Possession date of SPRINGWOODS: 30 April 2027, moved from 1 March 2025 (21 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800032668, and currently active. Its completion date has moved from March 2025 to April 2027: 21 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SPRINGWOODS?
How the possession date of SPRINGWOODS has moved
1 March 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EXT51800025129)
Reason the builder gave MahaRERA:
“We Would like to request you that the Project SPRINGWOODS BY PRATIK CONSTRUCTION which is located at land bearing C.T.S No.163A (pt) & 166 (pt) of Village Akurli, Taluka Borivali, situated at Wardarpada Road No.1, Kandivali (East), Mumbai.…” Read the full reason
“We Would like to request you that the Project SPRINGWOODS BY PRATIK CONSTRUCTION which is located at land bearing C.T.S No.163A (pt) & 166 (pt) of Village Akurli, Taluka Borivali, situated at Wardarpada Road No.1, Kandivali (East), Mumbai. 400101, having its Registration No.P51800032668 was mentioned to be completed on 1st March 2025. 1. Due to pollution control order which stated to do additional compliances like 35 feet tall patra wall, covering 14 floor building with green cloth (due to which external plaster work not possible) and storage of material in enclosed room etc delayed the wor…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SPRINGWOODS’s extension records on MahaRERA (P51800032668), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SPRINGWOODS
Ready · November 2026 · 62 filings read
- Risk & trust score, every point explained
- What the title report on MahaRERA says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800032668
- Status
- Registered and active
- Builder
- PRATIK CONSTRUCTION
- Location
- Kandivali East, Mumbai · 400101
- Project type
- Residential / Group Housing
- Registered on
- 17 Jan 2022
- Completion date at registration
- March 2025
- Latest completion date
- April 2027
- Delay so far
- 21 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 611
- Sold or booked
- 46%
- Towers
- 1
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- Title report on file
- Yes
- Latest construction certificate
- 22 Apr 2026
Construction progress of SPRINGWOODS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SPRINGWOODS | 100% | 92% | 0% | 34% |
Commencement certificate (CC), as filed on MahaRERA
- SPRINGWOODS: covers 23RD UPPER FLOORS
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SPRINGWOODS every month.
SPRINGWOODS: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 159 – 620 | 538 |
| 2 BHK | 620 | 44 |
| 1 Room Kitchen | 214 – 365 | 23 |
| Shops | 150 – 272 | 6 |
- Buildings: SPRINGWOODS (24 floors, 611 units)
- Land: 3,380 sq m (about 0.8 acres) · sanctioned built-up 8,475 sq m · recreational space 270 sq m
- Boundaries filed include: WADAR PADA ROAD
The builder’s record and reviews
Samarth Erectors & Developers (a group of 2 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 3 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 16 months late); 1 lapsed. 5 complaints on MahaRERA across 2 projects.
Read Google reviews of SPRINGWOODS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SPRINGWOODS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SPRINGWOODS
What is the possession date of SPRINGWOODS?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SPRINGWOODS in Kandivali East, Mumbai is 30 April 2027 — 21 months later than 1 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SPRINGWOODS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SPRINGWOODS's builder has filed on MahaRERA, the official one, is 30 April 2027, already 21 months later than the 1 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SPRINGWOODS extended?
According to GharKundli's check of MahaRERA records (updated November 2026), SPRINGWOODS's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "We Would like to request you that the Project SPRINGWOODS BY PRATIK CONSTRUCTION which is located at land bearing C.T.S No.163A (pt) & 166 (pt) of Village Akurli, Taluka Borivali, situated at Wardarpada Road No.1, Kandivali (East), Mumbai. 400101, having its Registration No.P51800032668 was mentioned to be completed on 1st March 2025. 1. Due to pollution control order which stated to do additional compliances like 35 feet tall patra wall, covering 14 floor building with green cloth (due to which external plaster work not possible) and storage of material in enclosed room etc delayed the wor…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SPRINGWOODS?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SPRINGWOODS in Kandivali East, Mumbai is P51800032668.
Is SPRINGWOODS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SPRINGWOODS is registered as P51800032668 and its status is "Registered and active".
What is the construction status of SPRINGWOODS?
According to GharKundli's check of MahaRERA records (updated November 2026), SPRINGWOODS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SPRINGWOODS is 92% done and internal work 0%. The latest construction certificate the builder filed there is dated 22 April 2026. GharKundli's full report compares construction progress with the deadline.
Does SPRINGWOODS have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SPRINGWOODS safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SPRINGWOODS is registered on MahaRERA as P51800032668, its completion date has moved 21 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SPRINGWOODS's possession date changes?
The latest dates are on SPRINGWOODS's MahaRERA page (P51800032668). GharKundli's Kundli Watch sends a free WhatsApp update on SPRINGWOODS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SPRINGWOODS have?
According to GharKundli's check of MahaRERA records (updated November 2026), SPRINGWOODS has one building filed: SPRINGWOODS with 24 floors and 611 units.
What are the flat sizes (carpet area) in SPRINGWOODS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed these homes for SPRINGWOODS: 1 BHK: 159 to 620 sq ft carpet (538 homes); 2 BHK: 620 sq ft carpet (44 homes); 1 Room Kitchen: 214 to 365 sq ft carpet (23 homes); Shops: 150 to 272 sq ft carpet (6 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of SPRINGWOODS?
According to GharKundli's check of MahaRERA records (updated November 2026), SPRINGWOODS stands on 3,380 sq m of land (about 0.8 acres), with 8,475 sq m of sanctioned built-up area and 270 sq m of recreational open space.
What is the track record of SPRINGWOODS's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Samarth Erectors & Developers (a group of 2 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 3 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 16 months late); 1 lapsed. 5 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SPRINGWOODS?
Google Maps has reviews of SPRINGWOODS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SPRINGWOODS?
SPRINGWOODS by PRATIK CONSTRUCTION is in Kandivali East, Mumbai (pincode 400101), Maharashtra, and is registered on MahaRERA as P51800032668, per GharKundli's check of MahaRERA records. Its boundaries filed there include WADAR PADA ROAD.
How many homes are in SPRINGWOODS?
According to GharKundli's check of MahaRERA records (updated November 2026), SPRINGWOODS has 611 homes in 1 tower registered on MahaRERA, and 46% of them are sold or booked.
When was SPRINGWOODS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SPRINGWOODS was registered on MahaRERA on 17 January 2022. A title report on the land is on file there.
Are there court cases on SPRINGWOODS?
No court cases are listed for SPRINGWOODS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SPRINGWOODS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PRATIK CONSTRUCTION.
Check it yourself on MahaRERA
- How to check the possession date of SPRINGWOODS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400101
- AJMERA ICONIC
- Aurigae Residency D Wing
- SIENNAA WING F
- UK LUXECITY - E - F
- 101 BOULEVARD
- SWAYAMBHU CO-OP. HSG. SOC. LTD.
- VEDA
- AVASA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.