DOTOM ISLE-SHAKTI
by M/S. DOTOM REAL ESTATE · Malad West, MumbaiAlso near Kharodi, Kandivali West
Possession date of DOTOM ISLE-SHAKTI: 30 June 2025, moved from 31 December 2024 (6 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800031765. Status: Lapsed (registration period ended). 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (June 2025) has passed.
What do you want to know about DOTOM ISLE-SHAKTI?
GharKundli’s full report on DOTOM ISLE-SHAKTI
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the June 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800031765
- Status
- Lapsed (registration period ended)
- Builder
- M/S. DOTOM REAL ESTATE
- Location
- Malad West, Mumbai · 400095
- Project type
- Residential / Group Housing
- Registered on
- 9 Nov 2021
- Completion date at registration
- December 2024
- Latest completion date
- June 2025
- Delay so far
- 6 months
- Homes
- 109
- Sold or booked
- 95%
- Towers
- 1
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of DOTOM ISLE-SHAKTI, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| CORAL | 100% | 100% | 85% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- CORAL: covers C.C. is re-endorsed as per approved amended plans dtd. 02/05/2023.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on DOTOM ISLE-SHAKTI every month.
DOTOM ISLE-SHAKTI: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 717 – 772 | 55 |
| 1 BHK | 377 – 398 | 35 |
| 3 BHK | 984 | 19 |
| Shops | 199 – 477 | 16 |
- Buildings: CORAL (29 floors, 125 units)
- Land: 23,122 sq m (about 5.7 acres) · sanctioned built-up 64,163 sq m
- Boundaries filed include: LAYOUT ROAD
The builder’s record and reviews
Dotom Real Estate (a group of 5 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 6 months); 5 still being built, none past the promised date yet; 1 lapsed. 23 complaints on MahaRERA across 3 projects.
Read Google reviews of DOTOM ISLE-SHAKTI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
DOTOM ISLE-SHAKTI: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about DOTOM ISLE-SHAKTI
What is the possession date of DOTOM ISLE-SHAKTI?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DOTOM ISLE-SHAKTI in Malad West, Mumbai is 30 June 2025 — 6 months later than 31 December 2024, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for DOTOM ISLE-SHAKTI?
Builders and listing sites often quote an earlier "target" date for handover. The completion date DOTOM ISLE-SHAKTI's builder has filed on MahaRERA, the official one, is 30 June 2025, already 6 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of DOTOM ISLE-SHAKTI?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DOTOM ISLE-SHAKTI in Malad West, Mumbai is P51800031765.
Is DOTOM ISLE-SHAKTI registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DOTOM ISLE-SHAKTI is registered as P51800031765 and its status is "Lapsed (registration period ended)".
What is the construction status of DOTOM ISLE-SHAKTI?
According to GharKundli's check of MahaRERA records (updated October 2026), DOTOM ISLE-SHAKTI's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on CORAL is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.
Does DOTOM ISLE-SHAKTI have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is DOTOM ISLE-SHAKTI safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), DOTOM ISLE-SHAKTI is registered on MahaRERA as P51800031765, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 6 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if DOTOM ISLE-SHAKTI's possession date changes?
The latest dates are on DOTOM ISLE-SHAKTI's MahaRERA page (P51800031765). GharKundli's Kundli Watch sends a free WhatsApp update on DOTOM ISLE-SHAKTI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does DOTOM ISLE-SHAKTI have?
According to GharKundli's check of MahaRERA records (updated October 2026), DOTOM ISLE-SHAKTI has one building filed: CORAL with 29 floors and 125 units.
What are the flat sizes (carpet area) in DOTOM ISLE-SHAKTI?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for DOTOM ISLE-SHAKTI: 2 BHK: 717 to 772 sq ft carpet (55 homes); 1 BHK: 377 to 398 sq ft carpet (35 homes); 3 BHK: 984 sq ft carpet (19 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of DOTOM ISLE-SHAKTI?
According to GharKundli's check of MahaRERA records (updated October 2026), DOTOM ISLE-SHAKTI stands on 23,122 sq m of land (about 5.7 acres), with 64,163 sq m of sanctioned built-up area.
What is the track record of DOTOM ISLE-SHAKTI's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Dotom Real Estate (a group of 5 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 6 months); 5 still being built, none past the promised date yet; 1 lapsed. 23 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of DOTOM ISLE-SHAKTI?
Google Maps has reviews of DOTOM ISLE-SHAKTI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is DOTOM ISLE-SHAKTI?
DOTOM ISLE-SHAKTI by M/S. DOTOM REAL ESTATE is in Malad West, Mumbai (pincode 400095), near Kharodi, Kandivali West, Maharashtra, and is registered on MahaRERA as P51800031765, per GharKundli's check of MahaRERA records. Its boundaries filed there include LAYOUT ROAD.
How many homes are in DOTOM ISLE-SHAKTI?
According to GharKundli's check of MahaRERA records (updated October 2026), DOTOM ISLE-SHAKTI has 109 homes in 1 tower registered on MahaRERA, and 95% of them are sold or booked.
When was DOTOM ISLE-SHAKTI registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DOTOM ISLE-SHAKTI was registered on MahaRERA on 9 November 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on DOTOM ISLE-SHAKTI?
No court cases are listed for DOTOM ISLE-SHAKTI on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of DOTOM ISLE-SHAKTI?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S. DOTOM REAL ESTATE, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of DOTOM ISLE-SHAKTI
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data