NIRVAANA PEARL

by Nirvaana Lifespace LLP · Chembur, Mumbai

Possession date of NIRVAANA PEARL: 30 October 2026, moved from 30 June 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800032083, and currently active. Its completion date has moved from June 2025 to October 2026: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about NIRVAANA PEARL?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NIRVAANA PEARL has moved

  1. 30 June 2025

    Completion date given when the project was registered

  2. 30 June 2026

    Extended at the builder's request (MahaRERA application EA31072502263)

    Reason the builder gave MahaRERA: “DUE TO COVID AND DELAY IN APPROVALS”
  3. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: NIRVAANA PEARL’s extension records on MahaRERA (P51800032083), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NIRVAANA PEARL

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800032083
Status
Registered and active
Builder
Nirvaana Lifespace LLP
Location
Chembur, Mumbai · 400007
Project type
Others
Registered on
6 Dec 2021
Completion date at registration
June 2025
Latest completion date
October 2026
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
95
Sold or booked
60%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of NIRVAANA PEARL, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NIRVAANA PEARL85%87.5%25%0%

Commencement certificate (CC), as filed on MahaRERA

  • NIRVAANA PEARL: covers 13 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NIRVAANA PEARL every month.

NIRVAANA PEARL: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK586 – 92953
1 BHK366 – 42328
3 BHK82114
Shops95 – 74812
  • Buildings: NIRVAANA PEARL (16 floors, 107 units)
  • Land: 937 sq m (about 0.2 acres) · sanctioned built-up 4,920 sq m

The builder’s record and reviews

Nirvaana Lifespace (a group of 4 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 7 still being built, 5 past the promised date (typically 12 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of NIRVAANA PEARL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NIRVAANA PEARL: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NIRVAANA PEARL

What is the possession date of NIRVAANA PEARL?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NIRVAANA PEARL in Chembur, Mumbai is 30 October 2026 — 12 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for NIRVAANA PEARL?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NIRVAANA PEARL's builder has filed on MahaRERA, the official one, is 30 October 2026, already 12 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NIRVAANA PEARL extended?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRVAANA PEARL's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "DUE TO COVID AND DELAY IN APPROVALS". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of NIRVAANA PEARL?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NIRVAANA PEARL in Chembur, Mumbai is P51800032083.

Is NIRVAANA PEARL registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRVAANA PEARL is registered as P51800032083 and its status is "Registered and active".

What is the construction status of NIRVAANA PEARL?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRVAANA PEARL's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NIRVAANA PEARL is 87.5% done and internal work 25%. GharKundli's full report compares construction progress with the deadline.

Does NIRVAANA PEARL have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is NIRVAANA PEARL safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRVAANA PEARL is registered on MahaRERA as P51800032083, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NIRVAANA PEARL's possession date changes?

The latest dates are on NIRVAANA PEARL's MahaRERA page (P51800032083). GharKundli's Kundli Watch sends a free WhatsApp update on NIRVAANA PEARL every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NIRVAANA PEARL have?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRVAANA PEARL has one building filed: NIRVAANA PEARL with 16 floors and 107 units.

What are the flat sizes (carpet area) in NIRVAANA PEARL?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for NIRVAANA PEARL: 2 BHK: 586 to 929 sq ft carpet (53 homes); 1 BHK: 366 to 423 sq ft carpet (28 homes); 3 BHK: 821 sq ft carpet (14 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of NIRVAANA PEARL?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRVAANA PEARL stands on 937 sq m of land (about 0.2 acres), with 4,920 sq m of sanctioned built-up area.

What is the track record of NIRVAANA PEARL's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirvaana Lifespace (a group of 4 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 7 still being built, 5 past the promised date (typically 12 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of NIRVAANA PEARL?

Google Maps has reviews of NIRVAANA PEARL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NIRVAANA PEARL?

NIRVAANA PEARL by Nirvaana Lifespace LLP is in Chembur, Mumbai (pincode 400007), Maharashtra, and is registered on MahaRERA as P51800032083, per GharKundli's check of MahaRERA records.

How many homes are in NIRVAANA PEARL?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRVAANA PEARL has 95 homes in 1 tower registered on MahaRERA, and 60% of them are sold or booked.

When was NIRVAANA PEARL registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NIRVAANA PEARL was registered on MahaRERA on 6 December 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on NIRVAANA PEARL?

No court cases are listed for NIRVAANA PEARL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of NIRVAANA PEARL?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Nirvaana Lifespace LLP, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2026 in Mumbai City →

Other projects in Chembur

All 40 projects in Grant Road (400007) →

Other projects by Nirvaana Lifespace LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.