building No 10: covers 24 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 every month.

NIRLON EMPLOYEES CHS LTD BUILDING NO. 10: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK536 – 647100
Shops61 – 23411
1 BHK3906
Office Space316 – 1,6433
1 Room Kitchen323 – 3333
  • Buildings: Nirlon Employees CHS LTD Building No 10 (24 floors, 123 units)
  • Land: 820 sq m (about 0.2 acres) · sanctioned built-up 2,645 sq m · recreational space 393 sq m
  • Boundaries filed include: 27m wide Sami Vivekanand Road

The builder’s record and reviews

Shivam Parivar Developers has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 5 months); 3 still being built, 2 past the promised date (typically 14 months late); 2 lapsed. 37 complaints on MahaRERA across 6 projects.

Read Google reviews of NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NIRLON EMPLOYEES CHS LTD BUILDING NO. 10: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NIRLON EMPLOYEES CHS LTD BUILDING NO. 10

What is the possession date of NIRLON EMPLOYEES CHS LTD BUILDING NO. 10?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 in Goregaon West, Mumbai is 30 April 2027 — 30 months later than 30 June 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for NIRLON EMPLOYEES CHS LTD BUILDING NO. 10?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NIRLON EMPLOYEES CHS LTD BUILDING NO. 10's builder has filed on MahaRERA, the official one, is 30 April 2027, already 30 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRLON EMPLOYEES CHS LTD BUILDING NO. 10's builder applied to MahaRERA to extend the completion date 2 times: to 29 June 2025, giving the reason "AS per attachment"; to 30 December 2026, giving the reason "We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the Industry Slow Down – As everybody is aware, Real Estate Industry is facing severe slowdown all across the country and we are no exceptions. It has affected our sales and further our liquidity. Lack of liquidity is affecting project progress which ultimately affecting Sales of the project.Uncertain operational challenges like heavy rains during ra…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of NIRLON EMPLOYEES CHS LTD BUILDING NO. 10?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 in Goregaon West, Mumbai is P51800029048.

Is NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 is registered as P51800029048 and its status is "Registered and active".

What is the construction status of NIRLON EMPLOYEES CHS LTD BUILDING NO. 10?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRLON EMPLOYEES CHS LTD BUILDING NO. 10's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Nirlon Employees CHS LTD Building No 10 is 72% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.

Does NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 is registered on MahaRERA as P51800029048, its completion date has moved 30 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NIRLON EMPLOYEES CHS LTD BUILDING NO. 10's possession date changes?

The latest dates are on NIRLON EMPLOYEES CHS LTD BUILDING NO. 10's MahaRERA page (P51800029048). GharKundli's Kundli Watch sends a free WhatsApp update on NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 have?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 has one building filed: Nirlon Employees CHS LTD Building No 10 with 24 floors and 123 units.

What are the flat sizes (carpet area) in NIRLON EMPLOYEES CHS LTD BUILDING NO. 10?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for NIRLON EMPLOYEES CHS LTD BUILDING NO. 10: 2 BHK: 536 to 647 sq ft carpet (100 homes); 1 BHK: 390 sq ft carpet (6 homes); 1 Room Kitchen: 323 to 333 sq ft carpet (3 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of NIRLON EMPLOYEES CHS LTD BUILDING NO. 10?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 stands on 820 sq m of land (about 0.2 acres), with 2,645 sq m of sanctioned built-up area and 393 sq m of recreational open space.

What is the track record of NIRLON EMPLOYEES CHS LTD BUILDING NO. 10's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivam Parivar Developers has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 5 months); 3 still being built, 2 past the promised date (typically 14 months late); 2 lapsed. 37 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of NIRLON EMPLOYEES CHS LTD BUILDING NO. 10?

Google Maps has reviews of NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NIRLON EMPLOYEES CHS LTD BUILDING NO. 10?

NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 by Shivam Parivar Developers Private Limited is in Goregaon West, Mumbai (pincode 400062), near Borivali West, Borivali East, Mandapeshwar, Maharashtra, and is registered on MahaRERA as P51800029048, per GharKundli's check of MahaRERA records. Its boundaries filed there include 27m wide Sami Vivekanand Road.

How many homes are in NIRLON EMPLOYEES CHS LTD BUILDING NO. 10?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 has 109 homes in 1 tower registered on MahaRERA, and 90% of them are sold or booked.

When was NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 was registered on MahaRERA on 23 April 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on NIRLON EMPLOYEES CHS LTD BUILDING NO. 10?

No court cases are listed for NIRLON EMPLOYEES CHS LTD BUILDING NO. 10 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of NIRLON EMPLOYEES CHS LTD BUILDING NO. 10?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shivam Parivar Developers Private Limited.