Possession date of Konark Bella Casa (MahaRERA P51800030388): 30 April 2027, moved from 31 December 2023 (36 months later). It has 35 homes (2 BHK, 3 BHK and Multi Purpose Room, 215–1356 sq ft carpet), 42% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800030388, and currently active. Its completion date has moved from December 2023 to April 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800030388, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Konark Bella Casa?

3 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Konark Bella Casa has moved

  1. 31 December 2023

    Completion date given when the project was registered

  2. 30 December 2024

    Extended at the builder's request (MahaRERA application EXT51800017929)

    Reason the builder gave MahaRERA: “DUE TO COVID 19 NOT ABLE TO COMPELTE PROJECT PLEASE GRANT US EXTENSION FOR 12 MONTHS”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800024978)

    Reason the builder gave MahaRERA: “Due to shortage of material and labor we are not able to complete project please grant us extension till 31/12/2025”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EA10032620156)

    Reason the builder gave MahaRERA:
    “Sub: Extension to the project bearing Registration No. P51800030388. Dear Sir/Madam, 1. We have completed till date work to the extent of 93%. Ground plus Two commercial portion is ready for occupation. Pit Puzzle Parking System is 100% com…” Read the full reason“Sub: Extension to the project bearing Registration No. P51800030388. Dear Sir/Madam, 1. We have completed till date work to the extent of 93%. Ground plus Two commercial portion is ready for occupation. Pit Puzzle Parking System is 100% completed. Fire Fighting system is fully completed for commercial portion. 2. Due to slow progress in work, our sales got affected resulting in financial crunch. 3. We want extension for further 12 months to complete the project For Konark Bella Casa LLP For KONARK BELLA CASA LLP SRekar hingall Authorised Partner”
  5. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Konark Bella Casa’s extension records on MahaRERA (P51800030388), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Konark Bella Casa

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 court cases, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800030388
Status
Registered and active
Builder
Konark Bella Casa LLP
Location
Opp Andheri Sports Complex, Mumbai · 400058
Project type
Others
Registered on
17 Aug 2021
Completion date at registration
December 2023
Latest completion date
April 2027
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
35
Sold or booked
42%
Towers
1
Complaints on MahaRERA
0
Court cases listed
3
Title report on file
Not found

Construction progress of Konark Bella Casa, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BELLA CASA100%85%80%60%

Commencement certificate (CC), as filed on MahaRERA

  • BELLA CASA: covers C.C. up to top of 9th floor

Latest CC order on MahaRERA: dated 02/03/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Konark Bella Casa every 1–2 months.

Konark Bella Casa: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK571 – 72125
3 BHK777 – 1,3568
Other635 – 3,1814
Office Space840 – 9643
Multi Purpose Room215 – 2252
  • Buildings: BELLA CASA (10 floors, 42 units)
  • Car parking: 36 covered
  • Land: 1,011 sq m (about 0.2 acres) · sanctioned built-up 3,197 sq m
  • Boundaries filed include: JAY PRAKASH ROAD, PLAYGROUND OF BHAVANS COLLEGE
  • Land, as filed: 188, 188/1 TO 188/4
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Konark Bella Casa →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Konark Bella Casa: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Konark Bella Casa

What is the possession date of Konark Bella Casa?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Konark Bella Casa in Opp Andheri Sports Complex, Mumbai is 30 April 2027 — 36 months later than 31 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 36 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Konark Bella Casa?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Konark Bella Casa's builder has filed on MahaRERA, the official one, is 30 April 2027, already 36 months later than the 31 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Konark Bella Casa extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Konark Bella Casa's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2024, giving the reason "DUE TO COVID 19 NOT ABLE TO COMPELTE PROJECT PLEASE GRANT US EXTENSION FOR 12 MONTHS"; to 31 December 2025, giving the reason "Due to shortage of material and labor we are not able to complete project please grant us extension till 31/12/2025"; to 31 December 2026, giving the reason "Sub: Extension to the project bearing Registration No. P51800030388. Dear Sir/Madam, 1. We have completed till date work to the extent of 93%. Ground plus Two commercial portion is ready for occupation. Pit Puzzle Parking System is 100% completed. Fire Fighting system is fully completed for commercial portion. 2. Due to slow progress in work, our sales got affected resulting in financial crunch. 3. We want extension for further 12 months to complete the project For Konark Bella Casa LLP For KONARK BELLA CASA LLP SRekar hingall Authorised Partner". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Konark Bella Casa?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Konark Bella Casa in Opp Andheri Sports Complex, Mumbai is P51800030388.

Is Konark Bella Casa registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Konark Bella Casa is registered as P51800030388 and its status is "Registered and active".

What is the current construction status of Konark Bella Casa? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Konark Bella Casa's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BELLA CASA is 85% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does Konark Bella Casa have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Konark Bella Casa safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Konark Bella Casa is registered on MahaRERA as P51800030388, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Konark Bella Casa?

Konark Bella Casa is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Konark Bella Casa are 215 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Konark Bella Casa?

For a flat in Konark Bella Casa (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Konark Bella Casa received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Konark Bella Casa is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Konark Bella Casa a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Konark Bella Casa is a redevelopment: 21 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Konark Bella Casa uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Konark Bella Casa was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Konark Bella Casa's possession date changes?

The latest dates are on Konark Bella Casa's MahaRERA page (P51800030388). GharKundli's Kundli Watch sends a free WhatsApp update on Konark Bella Casa every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Konark Bella Casa have?

According to GharKundli's check of MahaRERA records (updated October 2026), Konark Bella Casa has one building filed: BELLA CASA with 10 floors and 42 units.

What are the flat sizes (carpet area) in Konark Bella Casa?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Konark Bella Casa: 2 BHK: 571 to 721 sq ft carpet (25 homes); 3 BHK: 777 to 1356 sq ft carpet (8 homes); Multi Purpose Room: 215 to 225 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Konark Bella Casa have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 36 covered car parking spaces for Konark Bella Casa.

How big is the land of Konark Bella Casa?

According to GharKundli's check of MahaRERA records (updated October 2026), Konark Bella Casa stands on 1,011 sq m of land (about 0.2 acres), with 3,197 sq m of sanctioned built-up area.

What are the reviews of Konark Bella Casa?

Google Maps has reviews of Konark Bella Casa written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Konark Bella Casa?

Konark Bella Casa by Konark Bella Casa LLP is in Opp Andheri Sports Complex, Mumbai, pincode 400058 (near Andheri West, Ambivali West, Bandra West), Maharashtra, and is registered on MahaRERA as P51800030388, per GharKundli's check of MahaRERA records. Its boundaries filed there include JAY PRAKASH ROAD, PLAYGROUND OF BHAVANS COLLEGE. Its land is filed as 188, 188/1 TO 188/4. GharKundli lists all 148 MahaRERA projects in Andheri West (400058).

How many flats are in Konark Bella Casa, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Konark Bella Casa has 35 homes in 1 tower registered on MahaRERA, and 42% of them are sold or booked.

When was Konark Bella Casa registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Konark Bella Casa was registered on MahaRERA on 17 August 2021. GharKundli did not find a title report on the land on file there.

Does Konark Bella Casa have any legal issues or court cases?

3 court cases are listed for Konark Bella Casa on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Konark Bella Casa?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Konark Bella Casa LLP.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Andheri

All 148 projects in Andheri West (400058) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.