Commercial Project Andheri

by Havemore Realty Private Limited · Gundavali Andheri East, MumbaiAlso near Andheri Railway Station, Chakala MIDC, Jogeshwari East

Possession date of Commercial Project Andheri: 30 June 2029, moved from 30 June 2026 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800031752, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Commercial Project Andheri?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Commercial Project Andheri has moved

  1. 30 June 2026

    Completion date given when the project was registered

  2. 30 June 2029

    Extended at the builder's request (MahaRERA application EA29052621155)

    Reason the builder gave MahaRERA:
    “Due to management decisions and planning, there was a delay in “Commercial Project Andheri ” launching the project even after obtaining the RERA number, which resulted in a late start of construction work. As of Now , at the time of extensi…” Read the full reason“Due to management decisions and planning, there was a delay in “Commercial Project Andheri ” launching the project even after obtaining the RERA number, which resulted in a late start of construction work. As of Now , at the time of extension request with allotees Consent in this project”

Source: Commercial Project Andheri’s extension records on MahaRERA (P51800031752), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Commercial Project Andheri

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 8 court cases, and how it ended
  • Construction pace against the June 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800031752
Status
Registered and active
Builder
Havemore Realty Private Limited
Location
Gundavali Andheri East, Mumbai · 400069
Project type
Commercial
Registered on
8 Nov 2021
Completion date at registration
June 2026
Latest completion date
June 2029
Delay so far
36 months
Homes
0
Sold or booked
79%
Towers
1
Complaints on MahaRERA
0
Court cases listed
8
Title report on file
Not found

Construction progress of Commercial Project Andheri, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Commercial Project Andheri41%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Commercial Project Andheri: covers 11 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Commercial Project Andheri every month.

Commercial Project Andheri: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Shops1,680 – 11,00034
  • Buildings: Commercial Project Andheri (18 floors, 34 units)
  • Land: 3,757 sq m (about 0.9 acres) · sanctioned built-up 29,857 sq m · recreational space 715 sq m
  • Boundaries filed include: Western Express Highway

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Commercial Project Andheri →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Commercial Project Andheri: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Commercial Project Andheri

What is the possession date of Commercial Project Andheri?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Commercial Project Andheri in Gundavali Andheri East, Mumbai is 30 June 2029 — 36 months later than 30 June 2026, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Commercial Project Andheri?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Commercial Project Andheri's builder has filed on MahaRERA, the official one, is 30 June 2029, already 36 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Commercial Project Andheri extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Commercial Project Andheri's builder applied to MahaRERA to extend the completion date once: to 30 June 2029, giving the reason "Due to management decisions and planning, there was a delay in “Commercial Project Andheri ” launching the project even after obtaining the RERA number, which resulted in a late start of construction work. As of Now , at the time of extension request with allotees Consent in this project".

What is the RERA number of Commercial Project Andheri?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Commercial Project Andheri in Gundavali Andheri East, Mumbai is P51800031752.

Is Commercial Project Andheri registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Commercial Project Andheri is registered as P51800031752 and its status is "Registered and active".

What is the construction status of Commercial Project Andheri?

According to GharKundli's check of MahaRERA records (updated October 2026), Commercial Project Andheri's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Commercial Project Andheri is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Commercial Project Andheri have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Commercial Project Andheri safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Commercial Project Andheri is registered on MahaRERA as P51800031752, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Commercial Project Andheri's possession date changes?

The latest dates are on Commercial Project Andheri's MahaRERA page (P51800031752). GharKundli's Kundli Watch sends a free WhatsApp update on Commercial Project Andheri every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Commercial Project Andheri have?

According to GharKundli's check of MahaRERA records (updated October 2026), Commercial Project Andheri has one building filed: Commercial Project Andheri with 18 floors and 34 units.

How big is the land of Commercial Project Andheri?

According to GharKundli's check of MahaRERA records (updated October 2026), Commercial Project Andheri stands on 3,757 sq m of land (about 0.9 acres), with 29,857 sq m of sanctioned built-up area and 715 sq m of recreational open space.

Where can I read reviews of Commercial Project Andheri?

Google Maps has reviews of Commercial Project Andheri written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Commercial Project Andheri?

Commercial Project Andheri by Havemore Realty Private Limited is in Gundavali Andheri East, Mumbai (pincode 400069), near Andheri Railway Station, Chakala MIDC, Jogeshwari East, Maharashtra, and is registered on MahaRERA as P51800031752, per GharKundli's check of MahaRERA records. Its boundaries filed there include Western Express Highway.

How many homes are in Commercial Project Andheri?

According to GharKundli's check of MahaRERA records (updated October 2026), Commercial Project Andheri has 0 homes in 1 tower registered on MahaRERA, and 79% of them are sold or booked.

When was Commercial Project Andheri registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Commercial Project Andheri was registered on MahaRERA on 8 November 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on Commercial Project Andheri?

8 court cases are listed for Commercial Project Andheri on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Commercial Project Andheri?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Havemore Realty Private Limited.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in pincode 400069

All 96 projects in Andheri East (400069) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.