93 PALLADIAN
by Vijayalaxmi Builders & Contractors · Andheri East, Mumbai
Possession date of 93 PALLADIAN: 30 October 2028, moved from 30 June 2024 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800030498, and currently active. Its completion date has moved from June 2024 to October 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about 93 PALLADIAN?
How the possession date of 93 PALLADIAN has moved
30 June 2024
Completion date given when the project was registered
30 June 2025
Extended at the builder's request (MahaRERA application EXT51800019574)
Reason the builder gave MahaRERA: “the landslide issue due to which Stop Work was issued by SRA in the project on 25-07-2023. We have recently received the withdrawal of the Stop Work from SRA dated 19-03-2024 so we want to apply for Extention of completion date.”
30 June 2028
Extended at the builder's request (MahaRERA application EA24042620725)
Reason the builder gave MahaRERA:
“Self-Declaration for Extension of Completion Date of the Project "93 PALLADIAN" We, M/s. Vijayalaxmi Builders & Contractors, are constructing a commercial project called "93 PALLADIAN". We have registered the project under MahaRERA vide RER…” Read the full reason
“Self-Declaration for Extension of Completion Date of the Project "93 PALLADIAN" We, M/s. Vijayalaxmi Builders & Contractors, are constructing a commercial project called "93 PALLADIAN". We have registered the project under MahaRERA vide RERA registration no. P51800030498. The completion date of the project is 30/06/2025. I As per the original project timeline, the construction was expected to be completed by 30/06/2025. However, despite our best efforts, the completion has been delayed due to several unforeseen factors that impacted the construction process and delays in obtaining certain r…”30 October 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: 93 PALLADIAN’s extension records on MahaRERA (P51800030498), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on 93 PALLADIAN
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the October 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800030498
- Status
- Registered and active
- Builder
- Vijayalaxmi Builders & Contractors
- Location
- Andheri East, Mumbai · 400093
- Project type
- Commercial
- Registered on
- 25 Aug 2021
- Completion date at registration
- June 2024
- Latest completion date
- October 2028
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 94%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of 93 PALLADIAN, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| 93 PALLADIAN | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- 93 PALLADIAN: covers 10 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on 93 PALLADIAN every month.
93 PALLADIAN: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 225 – 707 | 113 |
| Shops | 111 – 458 | 6 |
- Buildings: 93 PALLADIAN (10 floors, 119 units)
- Car parking: 70 covered, 4 open
- Land: 3,821 sq m (about 0.9 acres) · sanctioned built-up 4,388 sq m
- Boundaries filed include: HOLY SPIRIT HIGH SCHOOL, MAHAKALI CAVES ROAD, GURUNANAK SCHOOL
The builder’s record and reviews
LEO Infrastructure (a group of 2 linked companies) has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 15 months late). No complaints on MahaRERA.
Read Google reviews of 93 PALLADIAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
93 PALLADIAN: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about 93 PALLADIAN
What is the possession date of 93 PALLADIAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for 93 PALLADIAN in Andheri East, Mumbai is 30 October 2028 — 48 months later than 30 June 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for 93 PALLADIAN?
Builders and listing sites often quote an earlier "target" date for handover. The completion date 93 PALLADIAN's builder has filed on MahaRERA, the official one, is 30 October 2028, already 48 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of 93 PALLADIAN extended?
According to GharKundli's check of MahaRERA records (updated October 2026), 93 PALLADIAN's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2025, giving the reason "the landslide issue due to which Stop Work was issued by SRA in the project on 25-07-2023. We have recently received the withdrawal of the Stop Work from SRA dated 19-03-2024 so we want to apply for Extention of completion date."; to 30 June 2028, giving the reason "Self-Declaration for Extension of Completion Date of the Project "93 PALLADIAN" We, M/s. Vijayalaxmi Builders & Contractors, are constructing a commercial project called "93 PALLADIAN". We have registered the project under MahaRERA vide RERA registration no. P51800030498. The completion date of the project is 30/06/2025. I As per the original project timeline, the construction was expected to be completed by 30/06/2025. However, despite our best efforts, the completion has been delayed due to several unforeseen factors that impacted the construction process and delays in obtaining certain r…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of 93 PALLADIAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of 93 PALLADIAN in Andheri East, Mumbai is P51800030498.
Is 93 PALLADIAN registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), 93 PALLADIAN is registered as P51800030498 and its status is "Registered and active".
What is the construction status of 93 PALLADIAN?
According to GharKundli's check of MahaRERA records (updated October 2026), 93 PALLADIAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work on 93 PALLADIAN is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does 93 PALLADIAN have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is 93 PALLADIAN safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), 93 PALLADIAN is registered on MahaRERA as P51800030498, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if 93 PALLADIAN's possession date changes?
The latest dates are on 93 PALLADIAN's MahaRERA page (P51800030498). GharKundli's Kundli Watch sends a free WhatsApp update on 93 PALLADIAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does 93 PALLADIAN have?
According to GharKundli's check of MahaRERA records (updated October 2026), 93 PALLADIAN has one building filed: 93 PALLADIAN with 10 floors and 119 units.
How much parking does 93 PALLADIAN have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 70 covered and 4 open car parking spaces for 93 PALLADIAN.
How big is the land of 93 PALLADIAN?
According to GharKundli's check of MahaRERA records (updated October 2026), 93 PALLADIAN stands on 3,821 sq m of land (about 0.9 acres), with 4,388 sq m of sanctioned built-up area.
What is the track record of 93 PALLADIAN's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), LEO Infrastructure (a group of 2 linked companies) has 2 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 15 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of 93 PALLADIAN?
Google Maps has reviews of 93 PALLADIAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is 93 PALLADIAN?
93 PALLADIAN by Vijayalaxmi Builders & Contractors is in Andheri East, Mumbai (pincode 400093), Maharashtra, and is registered on MahaRERA as P51800030498, per GharKundli's check of MahaRERA records. Its boundaries filed there include HOLY SPIRIT HIGH SCHOOL, MAHAKALI CAVES ROAD, GURUNANAK SCHOOL.
How many homes are in 93 PALLADIAN?
According to GharKundli's check of MahaRERA records (updated October 2026), 93 PALLADIAN has 0 homes in 1 tower registered on MahaRERA, and 94% of them are sold or booked.
When was 93 PALLADIAN registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), 93 PALLADIAN was registered on MahaRERA on 25 August 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on 93 PALLADIAN?
1 court case is listed for 93 PALLADIAN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of 93 PALLADIAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Vijayalaxmi Builders & Contractors.
Check it yourself on MahaRERA
- How to check the possession date of 93 PALLADIAN
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Andheri East
- SHIVSAI SRA CHS
- CRESCENT WESTERN TRADE CENTER - T2
- 140 SHER - E- PUNJAB
- saroj sadan CHSL
- AMEY APARTMENTS
- DIVYA DARPAN CO- OP HSG SOCIETY LTD
- INSPIRE RESIDENCY
- ASHTAVINAYAK APARTMENTS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.