Sainath Prathamesh Elite
by SHREE SAINATH DEVELOPERS · Laljipada, Mumbai 400067Also near Kandivali West, Malad West, OrlemRegistered on MahaRERA as “PRATHAMESH ELITE”
What’s in the report? →Possession date of Sainath Prathamesh Elite (MahaRERA P51800029737): 30 April 2028, moved from 31 December 2026 (12 months later). It has 108 homes (1 BHK, 2 BHK and 3 BHK, 464–2873 sq ft carpet), 71% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800029737, and currently active. Its completion date has moved from December 2026 to April 2028: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800029737, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Sainath Prathamesh Elite?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sainath Prathamesh Elite has moved
31 December 2026
Completion date given when the project was registered
30 December 2027
Extended at the builder's request (MahaRERA application EXT51800019853)
Reason the builder gave MahaRERA: “Due to shortage of material and labor not able to complete project please grant extension till 30/12/2027”
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sainath Prathamesh Elite’s extension records on MahaRERA (P51800029737), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sainath Prathamesh Elite
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800029737
- Status
- Registered and active
- Builder
- SHREE SAINATH DEVELOPERS
- Location
- Laljipada, Mumbai · 400067
- Project type
- Residential / Group Housing
- Registered on
- 26 Jun 2021
- Completion date at registration
- December 2026
- Latest completion date
- April 2028
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 108
- Sold or booked
- 71%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Sainath Prathamesh Elite, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PRATHAMESH ELITE | 100% | 75% | 10% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- PRATHAMESH ELITE: covers PLINTH LEVEL
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sainath Prathamesh Elite every 1–2 months.
Sainath Prathamesh Elite: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 669 – 777 | 43 |
| 1 BHK | 464 – 1,491 | 40 |
| 3 BHK | 823 – 953 | 21 |
| Shops | 1,163 – 2,873 | 4 |
- Buildings: PRATHAMESH ELITE (26 floors, 108 units)
- Car parking: 80 covered
- Land: 4,445 sq m (about 1.1 acres) · sanctioned built-up 7,595 sq m · recreational space 336 sq m
- Land, as filed: 858
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Sailee Developers (a group of 3 linked companies) has 6 projects on MahaRERA since 2018, this one included. Of the 6 GharKundli has checked: 6 still being built, 1 past the promised date (typically 12 months late). 22 complaints on MahaRERA across 2 projects.
Read Google reviews of Sainath Prathamesh Elite →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sainath Prathamesh Elite: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sainath Prathamesh Elite
What is the possession date of Sainath Prathamesh Elite?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sainath Prathamesh Elite in Laljipada, Mumbai is 30 April 2028 — 12 months later than 31 December 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Sainath Prathamesh Elite?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sainath Prathamesh Elite's builder has filed on MahaRERA, the official one, is 30 April 2028, already 12 months later than the 31 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sainath Prathamesh Elite extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sainath Prathamesh Elite's builder applied to MahaRERA to extend the completion date once: to 30 December 2027, giving the reason "Due to shortage of material and labor not able to complete project please grant extension till 30/12/2027". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sainath Prathamesh Elite?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sainath Prathamesh Elite in Laljipada, Mumbai is P51800029737.
Is Sainath Prathamesh Elite registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sainath Prathamesh Elite is registered as P51800029737 and its status is "Registered and active".
What is the current construction status of Sainath Prathamesh Elite? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Sainath Prathamesh Elite's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PRATHAMESH ELITE is 75% done and internal work 10%. GharKundli's full report compares construction progress with the deadline.
Does Sainath Prathamesh Elite have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sainath Prathamesh Elite safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sainath Prathamesh Elite is registered on MahaRERA as P51800029737, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sainath Prathamesh Elite?
Sainath Prathamesh Elite is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Sainath Prathamesh Elite are 464 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sainath Prathamesh Elite?
For a flat in Sainath Prathamesh Elite (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Sainath Prathamesh Elite received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sainath Prathamesh Elite is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Sainath Prathamesh Elite uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sainath Prathamesh Elite was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Sainath Prathamesh Elite's possession date changes?
The latest dates are on Sainath Prathamesh Elite's MahaRERA page (P51800029737). GharKundli's Kundli Watch sends a free WhatsApp update on Sainath Prathamesh Elite every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sainath Prathamesh Elite have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sainath Prathamesh Elite has one building filed: PRATHAMESH ELITE with 26 floors and 108 units.
What are the flat sizes (carpet area) in Sainath Prathamesh Elite?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Sainath Prathamesh Elite: 2 BHK: 669 to 777 sq ft carpet (43 homes); 1 BHK: 464 to 1491 sq ft carpet (40 homes); 3 BHK: 823 to 953 sq ft carpet (21 homes); Shops: 1163 to 2873 sq ft carpet (4 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Sainath Prathamesh Elite have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 80 covered car parking spaces for Sainath Prathamesh Elite.
How big is the land of Sainath Prathamesh Elite?
According to GharKundli's check of MahaRERA records (updated October 2026), Sainath Prathamesh Elite stands on 4,445 sq m of land (about 1.1 acres), with 7,595 sq m of sanctioned built-up area and 336 sq m of recreational open space.
What is the track record of Sainath Prathamesh Elite's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sailee Developers (a group of 3 linked companies) has 6 projects on MahaRERA since 2018, this one included. Of the 6 GharKundli has checked: 6 still being built, 1 past the promised date (typically 12 months late). 22 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Sainath Prathamesh Elite?
Google Maps has reviews of Sainath Prathamesh Elite written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sainath Prathamesh Elite?
Sainath Prathamesh Elite by SHREE SAINATH DEVELOPERS is in Laljipada, Mumbai, pincode 400067 (near Kandivali West, Malad West, Orlem), Maharashtra, and is registered on MahaRERA as P51800029737, per GharKundli's check of MahaRERA records. Its land is filed as 858. GharKundli lists all 318 MahaRERA projects in Kandivali West (400067).
How many flats are in Sainath Prathamesh Elite, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Sainath Prathamesh Elite has 108 homes in 1 tower registered on MahaRERA, and 71% of them are sold or booked.
When was Sainath Prathamesh Elite registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sainath Prathamesh Elite was registered on MahaRERA on 26 June 2021. GharKundli did not find a title report on the land on file there.
Does Sainath Prathamesh Elite have any legal issues or court cases?
No court cases are listed for Sainath Prathamesh Elite on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Sainath Prathamesh Elite?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE SAINATH DEVELOPERS, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sainath Prathamesh Elite
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Borivali
- Saffronwoods CHSL
- L&T Realty Ahana Tower A
- Avirahi Elegance
- L&T Realty Ahana Tower B
- Parshuram Heights
- Maru Mansion
- LA SERENA Tower 5, Tower 6 and Tower 7
- Shraddha Skyline
Other projects by SHREE SAINATH DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.