Shree Balaji 7
by Saptrishi Landmarks LLP · Vikhroli East, MumbaiAlso near Powai, Marol, Ballard Estate
Possession date of Shree Balaji 7: 30 September 2027, moved from 30 September 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800032058, and currently active. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Shree Balaji 7?
How the possession date of Shree Balaji 7 has moved
30 September 2026
Completion date given when the project was registered
30 September 2027
Extended at the builder's request (MahaRERA application EA12072621729)
Reason the builder gave MahaRERA:
“The main reason for the delay is pace of sales being lower than expected and thereby affecting the cash flows of the project. Lower than expected cash flows has in turn affected the pace of construction of the project thereby making it impo…” Read the full reason
“The main reason for the delay is pace of sales being lower than expected and thereby affecting the cash flows of the project. Lower than expected cash flows has in turn affected the pace of construction of the project thereby making it impossible to meet the scheduled due date 30/09/2026.We started construction work in full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed.Out of the total 118 flats availab…”
Source: Shree Balaji 7’s extension records on MahaRERA (P51800032058), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shree Balaji 7
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints, and how it ended
- Construction pace against the September 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800032058
- Status
- Registered and active
- Builder
- Saptrishi Landmarks LLP
- Location
- Vikhroli East, Mumbai · 400083
- Project type
- Residential / Group Housing
- Registered on
- 3 Dec 2021
- Completion date at registration
- September 2026
- Latest completion date
- September 2027
- Delay so far
- 12 months
- Homes
- 146
- Sold or booked
- 73%
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shree Balaji 7, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Shree Balaji 7 | 100% | 82% | 50% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Shree Balaji 7: covers 24 floors
Latest CC order on MahaRERA: dated 25/02/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shree Balaji 7 every month.
Shree Balaji 7: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 494 – 599 | 86 |
| 1 BHK | 341 – 415 | 56 |
| Other | 598 | 4 |
- Buildings: Shree Balaji 7 (24 floors, 146 units)
- Car parking: 52 covered
- Land: 803 sq m (about 0.2 acres) · sanctioned built-up 7,725 sq m · recreational space 128 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shree Balaji 7 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shree Balaji 7: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Shree Balaji 7
What is the possession date of Shree Balaji 7?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shree Balaji 7 in Vikhroli East, Mumbai is 30 September 2027 — 12 months later than 30 September 2026, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Shree Balaji 7?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shree Balaji 7's builder has filed on MahaRERA, the official one, is 30 September 2027, already 12 months later than the 30 September 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shree Balaji 7 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Balaji 7's builder applied to MahaRERA to extend the completion date once: to 30 September 2027, giving the reason "The main reason for the delay is pace of sales being lower than expected and thereby affecting the cash flows of the project. Lower than expected cash flows has in turn affected the pace of construction of the project thereby making it impossible to meet the scheduled due date 30/09/2026.We started construction work in full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed.Out of the total 118 flats availab…".
What is the RERA number of Shree Balaji 7?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shree Balaji 7 in Vikhroli East, Mumbai is P51800032058.
Is Shree Balaji 7 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Balaji 7 is registered as P51800032058 and its status is "Registered and active".
What is the construction status of Shree Balaji 7?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Balaji 7's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Shree Balaji 7 is 82% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does Shree Balaji 7 have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Shree Balaji 7 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Balaji 7 is registered on MahaRERA as P51800032058, its completion date has moved 12 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Shree Balaji 7's possession date changes?
The latest dates are on Shree Balaji 7's MahaRERA page (P51800032058). GharKundli's Kundli Watch sends a free WhatsApp update on Shree Balaji 7 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shree Balaji 7 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Balaji 7 has one building filed: Shree Balaji 7 with 24 floors and 146 units.
What are the flat sizes (carpet area) in Shree Balaji 7?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shree Balaji 7: 2 BHK: 494 to 599 sq ft carpet (86 homes); 1 BHK: 341 to 415 sq ft carpet (56 homes); Other: 598 sq ft carpet (4 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Shree Balaji 7 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 52 covered car parking spaces for Shree Balaji 7.
How big is the land of Shree Balaji 7?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Balaji 7 stands on 803 sq m of land (about 0.2 acres), with 7,725 sq m of sanctioned built-up area and 128 sq m of recreational open space.
Where can I read reviews of Shree Balaji 7?
Google Maps has reviews of Shree Balaji 7 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Shree Balaji 7?
Shree Balaji 7 by Saptrishi Landmarks LLP is in Vikhroli East, Mumbai (pincode 400083), near Powai, Marol, Ballard Estate, Maharashtra, and is registered on MahaRERA as P51800032058, per GharKundli's check of MahaRERA records.
How many homes are in Shree Balaji 7?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Balaji 7 has 146 homes in 1 tower registered on MahaRERA, and 73% of them are sold or booked.
When was Shree Balaji 7 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Balaji 7 was registered on MahaRERA on 3 December 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Shree Balaji 7?
No court cases are listed for Shree Balaji 7 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Shree Balaji 7?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Saptrishi Landmarks LLP.
Check it yourself on MahaRERA
- How to check the possession date of Shree Balaji 7
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Vikhroli East
- Element 7 8
- Shubh Elanza
- Kannamwar Nagar Panchsheel CHSL
- RUDRA VISHWAROOP RESIDENCY
- Truearth VEDAA
- Pragati Pinnacle
- Godrej Ivara
- Unique Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.